BLD20080182[,IIII1lIII_ 'ew&9„kftef2
'I
ITi1 HWA GEOSCIENCES INC.
GeotechnicaI & Pavement Engineering • Nydrogeo.logy • Geoenvironmental • Planning e; Permitting • Inspection & Testing
August 6, 2010
HWA Project No. 2006-171-21
City of Edmonds
121 Fifth Avenue North
Edmonds, Washington 98020
Attention: Mr. Jaime Hawkins
RECEIVED
AUG 0 g 20t0
ENGINEERING DIVISION
Subject: CONSTRUCTION QUALITY ASSURANCE INSPECTION AND TESTING SERVICES
76th Avenue W / 75th Place Walkway and 162"d Street SW Project
Edmonds, Washington
Dear Jaime:
As requested, HWA GeoSciences Inc. (HWA) provided construction observation, inspection and
testing services for the 76th Ave W/75th Place Walkway and 162"d St SW Project, in Edmonds,
Washington. These services were provided in accordance with our proposal dated February 17,
2009 and supplement dated February 8, 2010, and consisted of both periodic and continuous
construction monitoring and site inspection during various construction stages of the subject
project.
This report summarizes the results of HWA's monitoring and testing during construction of
various components of the project falling within our work scope. Our daily field inspection
reports and geotechnical engineering laboratory test results are compiled in the attached
Appendices A and B, respectively. Portland Cement Concrete (PCC) and Hot Mix Asphalt
(HMA) laboratory test results, which include determination of binder content, aggregate size
distribution and maximum theoretical density (Rice Density), are compiled in the attached
Appendices C and D, respectively.
PROJECT DESCRIPTION AND HWA WORK SCOPE
The approximate project location is shown on the Vicinity Map (Figure 1). The project included
construction of retaining walls (soldier pile walls, rockeries, gravity block and modular block
walls) and curb and gutter installation along 761h Avenue W and 75th Place; and a new park at
162d Street SW, with an elevated walkway along 75th Place.
' HWA provided construction observation and testing services on the project starting on August 8,
2009. That work consisted of providing full-time and part-time construction 21312 30th Drive SE
monitoringand inspection of rebar and concrete placement, Suite 110
p p ,grading and trench Bothell, WA 98021.7010
backfill construction. Inspection and monitoring was provided during the
Tel: 425.774.0106
Fax: 425.774.2714
' www.hwageo.com
i
August 6, 2010
HWA Project No. 2006-171-21
installation of retaining walls and for pin piles for the elevated sidewalk. Our work also included
compaction testing and inspection of native soils, crushed surfacing base course (CSBC), crushed
surfacing top course (CSTC), and Hot Mix Asphalt (HMA) Class '/2" asphalt paving. The last visit by
HWA personnel to the work site was on July 15, 2010.
HMA Placement and Compaction
HMA Class'/2" mix was used for paving surfaces in the park and along the street. The mix
originated from the CEMEX asphalt plants in Everett and Kenmore, Washington. All HMA
sampling and laboratory testing were performed by HWA. Laboratory testing consisted of
determination of binder content, aggregate size distribution and maximum theoretical density
(Rice Density). HWA's laboratory provided field personnel with the results of the maximum
theoretical density (Rice Density) for use during the paving operations and for field reports.
Continuous observation and testing were provided during the asphalt paving operations.
Welding
Welding of the elevated sidewalk panels to pin piles was inspected by HWA personnel and
inspected to AWS D1.1 Code and job site specifications.
Portland Cement Concrete
Six concrete design mixes; (#1189027) 3000-psi strength compressive design from CEMEX
p � g
(#M20120) 1,000-psi compressive strength design from Salmon Bay Sand and Gravel, (#3136
and #1997) 3,000-psi compressive strength design from Cal Portland, (#3717) 4,000-psi
compressive strength design from Glacier and (#1517) 5,000-psi compressive strength design
from CEMEX were used for the different phases of this project. Mix designated M20120 (CDF)
failed to meet the 1,000-psi as initially required however, the engineer waived the 1,000-psi and
replaced it with a 300-psi requirement.
As required, an HWA inspector tested fresh PCC mixes and monitored their placement. PCC
sampling was conducted in general accordance with ASTM C 172. Slump, temperature and air
' content parameters were measured in the field in general accordance with ASTM C 143, C 1064
and C 231, respectively. Four -inch diameter by eight -inch long cylindrical specimens and Six-
inch diameter by twelve -inch long cylindrical specimens were cast per ASTM C 31. Test
specimens were placed in insulated boxes, which remained on -site usually for 24 hours until
being transported to HWA's laboratory for further curing and compressive strength testing. The
' results of these tests are included in Appendix C. All tested PCC mixes met the requirements set
by the specifications of the project, as indicated in the test reports.
Other Material Laboratory Testing
In addition to the testing outlined in the previous paragraphs, representative aggregate samples
were obtained from Aggregate suppliers and returned to HWA's laboratory for further
' Inspection Final Report 2 HWA GeoSciences Inc.
I
August 6, 2010
HWA Project No. 2006-171-21
examination and testing. Laboratory tests were conducted on the selected aggregate samples to
characterize relevant physical properties, including grain size distribution, moisture -density
' relationship (Modified Proctor), sand equivalent and/or fracture face count.
The results of all material laboratory tests are summarized and attached in Appendix B of this
' report.
OUTSTANDING ISSUES
tAll identified issues were resolved by the end of the project with the exception of under -
compacted Hot Mix Asphalt pavement placement as described in Field Report FR-066. Our field
reports are attached in Appendix A and Field Report FR-066 shows the only outstanding issue
being un-resolved. There are no other outstanding issues that HWA is aware of.
Based on HWA's observations and the results of the testing reported herein, it is our conclusion
that the different components of construction observed during the various stages of construction
along 76t'' Ave W/75t" Place and on 162°d St SW Project in Edmonds, Washington, were carried
out in general compliance with the drawings and project specifications.
CONDITIONS AND LIMITATIONS
Our construction observations and tests on subgrade, aggregate, HMA pavement, PCC, Welded
' connections, construction of various retaining walls as described in this report, are based on
periodic and/or continuous services as required during construction. All special inspections were
monitored and performed by certified inspectors as necessary. The compressive strength results
of PCC cylinders reported are specific to the cylinder specimens prepared and are dependent on
many variables such as specimen density and method of densification employed. The
compaction testing results reported for aggregate and HMA pavement are dependent upon the
equipment and placement/compaction methods used, weather conditions, and specific locations
tested. Experience has shown aggregate and HMA compaction conditions can vary significantly
over small distances.
References to elevations and locations of tests herein are based on grade checker's stakes in the
field and/or interpolation from project plans. HWA did not provide surveying services and,
therefore, cannot comment upon the accuracy/appropriateness of the as -graded elevations or
surface geometry with respect to the project plans.
Our conclusions and opinions as to whether the work essentially complies with the job
specifications are based on our observations and test results, and on our general experience. The
conclusions presented herein apply only to our work with respect to the specific phases of the
project, and represent conditions at the end of our final observation during construction on July
Inspection Final Report 3 HWA GeoSciences Inc.
1
August 6, 2010
HWA Project No. 2006-171-21
15, 2010. We cannot provide advice, opinions or speculate on site conditions relative to wo
that we have not observed.
Within the limitations of scope, schedule and budget, HWA attempted to provide construction -
monitoring and testing services in accordance with generally accepted professional principles and
practices in this field.
HWA does not practice or consult in the field of safety engineering. We did not direct the
contractor's operations, and cannot be held responsible for the safety of field personnel other
than our own on the site. As such, the safety of others was the responsibility of the contractor.
We trust that the foregoing summary of our inspection services meets with your requirements and
' we appreciate the opportunity to have been of service to you on this project. Should you have
any questions, or if we may be of additional service, please call at your convenience.
Sincerely,
HWA GEOSCIENCES INC.
Tony Martin
Manager, Construction Inspection Services
TMM:LAB:tmm
Ralph Boirum, P.E.
Geotechnical Engineer, Principal
■ Attachments:
• Appendix A: Daily Field Inspection Reports
• Appendix B: Geotechnical Engineering Laboratory Results
• Appendix C: Portland Cement Concrete Results
• Appendix D: Hot Mix Asphaltic (HMA) Pavement Testing Results
Inspection Final Report 4 HWA GeoSciences Inc.
C
I�
LJ
■ APPENDIX A
DAILY FIELD INSPECTION REPORTS
r
r
19730-64th Avenue West, Suite 200
U 1 '1 '`�_, Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-001
Date (mm/dd/yy):
8/11/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit:No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Mild
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Eric S. Worth
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 11:05 Arrived at Site: 11:15 Departed Site: 1320 End Travel: 1315
ACTIVITY BEING INSPECTED: Controlled Density Fill (CDF) delivery and placement.
ITEM BEING CONSTRUCTED: Wall 1 Soldier Piles.
' TYPE OF INSPECTION: Periodic.
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: The CDF was being placed by pump truck.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's 'Field and Laboratory Concrete Test Report'
for Set CDF-1 for a summary of inspection and test data.
' CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
' MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: I received verbal confirmation from Jaime
Hawkins with the City of Edmonds that the supplied mix (Salmon Bay Sand And Gravel Mix ID M15120) was the mix
approved by the city.
Total time charged to the job for this visit is 2.5 hours including report writing.
SIGNATURES:
Signed: Reviewed:
' HWA Field senta ' HWA Project Engineer or
' SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
na na There are no outstanding issues at this time.
IF]
' This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
19730-64th Avenue West, Suite 200
.�j 1Q�• ;
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC.
