BLD20070978-1.pdf
City of Edmonds
TH
121 5 AVENUE NORTH EDMONDS, WA 98020 (425) 771-0220 FAX(425) 771-0221
Website: www.ci.edmonds.wa.us
DEVELOPMENT SERVICES DEPARTMENT
Planning Building Engineering
Plan Review Corrections
Plan Check : Date:
# BLD 2007-0978 November 14, 2007
Project Name/Address:
Harvey / SFR and DEMO 1240 Birch St.
Contact Person/Address/Fax:
Tom Leren/Phone: 425-776-6007/Fax: 425-771-8401/e-mail:
tom@lerendesign.com
Reviewer: Jaime HawkinsDivision:Engineering
During review of the subject submittal, it was found that the following information, corrections, or
clarifications would need to be addressed:
1.Please show all the existing/proposed utilities in the site plan and in sheet C1 of 1. Water meter, water
service line (from the meter to the house), side sewer, power, gas, etc.
2.Is the existing water meter to remain at its present location or is it to be relocated. Please show existing
and proposed location if applicable. This property is serviced by the OVWSD, water only.
3.Do you plan to use the existing sewer lateral? If so, verification of the laterals condition is to be done by
the City of Edmonds sewer department. Please contact Tim Harris at 425-771-0235 to schedule an
inspection. This inspection is preferably done at the time of the sewer cap prior to the demo of the
existing home. If the lateral is deemed unusable then, you shall install a new lateral per City of Edmonds
standard E6.4. Please add this comment in sheet C1 of 1, only.
4.With the installation of the new side sewer, a 6-in clean with 12-in cast iron locking lid shall be installed
at the property line per E6.2. Please add this call out on both the site plan and sheet C1 of 1.
5.Show the sewer extension and clean out for the drainage of the proposed swimming pool in both the site
plan and sheet C1 of 1.
6.Show the proposed external shower connecting to the side sewer. Both the site plan and sheet C1 of 1
7.Show the pools patio drainage connecting to the pools strip drain and the strip drain connecting to the
side sewer. Sheet C1 of 1, only.
8.Construction Sequence #9. Please revise section in parenthesis . (Contact the Olympic View Water
and Sewer District for sewer inspections .) The City of Edmonds is responsible for both the water and
sewer inspections.
9.Provide a breakdown of the proposed Impervious Surface in both the site plan and sheet C1 of 1.
10.Please add a call out to CB #3 to say Vane Grate
DATE FAXED/E-MAILED 11/14/2007
11.CB #1 is missing an invert elevation.
12.The proposed 12-in storm drain line between CB #2 and CB #1, and between CB #1 and existing cb
shall have at a minimum 2-ft of cover. If the required cover is not met, then, 12-in iron shall be required.
13.Show all piping between pool equipment shed and pool on the site plan and sheet C1 of 1.
Please submit resubmission to your permit coordinator. You may resubmit by fax: 425-771-0221. Please
contact me at 425-771-0220 if you have specific questions regarding these plan corrections.
DATE FAXED/E-MAILED 11/14/2007