Fax.425-774-2714
Field Report No.:
Date (mm/dd/yy): '
FR-002
'
8/12/2009
HWA Project No.:
-
2006-171 21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Partly Cloudy/Mild
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Eric S Worth
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 0735 Arrived at Site: 0745 Departed Site: 0755 End Travel: 0805
Second Site Visit: Start Travel: 1005 Arrived at Site: 1015 Departed Site: 1115 End Travel: 1125
ACTIVITY BEING INSPECTED: Controlled Density Fill (CDF) delivery and placement.
ITEM BEING CONSTRUCTED: Wall 1 Soldier Piles
TYPE OF INSPECTION: Periodic.
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: The CDF was being placed by pump truck.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's'Field and Laboratory Concrete Test Report'
for Set CDF-2 for a summary of inspection and test data.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: The test cylinders cast on 8/11/2009
(designated CDF-1) were collected and transported to HWA's Lynnwood laboratory. '
Total time charged to the job for this visit is 3.0 hours including report writing.
SIGNATURES: '
Signed: Reviewed: --51
-
HWA Fie( epr e HWA Project Engineer or ,evie re-�
SUMMARY OF UNRESOLVED ISSUES '
Report# Item# Status
na na There are no outstanding issues at this time.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1 ,.
19730-64th Avenue West, Suite 200
i� Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
t
Field Report No.:
FR-003
Date (mm/dd/yy):
8/13/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Partly Cloudy/Mild
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Eric S Worth
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 0535 Arrived at Site: 0740 Departed Site: 0745 End Travel: 0755
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: HWA was on site to collect the test cylinders
cast on 8/12/2009 (designated CDF-2) and transport them to HWA's Lynnwood laboratory.
' Total time charged to the job for this visit is 0.5 hours including report writing.
SIGNATURES:
Signed: '4� 'r'e i d' Reviewed:
HWA I`epres tative HWA Project Engineer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
' na na There are no outstanding issues at this time.
' This report should only be reproduced in its entirety. Report is not final until signed.by HWA field representative and HWA reviewer. Page 1 of 1
11
19730-64th Avenue West, Suite 200
ff1WLynnwood, WA 98036
n� 7 c INC.
Tel. 425-774-0106
HWAGECISCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-004
Date (mmldd/yy):
8/2712009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Sunny/Warm
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Jessica Herrera
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 0750 Arrived at Site: 0805 Departed Site: 0915 End Travel: 0925
ACTIVITY BEING INSPECTED: CDF delivery and placement.
ITEM BEING CONSTRUCTED: Soldier Piles.
DETAILED LOCATION: Wall 4, Piles 15,17 and 19.
TYPE OF INSPECTION: Periodic
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: The CDF was being placed using a TK40 putzmeister pump.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's'Field and Laboratory Concrete Test Report'
for Set CDF-3 for a summary of inspection and test data.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the.exception of any non-conformance items list below.
Item 1 - Slump exceeded the specified maximum.for this mix.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
Based on information provided by the concrete truck driver, the contractor and the batch plant operator said the slump
exceeded the maximum because more than the allowable amount of water was added at the jobsite. The contractor
indicated that he had been adding more water because the CDF was too thick to go through the pump. Tony Martin of
HWA informed Jaime Hawkins with the city of Edmonds of this occurrence. The contractor agreed to add only the
amount of water allowed for future loads but no satisfactory resolution has been reached regarding the CDF already
poured.
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURES:
Signe : ICA-
HWA Fiel R rese #ative
Reviewed: r '%"
HWA Project Engineer or
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
04 01 Unresolved - Slump exceeded the specified maximum for this mix.
0
E
1
r
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
19730-64th Avenue West, suite 200 Field Report No.: FR-005
, Lynnwood, WA 98036 Date (mm/dd/yy): 8/28/2009
Tel.425-774-0106 HWA Project No.: 2006-171-21
HWAGEOSCIENCES INC. Fax.425-774-2714 HWA Task No.: 400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Sunny/Warm
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Jessica Herrera
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 0730 Arrived at Site: 0740 Departed Site: 0750 End Travel: 0800
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
A site visit was made to obtain CDF cylinder set CDF-3 cast on 8/27/09. Upon arrival I immediately noticed that the
cooler containing the cylinders had been moved from its original position. The cylinders were transported to our office
in Lynnwood for testing.
Total time charged to the job for this visit is 0.5 hours including report writing.
SIGNATURES:
s 7
Signed:
HWA Fi Representati
7'x-�--�
42��
Reviewed:
HWA Project Engineer or Revi
SUMMARY OF UNRESOLVED ISSUES
Report# Item# . Status
04 01 Unresolved - Slump exceeded the specified maximum for this mix.
This report should only be reproduced in its entirety. Report is riot final until signed by HWA field representative and HWA reviewer. Page 1 of 1
HWAGEOSCIENCES INC.
. . ULWI I
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
Fax. 425-774-2714
Field Report No.:
FR-006
Date (mm/dI fty):
10/30/2009 '
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
ClientClient
Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Alix Rackleff
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 0830 Arrived at Site: 0840 Departed Site: 1120 End Travel: 1130
Glacier Visit: Start Travel: 1230 Arrived at Site: 1300 Departed Site: 1320 End Travel: 1340
ACTIVITY BEING INSPECTED: Concrete delivery and placement.
ITEM BEING CONSTRUCTED: Driveways.
DETAILED LOCATION: Right of Center Line on 76th Ave.
TYPE OF INSPECTION: Periodic.
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: The concrete was being placed by tail -gating -
No consolidation was observed.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's 'Field and Laboratory Concrete Test Report'
for Set C-1 for a summary of inspection and test data.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
At the time of my arrival the contractor had placed and compacted 2" of CSTC in the Driveway at address 16411. 1
observed placement and compaction of 2" of CSTC in driveways at addresses 16429, 16711, 16717, and
Sta: 15+90. Physical evaluation using a 1/2" steel T-handled probe indicated the CSTC to be dense and well
compacted in the driveways.
At the request of Jaime Hawkins a visit was made to Glacier aggregate pit in Kenmore to obtain samples of CSTC and
CSBC for acceptance testing.
Total time charged to the job for this visit is 5.0 hours including report writing.
SIGNATURES:
Sig ne
HWA el epr sentative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
Y
Reviewed:�—
HWA Project Engineer or Review
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1 '
1
1
1
1
1
1
1
1
1
1
1
1
1
1
�..�
19730-64th Avenue West, Suite 200
ur
Lynnwood, WA 98036
Tel. 425-774-0106
I-IWVAGEOSCIENCES INC.
Fax.425-774-2714
Field Report No.:
FR-007
Date (mm/dd/yy):
10131/2009
HWA Project No.:
'2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Alix Rackleff
FIELD (REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 1200 Arrived at Site: 1210 Departed Site: 1220 End Travel: 1230
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
A site visit was made to obtain cylinder set C-1 cast on 10/30/09. The cylinders were transported to our office in
Lynnwood for testing.
Total time charged to the job for this visit is 1.0 hours including report writing.
n I
SIGNATURES:
Signed:
HWA Fiel epresen ative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
Reviewed: / V
HWA Project Engineer or Reviewer
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
1
19730-64th Avenue West, Suite 200
1 �► rC��, Lynnwood, WA 98036
T L T Tel.425-774-0106
1 l V VAGEOSCIEiV CES INC. Fax. 425-774-2714
Field Report No.:
FR-008
Date (mm/dd/yy):
11/23/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
I Brian Coker .
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 0900 Arrived at Site: 0915 Departed Site: 1600 End Travel: 1630
ACTIVITY BEING INSPECTED: Concrete delivery and placement.
ITEM BEING CONSTRUCTED: Elevated Sidewalk footing and wall.
DETAILED LOCATION: West side of 75th Ave West between stations 32+00 and 34+50.
TYPE OF INSPECTION: Periodic.
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: The concrete was being placed by tail -gating and concrete
was mechanically vibrated.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's 'Field and Laboratory Concrete Test Report'
for Sets C-2 and C-3 for a summary of inspection and test data.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
-Total yardage of concrete for this pour was 57.5 yards.
-Contractor chose to use 5000 psi mix ( Mix Design No. 1517) instead of specified minimum 4000 psi. See attached
sheets.
-Total time charged to the job for this visit is 7.0 hours including report writing.
SIGNATURES:
Signed: Reviewed:
HWA Field Representative HWA Project Engineer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
1
u
u
1
1
0
u
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1 11
1
1
1
1
1
1
1
1
1
1
1
i
1
1
1
1
1
1
i
11/20/2009 19:13 3606541840
$Elk
FWashilncdton State
Dep}artnient of Transportation
NTN CONSTRUCTION INC
PAGE 02/03
Concrete Mix Desigi
Contractor Submitted By Date
NTN 111120/2009 '
Concrete Supplier Plant Location
CalPoitland Everett
Contract Number Contract Name
176th Ave West Improvements, Edmonds
This mix is to be used in the following Bid Item No(s):
Concrete Class: (check one only)
❑ 3000 ❑ 4000 ❑ 4000D a ❑ 4000P a. ❑ 4000W ❑ Concrete Overlay Cement Concrete Pavement d
0 Other Class 5000 wt Air
Remarks; MAX SLUMP = 5.5'
Mix Design No. 1517 Plant No. 261
Cementitious Materials
Source
Type, Class, or Grade
Sp. Gr.
I-bslcy
Cement
Nan'in-
Type 1-11
3.15
660
Fly -Ash a
Headwaters/ENX
--
2.20
131
GGBFS
Latex
Microsilioa
—
-
Concrete Admixtures
Manufacturer
Product
Type
ESt. Range
Q21C
Air Entrainment
W.R. Grace
Deravair
s
A -Water Reducer
.5 - 75
water Reducer
W.R. Grace
WRDA 64
5 - 35
High -Range Water Reducer
W.R. Grace
ADVA 190
F-MRWR min 12
Set Retarder
Master Builders BASF
Pozzolith 100XR
IB-Retarder
0 - 15
Other
--
Water (Maximum) 240 (lbs/cy) Is any of the water Recycled or Reclaimed? Yes` ❑ No
Water/Cementitious Ratio (Maximum) 0.30 Mix Design Density: 147 lbs/Of
Design Performance
1
2
3
4
5
Average'
28 Day Compressive Strength
7265
6240
6210
8205
6095
6,803
(c tinders si
14 Day Flexural
r-
Agancy uac only: Check appropriate box
This mix design Meats Contract Specifications and may be used on the bid items noted above.
This mix design Does Not Meet Contract Specifications and is being returned for corrections.
Reviewed By: (PC 5igneture) (Data)
Q _ Forrn S50.Ge0 EF
Revised i.:2G13
t7lsirlt.*110n: prigin.01- C:%��rL'e�CfOt
Q0riiA-. To - Rtlip htet5rint,111T-Ggtisra! McOria!- E:lg ': Regional Nnteria13 Lab: Froject In5pgrWr
11/20/2009 19:13 3606541840
NTN CONSTRUCTION INC PAGE 03/03
Combined Gradation Chart
Concrete
Component
Component
Component
Component
Component
Combined
A re ates
1
2
3
4
5
Gradation
WSDOT Pit No.
D-172
UUSQ0T ASR 14-pay
'
Resultsb
i 3
Grading c
WSDOT Class,2
AASi1TQ ##57
BLD_SAND
AGG 57
Percent of Total Aggregate
40
-
60
-
100%
Specific Graevity
2.65
-
2.68
Lbs/cy (ssd)
1180
1760
Percent Passina
2 inch
100.0
100.0
-
-
100.0
1-1/2 inch
100.0
100.0
-
100.0
1 inch
100.0
98.0
-
98.8
3/4 inch
100.0
-
63.0
-
89.8
1/2 inch
100.0
-
45.0
-
67.1
3/8 inch
100.0
_
15.0
49.1
No.4
98.5
1.7
-
40.6
No.8
67.1
0.3
-
35.1
No.16
75.G
_
0.3
-
3015
No.30
55.7
0.3
-
-
22.5
No.50
21,6
_
0.3
-
8.8
No.100
4.1
-
0.3
-
1.8
No, 200
0'6
0.3
-
-
1.4
Fineness Modulus! 2.57 (Required for Class 2 Sant
ASR Mitigation Method Proposed°'
Notes;
a Required for Class 40001) and 4000P nnixes.
f, If Alkali Gilioa Reactivity Miti.ggation is required per WSDOT ASA database , A.ttach evidence thmt mitigating mcasuro controls
expansion in the form of ASTIV1 C 1260.1 AASHTO T-303, ASTM t~ 1293, or ASTM C 295 test results
AASHTQ No. 467. 57. 67, 7. 6: WSDOT Class 1. Class 2; or combined gradation. See Standard
Specification 5-03,1
ct Required for Cement Concrete Pavements
e A:ttach test results indicating conformance to Standard Specification 9-25.1
0:; ? FCrr' 3t 0-17-0 EF
19730-64th Avenue West, Suite 200
ULWALynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-009
Date (mm/dd/yft
11/2412009
HWA Project No.:
2006-171-21
HWA Task -No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway Project
Edmonds, WA
'Weather
-
Client
ClientCity
Client Representative
of EdmondsJaime
Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 6:30 Arrived at Site: 6:40 Departed Site: 15:50 End Travel: 16:00
ACTIVITY BEING INSPECTED: Class 1/2" HMA Asphaltic Concrete Pavement delivery, placement, and compaction.
GENERAL LOCATION: Road patch along curb and gutter on 75th Avenue West
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field Compaction Test
Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: The HMA was placed using a wheelbarrow. Compaction was applied using a
DD28HF vibratory steel break -down roller, and a plate compactor.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation, periodic temperature monitoring,
and compaction testing of the completed pavement. Compaction test results are summarized on the attached 'Field Compaction .
Test Report'. A sample of the HMA was sampled from the haul vehicle on site as requested by the Jaime Hawkins. It is my
understanding that the HMA mix was obtained from Cemex plant in Kenmore.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in conformance with
approved plans, specifications and RAS.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA was on site as requested to observe the placement of HMA at Station 12+00 through 22+00 along 75th Avenue West between
the curb and gutter and the center line of East lane. HWA confirmed that compaction was met using a Nuclear Density Gauge.
HMA was placed in two lifts. The total tonage of HMA placed today was 70.5-tons.
While on site HWA obtained Concrete cylinder sets C-2 and C-3 cast on 11/23/2009 and transported them to HWA office for testing.
Total time charged to the job for this visit is 10 hours including report writing.
SIGNATURES:
HWA F4 Representative HWA Project Engineer eviewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
na na There are no outstanding issues at this time.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 2
19730-64th Avenue West, Suite 200
WALynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSmNCES INC. Fax.425-774-2714
Field Report No.:
FR-009
Date (mm/dd/yft
11/24/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
I Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED: see accompanying field report
Elev'n
Lab Control*
Field Test
Relative
Density
Moist.
or
Probe
(Proctor/Rice/Marshall)
Compaction
Test
Depth
Depth
ID
Max.
Opt.
Over
Total
Dry
Moist.
Field
Spec
No.
Detailed Test Location
B.G.**
(in)
#
Dens.
Moist.
Size %
pcf
pcf
%
%
%
1
Station 11+00
T.O.G
BIS
HMA
154.7
141.5
91
91
I
2
Station 11+50
T.O.G
BIS
HMA
154.7
140.1
91
91
3
Station 12+00
T.O.G
BIS
HMA
154.7
140.4
91
91
4
Station 12+50
T.O.G
BIS
HMA
154.7
140.8
91
91
5
Station 13+00
T.O.G
BIS
HMA
154.7
140.1
91
91
6
Station 14+00
T.O.G
BIS
HMA
154.7
141.5
91
91
7
Station 16+00
T.O..G
BIS
HMA
154.7
141.6
92
91
8
Station 18+00
T.O.G
BIS
HMA
154.7
140.6
91
91
9
Station 30+00
T.O.G
BIS
HMA
154.7
140.2
91
91
1
1
10
Station 32+00
T.O.G
BIS
HMA
154.7
140.9
91
91
11
12
13
Test Method ASTM D2922/D3017 (soil) uASTM D2950 (asphalt) Other:
Densometer: X Troxler 3440 Troxler 3430 Troxler 3411-B CPN MC1-DR-P
Serial #: 37406 Density Standard Count.: 2785 Moisture Standard Count: 737
*Lab Control: Standard Proctor Modified Proctor
Asphalt Marshall Density x Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 2
W.
~GEOSCIENCES INC.
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
Fax. 425-774-2714
Field Report No.:
FR-010
Date (mm/dd/yy):
11/25/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 06:30 Arrived at Site: 6:40 Departed Site: 15:50 End Travel: 16:00
ACTIVITY BEING INSPECTED: Class 1/2" HMA Asphaltic Concrete Pavement delivery, placement, and compaction.
GENERAL LOCATION: Road patch along curb and gutter on the East side of 75th Avenue West.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field Compaction
Test Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: The HMA was placed using wheelbarrows. Compaction was applied
using a DD28HF vibratory steel break -down roller, and a plate compactor
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation, periodic temperature
monitoring, and compaction testing of the completed HMA. Compaction test results are summarized on the attached
Field Compaction Test Report'. A sample of the HMA mix was sampled from the haul vehicle on site as requested by
Jaime Hawkins. It is my understanding that the HMA mix was obtained from Cemex plant in Kenmore.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
' ACTIVITY BEING INSPECTED: Compaction of Crushed Surfacing Top Course (CSTC designated AG-1) for use as
driveway base for asphalt.
GENERAL LOCATION: Residence driveway on East side of 75th Avenue West at station 24+00
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field Compaction
Test Report'.
TYPE OF INSPECTION: Periodic
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by the contractor, materials were
placed in approximately one foot lifts and compacted with a plate compactor.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was not able to observe either the lift placement and the compaction application prior to testing, for the
following tests. Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected were found to be in
' conformance with approved plans, specifications and RFIs, with the exception of the following items.
Item 1 - Unresolved- Nuclear density testing at residence driveway at station 24+00 indicated that the driveway backfill
material did not meet the compaction requirement.
L
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page "I of 3
I
u'
HWAGWSCIENCES INC.
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
Fax. 425-774-2714
Field Report No.:
Date (mm/dd/yy):
HWA Project No.:
HWA Task No.:
FR-010
11/25/2009
2006-171-21
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA on site as requested to observe the placement of HMA at Station 22+00 through 32+00 along 75th Avenue West
between the curb and gutter and the center line of East lane. HWA confirmed that compaction was met using Nuclear
Density Gauge. HMA was placed in two lifts. The total tonnage of HMA placed today was 56.5-tons
At the time of HWA's arrival the contractor had placed and compacted 12" of CSTC in the Driveway at address 16411 at
station 24+00. Physical evaluation and Nuclear Density testing indicated the CSTC to be loose and notwell compacted
in the driveway.
Total time charged to the job for this visit is 10 hours including report writing. ,
SIGNATURES:
r
Signed: - Reviewed: � :,•-.- �- �4:-�.�=--
HWA Field Vepresentative HWA Project Engineer or,R� eviE er
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
010 1 Unresolved Nuclear density testing indicated the CSTC is loose and not well compacted in
the driveway.
This report should only be reproduced in its entirety. Report is not final until signed by HWA Feld representative and HWA reviewer. Page 2 of 3
11
19730-64th Avenue West, Suite 200
X.
L nnwood WA 98036
y
Li iI`
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax 425-774-2714
Field Report No.:
FR-010
Date (mm/dd/yy):
11/25/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED: see accomoanvinq field repot
Elev'n
Lab Control*
Field Test
Relative
or
Probe
(Proctor/Rice/Marshall)
Density
Moist.
Compaction
Test
Depth
Depth
ID
Max.
Opt.
Over
Total
Dry
Moist.
Field
Spec
No.
Detailed Test Location
B.G."
(in)
#
Dens.
Moist.
Size %
pcf
pcf
%
%
%
1
Station 23+00 on 75th Avenue West
T.O.G
B/S
HMA
154.9
141.7
91
91
2
Station 24+00 on 75th Avenue West
T O.G
B/S
H3A
154.9
141.1
91
91
3
Station 12+00 on 75th Avenue West
T.O.G
B/S
HMA
154.9
141.4
91
91
4
Station 25+50 on 75th Avenue West
T.O.G
B/S
H3A
154.9
141.8
92
91
5
Station 26+00 on 75th Avenue West
T.O.G
B/S
H3A
154.9
140.2
91
91
6
Station 27+00 on 75th Avenue West
T.O.G
B/S
H3A
154.9
141.6
91
91
7
Station 28+00 on 75th Avenue West
T.O.G
B/S
H3A
154.9
141.7
91
91
8
Station 29+00 on 75th Avenue West
T.O.G
B/S
HMA
154.9
141.6
91
91
9
Station 30+00 on 75th Avenue West
TO.G
B/S
HMA
154.9
141.3
91
91
10
Station 32+00 on 75th Avenue West
T.O.G
B/S
H3A
154.9
141.0
91
91
11
Center of Driveway
T.O.G
8"
AG-1
137.1
7.3
5
137.3
126.5
8.6
92
95
12
3ft Northeast and Center of Driveway
T.O.G
8"
AG-1
137.1
7.3
5
136.9
125.4
9.2
1
95
13
4ft Southwest and Center of Driveway
T.O.G
8"
AG-1
137.1
7.3
- 5
137.4
127.4
7.9
L93
95
Test Method X ASTM D2922/D3017 (soil) x ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-B CPN MCI-DR-P
Serial #: 37406 Density Standard Count.: 2785 Moisture Standard Count: 737
"Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density x Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 3 of 3
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGE(JSCIE I�TCES Z10TC. Fax. 425-774-2714
Field Report No.:
FR-011
Date (mm/dd/yy):
11/27/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name,
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
- FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 0900 Arrived at Site: 1000 Departed Site: 1020 End Travel: 1030
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
A site visit was made to obtain cylinder set C-4 cored by contractor on 11/26/09. The cored cylinders were transported
to our office in Lynnwood for testing.
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURES:
P
Signed: Reviewed- 7"�
HWA Field Representative HWA Project Engineer or R'ev' we'r
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
010 1 Unresolved Nuclear density testing indicated the CSTC to be loose and.not well compacted in the
driveway.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
LWI
■ I`1WAGEOSCIENCESINC.
H
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
Fax. 425-774-2714
Field Report No.:
FR-012
Date (mm/ddlyy):
11/30/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 08:00 Arrived at Site: 08:10 Departed Site: 15:50 End Travel: 16:00
ACTIVITY BEING INSPECTED: Class 1/2" HMA Asphaltic Concrete Pavement delivery, placement, and compaction.
GENERAL LOCATION: Sidewalk and driveways on the East side of 75th Avenue West.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: The HMA was placed using wheelbarrows. Compaction was applied
using a DD28HF vibratory steel break -down roller, and a plate compactor
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation, periodic temperature
monitoring, and compaction testing of the completed pavement. Compaction test results are summarized on the
attached 'Field Compaction Test Report'. A sample of the HMA mix was sampled from the haul vehicle on site as
requested by Jaime Hawkins. It is my understanding that the HMA mix was obtained from Cemex plant in Kenmore.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA was on site as requested to observe the placement of HMA in the sidewalk and driveway areas between Station
11+50 through 18+00 along 75th Avenue West. HWA confirmed compaction was met using a Nuclear Density Gauge.
HMA,was placed in one lift. The total tonnage placed today was 54.18-tons.
Total time charged to the job for this visit is 8.5 hours including report writing.
SIGNATURES: 1.
Signed: Reviewed:`�--�-
HWA Field Representative HWA Project Engineer 6r-R sewer
SUMMARY OF UNRESOLVED ISSUES ,
' Report# Item# Status
010 1 Unresolved Nuclear density testing indicated the CSTC to be loose and not well compacted in the
driveway.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 2
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-012
Date (mm/dd/yy):
11/30/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED: see accompanying field report
Elev'n
Lab Control*
Field Test
Relative
Density
Moist.
or
Probe
(Proctor/Rice/Marshall)
Compaction
ID
Max.
Opt.
Over
Total
Dry
Moist.
Field
Spec
Test
Depth
Depth
No.
Detailed Test Location
B.G."(in)
#
Dens.
Moist.
Size %
pcf
pcf
%
1
Sidewalk apron @ Station 12+00 on
T O.G
BIS .
HMA
155.3
141.5
91
91
75th Avenue West
4
2
Sidewalk apron @ Station 13+00 on
T.O.G
BIS
HMA
155.3
142.1
92
91
75th Avenue West
4
3
Sidewalk apron @ Station 14+00 on
T.O.G
BIS
HMA
155.3
141.5
91
91
75th Avenue West
4
4
Sidewalk apron @ Station 15+00 on
T.O.G
BIS
HMA
155.3
141.7
91
91
75th Avenue West
4
5
Sidewalk apron @ Station 16+00 on
T.O.G
BIS
HMA
155.3
141.2
91
91
75th Avenue West
4
6
Sidewalk apron @ Staion 17+00 on
T O. G
BIS
HMA
155.3
141.9
91
91
75th Avenue West
4
7
Sidewalk apron @ Staion 18+00 on
T.O.G
BIS
HMA
155.3
140.9
91
91
75th Avenue West
4
8
Center of Driveway #16717 & 8' East
T.O.G
BIS
HMA
155.3
141.8
91
91
9
Center of Driveway#16711 & 12'
T.O.G
BIS
HMA
155.3
140.8
91
91
East
10
Center of Driveway #1662 & 10' East
T.O.G
BIS
HMA
155.3
142.0
91
91
11
Center of Driveway #1662 & 20' East
T O.G
BIS
HMA
155.3
141.6
91
91
12
13-
Test Method ASTM D2922/D3017 (soil) x ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-B CPN MCI-DR-P
Serial #: 37406 Density Standard Count.: 2785 Moisture Standard Count: 737
*Lab Control: Standard Proctor Modified Proctor
Asphalt Marshall Density x Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 2
L
19730-64th Avenue West, Suite 206
Lynnwood, WA 98036,
Tel. 425-774-0106
' HWAGEOSCIENCES INC. Fax.425-774-2714
Project Name Location or Address or Project
76th Ave W/75th PI W Walkway Edmonds, WA
Client Client Representative
Citv of Edmonds Jaime Hawkins
or
Field Report No.:
FR-013
Date (mm/ddlyy):
121112009
HWA Project No.:
2006-171-21
HWA Task No.:
300
overcast/Cool
HWA Project Manag
Tonv Martin
General contractor I Brian Coker
Precision Earthworks
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 08:30 Arrived at Site: 08:40 Departed Site: 15:50 End Travel: 16:00
ACTIVITY BEING INSPECTED: Class 1/2" HMA Asphaltic Concrete Pavement delivery, placement, and compaction.
GENERAL LOCATION: Sidewalk and driveways on. the East side of 75th Avenue West.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: The HMA was placed using wheelbarrows. Compaction was applied
using a DD28HF vibratory steel break -down roller, and a plate compactor
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation, periodic temperature
monitoring, and compaction testing of the completed pavement. Compaction test results are summarized on the
attached 'Field Compaction Test Report'. A sample of the HMA mix was sampled from the haul vehicle on site. It is my
understanding that the HMA mix was obtained from Cemex plant in Kenmore.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list below.
ACTIVITY BEING INSPECTED: Compaction of sample AG-1 crushed surfacing top course for use as driveway base for
asphalt.
ITEM BEING CONSTRUCTED: Residence driveway on East side of 75th Avenue West @ station 24+00
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached field compaction
test report.
TYPE OF INSPECTION: Periodic
STATUS AND DETAILS OF CONSTRUCTION: Materials were placed in approximately one foot lifts and compacted
with a single drum vibrating roller.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction testing. HWA was
able to observe both the lift placement and the compaction application prior to testing for the following test. Test results
are summarized on the attached field compaction test report.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
' HWA observed the contractor over excavate the loose saturated material on the lower half of the driveway down to firm
suitable soil approximately 18" to 2' in depth and apply fabric followed by top course.
Total time charged to the job for this visit is 8 hours including report writing.
SIGNATURES:
n
Signe _ �� Reviewed: l� '
HWA Fie Repr sentative HWA Project Engineer or er
Pa e 1 of 3
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
Avenue West, Suite 200
19730-64t
Lynnwood,
Lynnwoodod,, WA 98036
Tel. 425-774-0106
H.WAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-013
Date (mm/dd/yy):
12/1/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Brian Coker
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
010 1 Resolved: CSTC material was recompacted, re -tested and determined to meet the contract
specifications.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 3
u
L'
ri
L
ULWA 19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-013
Date (mm/dd/yy):
12/1/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Mather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I Brian Coker
.FIELD COMPACTION TEST REPORT -NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED: see accompanying field report
Elev'n Lab Control* Field Test Relative
or Probe (Proctor/Rice/Marshall) 11 Densitv Moist_ Cmmnnction
Test
Depth
Depth
No.
Detailed Test Location
B.G.**
(in)
1
Sidewalk apron @ Station 18+50 on
75th Avenue West
T.O.G
8/S
Sidewalk apron @Station 19+00 on
2
75th Avenue West
T.O.G
B/S.
3
Sidewalk apron @ Station 19+50 on
75th Avenue West
T.O.G
8/S
Sidewalk apron @ Station 20+00 on
4
75th Avenue West
T. O. G
B/S
Sidewalk apron @ Station 21+00 on
5
75th Avenue West
T. O. G
8/S
Sidewalk apron @ Station 22+00 on
6
75th Avenue West
T. O. G
8/S
Sidewalk apron @ Station 23+00 on
7
75th Avenue West
T.O.G
B/S
8
Center of Driveway #16642 & 5' East
T.O.G
B/S
9
Retest of #11 on FR 010 Center of
Driveway
T.O.G
8"
Retest of #12 on FR 010 aft
10
Northeast & center of driveway
T. O. G
8'
11
Retest of #13 on FR 010 4ft
T.O.G
8',
Southwest & center of driveway
12
ID
Max.
Opt.
Over
Total
Dry
Moist.
Field
Spec
#
Dens.
Moist.
Size %
pcf
pcf
%
%
%
HMA
155.3
141.7
91
91
5
HMA
155.3
142.1
92
91
5
HMA
155.3
140.9
91
91
5
HMA
155.3
141.9
91
91
5
HMA
155.3
141.0
91
91
5
HMA
155.3
142.0
91
91
5
HMA
155.3
1
91
91
5
HMA
155.3
F40.
91
91
5
AG-1
137.1
7.3
5
139.2
130.6
6.6
95
95
AG-1
137.1
7.3
5
141.1
131.2
7.6
96
95
AG-1
137.1
7.3
5
142.0
130.4
8.9
95
95
Test Method X ASTM D2922/D3017 (soil) x ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-B CPN MC1-DR-P
Serial #: 37406 Density Standard Count.: 2806 Moisture Standard Count: 738
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density x Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to,a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 3 of 3
HWAGEOSCI ACES INC.
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
Fax. 425-774-2714
Field Report No.:
FR-014
Date (mm/dd/yy):
12/2/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD REPORI
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 08:00 Arrived at Site: 08:10 Departed Site: 14:50 End Travel: 15:00
ACTIVITY BEING INSPECTED: Class 1/2" HMA Asphaltic Concrete Pavement delivery, placement, and compaction.
GENERAL LOCATION: Sidewalk and driveways on the East side of 75th Avenue West.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: The HMA was placed using wheelbarrows. Compaction was applied
using a DD28HF vibratory steel break -down roller, and a plate compactor
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation, periodic temperature
monitoring, and compaction testing of the completed pavement. Compaction test results are summarized on the
attached 'Field Compaction Test Report'. A sample of the HMA mix was sampled from the haul vehicle on site. It is my
understanding that the HMA mix was obtained from Cemex plant in Kenmore.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list below.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor place an approximate 12" uncompacted lift of 1 1/4" minus base course at the footing of
the evaluated sidewalk between G.L. 44+00 and 45+00.
Also observed on this day while on site was a 1 Oft by 6ft loose saturated pumping area of soil in the first 7ft east of the
curb in driveway #16221. Contractor over excavated the saturated area and installed fabric and 2" x 4" Quarry spalls.
I
Total time charged to the job for this visit is 7.5 hours including report writing. I
SIGNATURES:
Signed: Reviewed: e-�
HWA Fi Id Representative HWA Project Engineer or evie
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 2
11
L
::..:..., ..19730-64th Avenue West, u'te 200
�.
_ Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-014
Date (mm/dd/yy):
12/2/2009
HWA Project No.:
2006-171-21
HWA Task No.:
300
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED: see accompanying field report
Elev'n
Lab Control*
Field Test
Relative
Density
Moist.
or
Probe
(Proctor/Rice/Marshall)
Compaction
Test
Depth
Depth
ID
Max.
Opt.
Over
Total
Dry
Moist.
Field
Spec
No.
Detailed Test Location
B.G.**
(iri)
#
Dens.
Moist.
Size %
pcf
pcf
%
%
%
1
Sidewalk apron @ Station 31+50 on
T 0.G
B/S
HMA
155.3
141.6
91
91
75th Avenue West
6
2
Sidewalk apron @ Station 31+00 on
T.O.G
B/S
HMA
155.3
142.0
91
91
75th Avenue West.
6
3
Sidewalk apron @.Station 30+00 on
T.O.G
B/S
HMA
155.3
140.9
91
91
75th Avenue West
6
4
Sidewalk apron @ Station 29+00 on
T.O.G
B/S
HMA
155.3
142.2
92
91
75th Avenue West
6
5
Sidewalk apron @ Station 28+00 on
T.O.G
B/S
HMA
155.3
141.1
91
91
75th Avenue West
6
6
Center of driveway #16221 & 10ft
S. G
8"
AG-1
137.1
7.3
5
141.8
130.7
$.6
95
95
East of Curb
7
Center of driveway #16221 & 15ft
S. G
8"
AG-1
137.1
7.3
5
140.1
129.9
7.9
95
95
East of Curb
8
9
10
11
12
13
Test Method X ASTM D2922/D3017 (soil) x ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-B CPN MC1-DR-1P
Serial #: 37406 Density Standard Count.: 2806 Moisture Standard Count: 738
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density x Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is notfinal until signed by HWA field representative and HWA reviewer. Page 2 of 2
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0105
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-015
Date (mm/dd/yy):
'
12/7/2009
HWA Project No.:
2006-171-21
HWA Task No.:
500
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 09:00 Arrived at Site: 09:10 Departed Site: 12:50 End Travel: 13:00
ACTIVITY BEING INSPECTED: Preparation of Bearing Soils.
ITEM BEING CONSTRUCTED: Footings for precast pedestrian sidewalk
DETAILED LOCATION: Station 44+00 to 45+00
TYPE OF INSPECTION: Periodic
STATUS AND DETAILS OF CONSTRUCTION: At the time of our inspection, the contractor was over excavating
approximately 3' in depth for the footing subgrade.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and probing with a 1/2" diameter
steel T-handled probe to check subgrade for areas of soft, loose, disturbed or otherwise unsuitable soils. Physical
evaluation indicated the prepared subgrade soils were dense and well compacted.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
Total time charged to the job for this visit is 4.0 hours including report writing.
SIGNATURES:
O
Signed: Reviewed:
HWA Field Representative HWA Project Engineer or�Rev w
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
None at this time.
11
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
C'
J
19730-64th Avenue West, Suite 200
U '1 MA
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax. 425-774-2714
Field Report No.:
FR-016
Date (mm/dd/yy):
121812009
HWA Project No.:
2006-171-21
HWA Task No.:
.500
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
113rian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 08:00 Arrived at Site: 08:10 Departed Site: 15'50 End Travel: 16:00
ACTIVITY BEING INSPECTED: Excavation of unsuitable soil.
GENERAL LOCATION OR AREA: SMH5 at Station 16+00 .
DETAILED LOCATION: SMH5 at station 16+00, East lane.
TYPE OF INSPECTION: Continuous
CONTRACTOR ACTIVITIES RELATED TO THIS ITEM: This excavated area measured 10'x5'x10.5' The excavated
soils were found to be poorly consolidated and consisting of tree roots, slabs of asphalt concrete and 2-foot to 3-foot
diameter boulders.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation of the excavation. When necessary,
the sidewalls and base of the excavation were probed with a 1/2" diameter steel T-handled probe to confirm that
unsuitable soils had been removed, and that only suitably firm soils remain.
' CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor place pea gravel bedding under a 18-inch storm culvert and placed a 2 feet to 4 feet lift of
uncompacted CSBC over and around the pipe. The placement of CSBC was approximately 7.5 feet below top of grade.
HWA will return on 12/9/2009 for compaction test of compacted CSBC.
Total time charged to the job for this visit is 8.0 hours including report writing.
SIGNATURES:
Signed: ,e,P/ u% Reviewed:
HWA Fie[epresentative HWA Project Engineer or R vi r
SUMMARY OF UNRESOLVED ISSUES
11 Report# Item# Status
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel.425-774-0106 '
HWAGEOSCIENCES INC. Fax.425-774-2714
Project Name Location or Aooress c
76th Ave W/75th PI W Walkway Edmonds, WA
City of Edmonds JJaime Hawkins
N-inn Authoritv (enoineer or architect of record) j Design Authority Repr
Precision Earthworks
Field Report No.:
Date (mm/ddlyy):
HWA Project No.:
HWA Task No.:
FR-017
12/9/2009
2006-171-21
500
overcast/Cool
Tonv Martin
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 06:50 Arrived at Site: 07:00 Departed Site: 07:20 End Travel: 07:30
Start Travel: 08:50 Arrived at Site: 09:00 Departed Site: 11:20 End Travel: 11:30
Start Travel: 12:50 Arrived at Site: 13:00 Departed Site: 15:50 End Travel: 16:00
ACTIVITY BEING INSPECTED: Compaction of CSBC for use as trench backfill.
GENERAL LOCATION: SMH5 at Station 16+00
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation materials were
placed in approximately 2-foot lifts (uncompacted thickness) and compacted with a Case 580 backhoe.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor spread out the 2-feet to 4-feet lift of uncompacted CSBC that was placed around the 18-
inch storm culvert on 12/8/2009, to a more even 2-foot lift approximately 8 feet below top of grade. Compaction was
obtained by a Case 580 backhoe with medium pressure on the first lift. More compactive effort was exerted on the
remaining lifts causing the backhoe outriggers to come off the ground.
Total time charged to the job for this visit is 6.0 hours including report writing.
SIGNATURES:
Signe
HWA Fiel epre entative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
HWA Project Engineer or
I
Pa e 1 of 2 1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
1
ULWALynnwood,
19730-64th Avenue West, Suite 200
WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC.
Fax.425-774-2714
Field Report No.:
FR-017
Date (mm/dd/yy):
12/9/2009
HWA Project No.:
2006-171-21
HWA Task No.:
500
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD COMPACTION TEST REPORT a NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED: see accompanying field report
1
n
11
F
Test
No.
Detailed Test Location
Elev'n
or
Depth
B.G."
Probe
Depth
(in)
Lab Control"
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens.
Opt.
Moist.
Over
Size %
Total
pcf
Dry
pcf
Moist.
%
Field
°10
Spec
1
East Lane/5ft West of curb
-8'
8"
AG-2
143.5
5.1
23
136.9
4.5
95
95
2
West Lane/8ft West of curb
-8'
8"
AG-2
143.5
5.1
23
137.1
3.7
96
95
3
East Lane/3ft West of curb
-6'
8"
AG-2
143.5
5:1
23
137.0
4.0
95
95
4
West Lane/10ft West of curb
-6'
8"
AG-2
143.5
5.1
23
136.4
4.5
95
95
5
East Lane/6ft West of Curb
-2'
8"
AG-2
143.5
5.1
23
136.9
4.1
95
95
6
West Lane/9ft West of curb
-2'
8"
AG-2
143.5
5.1
23
137.4
3.9
96
95
7
8
9
10
11
12
13
Test Method X ASTM D2922/D3017 (soil) ASTM D2950 (asphalt) Other:
Densometer: X Troxler 3440 _Troxler 3430 Troxler 3411-B CPN MC1-DR-P
Serial #: 37406 Density Standard Count.: 2806 Moisture Standard Count: 738
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 2
19730-64th Avenue West, Suite 200
iriLynnwood, WA 98036
W
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
76th Ave W/75th PI W Walkway lEdmonds, WA
of Edmonds (Jaime Hawkins
Field Report No.:
FR-018
Date (mm/ddlyy):
12/10/2009
HWA Project No.:.
2006-171-21
HWA Task No.:
500
overcast/Cool
Design Authority (engineer or arcnnect or recora) vc� y �uu ,., . • -• ••_- --
Tony Martin
General Contractor General Contractor Representative -77HWA Field Representative
Precision Earthworks Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 07:20 Arrived at Site: 07:30 Departed Site: 09:20 End Travel: 09:30
Start Travel: 10:50 Arrived at Site: 11:00 Departed Site: 15:20 End Travel: 15:30
ACTIVITY BEING INSPECTED: Excavation of soil.
GENERAL LOCATION OR AREA: SMH5 at Station 16+00 to SMH4 at Station 15+72
DETAILED LOCATION: Storm pipe trench between SMH4 and SMH5.
TYPE OF INSPECTION: Continuous
CONTRACTOR ACTIVITIES RELATED TO THIS ITEM: Excavated trench area measured 40"x5'x10'
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation of the excavation. When necessary,
the sidewalls and base of the excavation were probed with a 1/2" diameter steel T-handled probe to confirm that
unsuitable soils had been removed, and that only suitably firm soils remain.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use as trench backfill.
GENERAL LOCATION: SMH5 at Station 16+00 to SMH4 at Station 15+72
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report',
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials were
placed in approximately 2' foot lifts uncompacted thickness and compacted with a Case 580 backhoe.
HWA INSPECTION ACTIVITIES RELATED OlmenEM: HWA an the compaction ontappf slat on priotion and r to testing,, foraction
lltests.
testing. HWA was able to observe both the liftplace
Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor place 3" of bedding, consisting of pea gravel under SMH4 and an additional 2" to 4"
around the sewer manhole followed by two, 2' lift of CSBC over and around the 12" storm pipe. Compaction was
obtained using a jumping jack and a Case 580 backhoe with medium pressure on the first lift covering storm pipe. More
compactive effort was exerted on the remaining lifts causing the backhoe outriggers to come off the ground.
Total time charged to the job for this visit is 6.5 hours including report writing.
SIGNATURES:
Signed: Reviewed --r-�
HWA Field Representative HWA Project Engineer or Re aevG
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer.
1
Page 1 of 3 1
UiW 19730-64th Avenue West, Suite 200
Lynnwood, WA 98035
Tel. 425-774-0106
HWAGEOSCIENCES INC. F...425-774-2714
Field Report No.:
FR-018
Date (mm/dd/yft
12/10/2009
HWA Project No.:
2006-171-21
HWA Task No.:
500
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony'Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
None at this time.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 3
19730-64th Avenue West, Suite 200
[rLWA,
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax. 425-774-2714
Field Report No.:
FR-018
'
Date (mm/dd/yy):
12/10/2009
HWA Project No.:
2006-171-21
HWA Task No.:
500
■
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
I Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED- see nrromnanvina ffetd rennrt
Test
No.
Detailed Test Location
Elev'n
or
Depth
B.G.**
Probe
Depth
(in)
Lab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens.
Opt.
Moist.
Over
Size %
TotaldDMoist.
pcf
%
Field
%
Spec
%
1
6ft South of SMH 5
-4"
8"
AG-2
143.5
5.1
23
144.0
5.5
95
95
2
13ft South of SMH 5
-4"
8"
AG-2
143.5
5.1
23
143.7
5.0
95
95
3
5ft South of SMH 5
-2"
8"
AG-2
143.5
5.1
23
143.5
4.7
96
95
4
12ft south of SMH 5
-2"
8"
AG-2
143.5
5.1
23
144.7
137.2
5.5
96
95
5
6
7
8
9
10
11
12
13
Test Method X ASTM D2922/D3017 (soil) ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-B CPN MCI-DR-P
Serial #: 37406 Density Standard Count.: 2787 Moisture Standard Count: 729
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to.a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 3 of 3
H
H
I
D
19730-6411 Avenue West, Suite 200
�,• ; Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-019
Date (mmldd/yy):
12/14/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/ Wet
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Brian Coker
FIELD KtFUK I
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 08:20 Arrived at Site: 08:30 Departed Site: 15:20 End Travel: 15:30
ACTIVITY BEING INSPECTED: Excavation of soil.
GENERAL LOCATION OR AREA: Northend of 75th & 76th at the South corner of the elevated sidewalk.
DETAILED LOCATION: C.B. type 1, Number 11 and 12" storm pipe trench at station 31+86.
TYPE OF INSPECTION: Continuous
CONTRACTOR ACTIVITIES RELATED TO THIS ITEM: Excavated trench area measured 35'x3'x3'
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation of the excavation. When necessary,
the sidewalls and base of the excavation were probed with a 1/2" diameter steel T-handled probe to confirm that
unsuitable soils had been removed, and that only suitably firm -soils remain.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use as wall backfill in the park.
GENERAL LOCATION: Modular block wall approximately at stations 00+00 to 01+55.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached'Field
Compaction Test Report'. The elevations are measured from the footing and the course applied.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials were
placed in approximately 9" lifts uncompacted thickness and compacted with a plate compactor.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor place 2 feet of AG-2 CSBC over and around the 12" storm pipe followed by a 1 foot lift.
Compaction was obtained on each lift using a steel vibratory plate attachment on a Case 580 backhoe. Heavy
compaction effort was exerted to the point of causing the backhoe outriggers- to come off the ground.
HWA observed the contractor place clean crushed rock in each block cell and on top of the Geo-grid fabric behind the
modular block wall every second layer of block followed by AG-2 CSBC. This work was located in the park between
approximate locations 0+00 to 1+55. Compaction was obtained using a plate compactor and material was compacted
after each course of block was applied.
' It should be noted that C.B.11 location was changed from the approved plans and was approved per Ed with the City of
Edmonds. The plans call for the C.B. to be 8 inches from the corner of the elevated sidewalk wall, but because the
footing was too high, the C.B. 11 was relocated 3 feet from the corner of the elevated sidewalk.
Total time charged to the job for this visit is 7 hours including report writing.
' This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 3
19730-64th Avenue West, Suite 200
ULWALynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-019
Date (mm/ddlyft
12/14/2009
HWA Project No.:
. 2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/ Wet
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
SIGNATURES:
Signed:
HWA Field e esen ative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
None at this time.
K
s t.
Reviewed .
HWA Project Engineer wiewer
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 3
1
19730-64th Avenue West, Suite 200
WALynnwood, WA 98036Tel. 425-774-0106
' HWAGEOSCIENCES INC. Fax.425-774-2714
L]
Field Report No.:
FR-019
Date (mm/dd/yy):
12/14/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/ Wet
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED: see accmmnanvina field rennrt
Test
No.
Detailed Test Location
Elev'n
or
Depth
B.G.**
Probe
Depth
(in)
Lab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens.
Opt.
Moist.
Over
Size %
Total
pcf
Dry
pcf
Moist.
%
Field
%
Spec
%
1
Station 0+25, 2ft East of block edge
Block
8
AG-2
143.5
5.1
23
143.2
136.3
5.1
95
95
2
Station 0+50, 2ft East of block edge
Block
8"
AG-2
143.5 1
5.1
23
143.2
136.7
4.8
95
95
3
Station 0+75, 2ft East of block edge
4t h
Block
8"
AG-2
143.5
5.1
23
144.5
137.0
5.5
95
95
4
Station 1 +25, 2ft East of block edge
B� tck
8"
AG-2
143.5
5.1
23
144.8
137.2
5.6
96
95
5
5ft south east of C.8 11
8"
AG-2
143.5
5.1
23
143.6
136.4 '
5.3
95
95
6
8ft south east of C.B.11
-1'
8"
AG-2
143.5
5.1
23
142.4
136.5
5.1
95
95
7
6ft south east of C.B.:11
T.O.G
8"
AG-2
143.5
5.1
23
144.2
136.9
5.4
95
95
8
15ft south east of C.6.11
T.O.G
8"
AG-2
143.5
5.1
23
143.9
136.2
5.7
95
95
9
.10
11
12
L13
7
Test Method X ASTM D2922/D3017 (soil) ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-B CPN MC1-DR-P
Serial #: 37406 Density Standard Count.: 2791 Moisture Standard Count: 730
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 3 of 3
19730-64th Avenue West, Suite 200
\►� �C�; Lynnwood, WA 98036
�� Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-020
Date (mm/dd/yy):
12/15/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Periods of Rain
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 010:20 Arrived at Site: 010:30 Departed Site: 15:20 End Travel: 14:30
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use as wall backfill in the park.
GENERAL LOCATION: Modular block wall approximately at stations 00+00 to 01+55
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report. The elevations are measured from the footing and the course applied.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials
were placed in approximately 9" lifts uncompacted thickness and compacted with a plate compactor.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor place clean crushed rock in each block cell and on top of the Geo-grid fabric behind the
modular block wall, followed by AG-2 CSBC. This work was located in the park between approximate locations 0+00
to 1+55. Compaction was obtained using a plate compactor and material was compacted after each course of block
was applied.
Total time charged to the job for this visit is 4 hours including report writing.
SIGNATURES:
Signed:
HWA Fiel epresentative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
None at this time.
Reviewed:
HWA Project Engineer o R er
1
n
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer
Page 1 of 2 1
0
n
0
19730-64th Avenue West, Suite 200
i1 Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. F...425-774-2714
Field Report No.:
FR-020
Date (mm/dd/yft
12/15/2009
HWA Project No.;
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Periods of Rain
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Brian Coker
HtLU UUMPAU I ION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTFIT spp acrtmanvinrr fialrl rannrf
Test
No.
Detailed Test Location
Elev'n
or
Depth
B.G.**
Probe
Depth
(in)
Lab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens.
Opt.
Moist.
Over
Size %
Total
pcf
Dry
pcf
Moist.
%
Field
%
Spec
%
1
Station 0+25, 3ft East of block edge
5t h
Block
4"
AG-2
143.5
5.1
23
143.5
136.1
5.5
95
95
2
Station 0+50, aft East of block edge
Block
4"
AG-2
143.5
5.1
23
145.7
136.5
6.8
95
95
3
Station 0+75, 2ft East of block edge
85ohk
4"
AG-2
143.5
5.1
23
145.2
136.0
6.8
95
95
4
Station 1 +25, 2ft East of block edge
g5t h
loc5
4"
AG-2
143.5
5.1
23
145..1
136.2
6.6
95
95
6
7
8
9
10
11
12
13
Test Method X ASTM D2922/D3017 (soil) ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-B CPN MC1-DR-P
Serial #: 37406 Density Standard Count.: 2787 Moisture Standard Count: 729
"Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. *"Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 2
1
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Project Name Location or Address of Project
76th Ave W/75th :PI W Walkway Edmonds, WA
Client Client Representative
Citv of Edmonds Jaime Hawkins
or architect of
Field Report No.:
FR-021
Date (mm/dd/yy):
1211712009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Clear/Sun at times
Tony Martin
3eneral Contractor I Brian Coker
Precision Earthworks
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 07:20 Arrived at Site: 07:30 Departed Site: 15:20 End Travel: 15:30
ACTIVITY BEING INSPECTED: Excavation of compacted AG-2 CSBC.
GENERAL LOCATION OR AREA: North end of 75th & 76th at the South corner of the elevated sidewalk.
DETAILED LOCATION: C.B. type 1, Number 11 and 12" storm pipe trench at station 31+86.
TYPE OF INSPECTION: Periodic
CONTRACTOR ACTIVITIES RELATED TO THIS ITEM: HWA observed the contractor excavate 6" from the top ofr cold
grade of previously placed compacted CSBC in the 35'x3' trench line of C.B. #11 at station 31+86 in preparation fo
mix asphalt.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation of the excavation.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
ACTIVITY BEING INSPECTED: Compaction. of AG-2 CSBC for use as wall backfill in the park.
GENERAL LOCATION: Modular block wall approximately at stations 00+00 to 01+55.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report'. The elevations are measured from the footing and the course applied.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials were
placed in approximately 18" to 20" lifts uncompacted thickness and compacted with a plate compactor and a BW90 A-
D2 double drum vibrating roller..
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list below
See unresolved item number one.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor excavate 6" from the top of grade of previously placed compacted CSBC in the trench
line of C.B #11 at station 31+86 in preparation for cold mix asphalt. Contractor re -compacted the trench prior to cold mix
asphalt with a plate compactor and a steel vibratory hoe-pac on a Case 580 backhoe.
HWA observed the contractor place 18" to 20" of uncompacted clean crushed rock on top of the Geo-grid fabric behind
the modular block, followed by AG-2 CSBC. This work was located in the park between approximate locations 0+00 to
1+55. Compaction was obtained using a plate compactor and a small double drum vibrating BW90 A-D2 roller.
Total time charged to the job for this visit is 8 hours including report writing.
1
1
ii
1
Pa e 1 of 3 ,
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
C
19730-64th Avenue West, suite 200 Field Report No.: FR-021
U LWA Lynnwood, WA 98036 Date (mm/dd/yft 12/17/2009
Tel.425-774-0106 HWA Project No.: 2006-171-21
' HWAGEOSCIENCES INC. F...425-774-2714 HWA Task No.: 400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
.Edmonds,
WA .
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear/Sun at times
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
SIGNATURES:
7 _
Signe .Reviewed:�--
' HWA F'dld epres ntative HWA Project Engineer or Revi wei/
G
ILI
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
F.R. 021 1 Unresolved: Upon arrival HWA observed contractor had placed the sixth and seventh block from the
foundation up without placing any clean crushed rock in the cells of the sixth block. HWA notified two employees from
Precision Earthworks as well as Precisions Earthworks block wall subcontractor foreman and advised them to remove
the seventh course of block and fill the sixth course of block cells. The contractor continued to place block without
removal of the seventh course and filling cells as required. The City Inspector was informed.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 3
Avenue West, Suite 200
19730-64t
Lynnwood,
WA 98036
Tel.425-774-0106
I-�WAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-021
Date (mm/dd/yy):
12/17/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear/Sun at times
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
I Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED: see accomoanvina field report
Test
No.
Detailed Test Location
Elev'n
or
Depth
B.G.**
Probe
Depth
(in)
Lab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens.
Opt.
Moist.
Over
Size %
Total
pcf
Dry
pcf
Moist.
%
Field
%
Spec
%
1
Station 0+25, 5ft East of block edge
Block
8
AG-2
143.5
5.1
23
146.3
137.4
6.5
96
95
2
Station 0+50, 4ft East of block edge
Block
8"
AG-2
143.5
5.1
23
145.1
136.8
6.1
95
95
3
Station 0+75, 3ft East of block edge
Block th
8'
AG-2
143.5
5.1
23
145.2
137.0
6.0
95
95
4
Station 1 +25, 4ft East of block edge
Block th
8
AG-2
143.5
5.1
23
144.7
137.1
5.6
96
95
5
1Oft southeast of C.B 11
-6"
8"
AG-2
143.5
5.1
23
144.6
136.1
6.3
95
95
6
15ft south east of C.B.11
-6"
8"
AG-2
143.5
5.1
23
151.0
135.8
6.1
95
95
7
20ft south east of C.B.11
-6"
8"
AG-2
143.5
5.1
23
146.8
136.9
7.3
95
95
8
9
10
11
12
13
Test Method X ASTM D29221D3017 (soil) ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-13 CPN MC1-DR-P
Serial #: 37406 Density Standard Count.: 3080 Moisture Standard Count: 681
"Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer.. Page 3 of 3
I - � ff.rLTV,,
L
u
U
n
HWAGEOSCIENCES INC.
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
Fax. 425-774-2714
Field Report No.:
FR-022
Date (mm/ci fty):
12/18/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 08:20 Arrived at Site: 08:30 Departed Site: 11:20 End Travel: 11:30
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use as wall backfill in the park.
GENERAL LOCATION: Modular block wall approximately at stations 00+00 to 01+00.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report'. The elevations are measured from the footing and the course applied.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials were
placed in approximately 9" lifts uncompacted thickness and compacted with a plate compactor and a BW90
A-D2 double drum vibrating roller.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor place 9" of uncompacted clean crushed rock on top of the Geo-grid fabric behind the
modular block, followed by AG-2 CSBC. This work was located in the park between approximate locations 0+00 to
1+00. Compaction was obtained using a plate compactor and a small double drum vibrating BW90 A-D2 roller.
Total time charged to the job for this visit is 3 hours including report writing.
SIGNATURES:
Signet
HWA R I epresentative HWA Project Engine or viewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
F.R. 021 1 Unresolved: Upon arrival HWA observed contractor had placed the sixth and seventh block from the
foundation up without placing any clean crushed rock in the cells of the sixth block. HWA notified two employees from
Precision Earthworks as well as Precisions Earthworks block wall subcontractor foreman and advised them to remove
the seventh course of block and fill the sixth course of block cells. The contractor continued to place block without
removal of the seventh course and filling cells as required. The City Inspector was informed.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 2
1
ULWA 19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
HVOAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-022
Date (mm/dd/yft
12/18/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
ress of Project
Permit No.
76th Ave W/75th PI W Walkway
EEdmonds,
WA
Client
tative
WeatherCit
of Edmonds
kins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
Ge neral Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
ritLu t,UIVIVAU I IUN I tti I KLPURT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PRO.IF('T IMPRr)\/FItAFNT TFCTi=n- onn s;,1.4
Test
No.
Detailed Test Location
Elev'n
or
Depth
B.G."(in)
Probe
Depth
Lab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens.
Opt.
Moist.
Over
Size %
Total
pcf
Dry
pcf
Moist.
%
Field
%
Spec
%
1
Station 0+00, 5ft East of block edge
T.O.W
6"
AG-2
143.5
5.1
23
146.1
137.4
6.4
96
95
2
Station 0+25, 5ft East of block edge
T.O.W
6"
AG-2
143.5
5.1
23
146.5
136.8
7.1
95
95
3
Station 0+50, 3ft East of block edge
T.O.W
6"
AG-2
143.5
5.1
23
146.5
137.0
7.0
95
95
4
Station 0+75, 3ft East of block edge
T.O.W
6"
AG-2
143.5
5.1
23
146.1
137.1
6.6
96
95
5
6
7
8
9
10
11
12
13
LA
Iest Method X ASTM D2922/D3017 (soil) ASTM D2950 (asphalt) Other:
Dosimeter: x Troxler 3440 _Troxler 3430 Troxler 3411-B CPN MCI-DR-P
Serial #: 37406 Density Standard Count.: 2885 Moisture Standard Count: 737
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
1
I�
I
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 2 ,
r-,
11
1
1
� I
19730-64th Avenue West, Suite 200
ULWALynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-023
Date (mm/dd/yy):
12/21/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
I Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 11:20 Arrived at Site: 11:30 Departed Site: 16:20 End Travel: 16:30
ACTIVITY BEING INSPECTED: Removal of existing block wall and excavation of unsuitable soil.
GENERAL LOCATION OR AREA: Ecology block wall on the West side of 75th &76th place at station 16+00.
TYPE OF INSPECTION: Continuous
CONTRACTOR ACTIVITIES RELATED TO THIS ITEM: This excavated area measured 17'xl3'xl1' The excavated
soils were found to be poorly consolidated and consisting of construction debris, i.e. pieces of pipe, 2"x4"s, rebar, large
slabs of asphalt and 2' to 3' diameter boulders.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation of the excavation. When necessary,
the sidewalls and base of the excavation were probed with a 1/2" diameter steel T-handled probe to confirm that
unsuitable soils had been removed, and that only suitably firm soils remain.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use as subgrade under ecology block wall.
GENERAL LOCATION: Ecology block wall on the West side of 75th &76th place at station 16+00.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report'.
TYPE OF INSPECTION: Periodic
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, CSBC was
placed as a base under the first ecology block on each side of the culvert pipe in a 12-inch lift of uncompacted thickness
and compacted with a jumping jack. The placement of CSBC was approximately 11-feet below top of asphalt.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor address unresolved item number 1 on F.R. 021. The contractor removed two course of
block from the park wall and filled each empty cell with clean crushed rock as per plan. This work was located in the
park between approximate locations 0+00 to 1+00. Contractor re -compacted areas that were disturbed in removal of
blocks. Compaction methods were a plate compactor and a small double drum vibrating BW90 A-D2 roller.
Total time charged to the job for this -visit is 6 hours including report writing.
SIGNATURES:
Signe . 7�%'� ��iA� Reviewed:
HWA I Rep esentative HWA Project Engineer or R vi
Report is not final until signed b HWA field representative and HWA reviewer.
This report should only be reproduced in its entirety. p 9 Y p
Page 1 of 3
19730-64t
Lynnwood, Avenue West, Suite200
Lynnwood, WA 98036
Tel. 425-774-0106
HWA.GEOSCIENCES INC.
Fax.425-774-2714
Field Report No.:...
FR-023
Date (mm/dd/yy):
12/21/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Brian Coker
SUMMARY OF UNRESOLVED -ISSUES
Report# Item# Status
F.R. 021 1 Resolved: Upon arrival HWA observed contractor had placed the sixth and seventh block from the
foundation up without placing any clean crushed rock in the cells of the sixth block. HWA notified two employees from
Precision Earthworks as well as Precisions Earthworks block wall subcontractor foreman and advised them to remove
the seventh course of block and fill the sixth course of block cells. The contractor continued to place block without
removal of the seventh course and filling cells as required. The City Inspector was informed.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 3
I
G
Lynnwood, Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-023
Date (mm/dd/yy):
12/21/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative,
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: . see accompanying field report
PROJECT IMPROVFMFNT TFSTFfl• SPP arcmmnanvinn finlrl rPnnrf
Test.
No.
Detailed Test Location
Elev'n
or
Depth
B.G.**
Probe
Depth
(in)
Lab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens.
Opt.
Moist.
Over
Size %
Total
pcf
Dry
pcf
Moist.
%
Field
%
Spec
%
1
Station 16+00, 6ft East from end of
culvert pipe
-10,
6"
AG-2
143.5
5.1
23
145.7
135.7
7.4
95
95
2
Station 16+00, 8ft East from of end of culvert pipe
_90'
6"
AG-2
143.5
5.1
23
145.4
135.8
7.1
95
95
3
4
5
6
7
8
9
10
11
12
13
Test Method X ASTM D2922/D3017 (soil) ASTM D2950 (asphalt) Other:
Dosimeter: Troxier 3440 _Troxler 3430 Troxler 3411-B x CPN MC1-DR-P
Serial #: 5617 Density Standard Count.: 37986 Moisture Standard Count: 9628
"Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 3 of 3
UJW 19730-64th Avenue West, Suite 100
Lynnwood, WA 98036
Tel. 425.774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-024
Date (mm/dd/yy):
12/22/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Brian Coker
NtLU KCrvr<I
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 7:20 Arrived at Site: 7:30 Departed Site: 4:20 End Travel: 4:30
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use as modular bloat wall Dacmiii .
GENERAL LOCATION: Modular block wall on the East side of 75th & 76th place at station 23+50.
DETAILED LOCATION: The specific locations and elevations tested are summarized .on the attached 'Field
Compaction Test Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials were
placed in approximately 9" lifts uncompacted thickness and compacted with a plate compactor and a jumping jack.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use as ecology block wall backfill.
GENERAL LOCATION: Ecology block wall on the West side of 75th &76th place at station 16+00.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached `Field
Compaction Test Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, CSBC was
placed in a 2' lift of uncompacted thickness behind each ecology block. Compaction was obtained with a steel vibratory
hoe -pack and a jumping jack. The placement of CSBC was approximately 10-feet below top of asphalt.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor place 9-inch of uncompacted clean crushed rock on top of the Geo-grid fabric behind the
modular block, followed by AG-2 CSBC. This work was located on the East side of 75th & 76th place at location 23+50
Compaction was obtained using a plate compactor and a jumping jack.
Total time charged to the job for this visit is 10 hours including report writing.
SIGNATUR;F*
:
Signe �, I Reviewed
HWA epr sentative HWA Project Engineer
1
I
1
r 1
Page 1 of 3a '
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. P
19736-6411 Avenue West, suite 200
Field Report No.:
FR-024
Lynnwood, WA 98036
Date (mm/ddlyy):
12/22/2009
Tel.425-774-0106
HWA Project No.:
2006-171-21
'
HWAGEOSCIENCES INC. Fax. 425-774-2714
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
' This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 3
I
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-024
Date (mm/dd/yy):
12/22/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400 ■
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker .
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TFSTFD- snn nrrmmnnnvinn fipfrl rannrt
Elev'n
Lab Control*
Field Test
Relative
or
Probe
(Proctor/Rice/Marshall)
Compaction
Density
Moist.
Test
Depth
Depth
ID
Max.
Opt.
Over
Total
Dry
Moist.
Field
Spec
No.
Detailed Test Location
B.G.-
(in)
#
Dens.
Moist.
Size %
pcf
pcf
%
%
%
1
Station 23+50, 6ft S. of power pole
4'
6"
AG-2
143.5
5.1
23
144.4
135.8
6.4
95
95
and aft East of block wall
2
Station 23+50, 8ft S. of power pole
4'
6"
AG-2
143.5
5.1
23
143.9
135.7
6.1
95
95
and 4ft East of block wall
Station 23+50, 12ft S. of power pole
3
and 2ft East of block wall
-2'
6"
AG-2
143.5
5.1
23
144.5
136.2
6.1
95
95
4
Station 23+50, 1Oft S. of power pole
-2
6"
AG-2
143.5
5.1
23
143.5
135.7
5.8
95
95
and 4ft East of block wall
5
Station 23+50, 5ft N. of power pole
_2'
6"
AG-2
143.5
5.1
23
143.5
136.1
5.5
95
95
and 2ft East of block wall
6
Station 23+50, 8ft N. of power pole
-2'
6"
AG-2
143.5
5.1
23
144.1
136.0
6.0
'95
95
and 2ft East of block wall
.
7
Station 16+00 3ft S.of pipe & 3ft E. of
8'
8'
'AG-2
143.5
5.1
23
143.9
137.1
5.0
96
95
back edge of block
8
Station 16+00 3ft N. of pipe & 2ft E.of
-8'
8"
AG-2
143.5
5.1
23
142.8
136.4
4.18
95
95
back edge of block
9
Station 16+00 3ft S of pipe & 2ft E.
-6'
8"
AG-2
143.5
5.1
23
144.5
137.0
5.5
95
95
from back edge of block
10
Station 16+00 2ft N. of pipe & 2ft E.
-6'
8"
AG-2
143.5
5.1
23
143.7
136.8
5.1
95
95
of back edge of block
11
12
13
Test Method X ASTM D2922/D3017 (soil) ASTM D2950 (asphalt) I Other:
Dosimeter: Troxler 3440 Troxler 3430 Troxler 3411-B x CPN MC1-DR-P
Serial #: 5617 Density Standard Count.: 38043 Moisture Standard Count: 9700
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. -Depth B.G. indicates depth below grade. ' Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
I
fl
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 3 of.3
I
I
II
L' J
Avenue West, Suite 200
Lynnwood,
WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-025
Date (mmlddlyy):
12/24/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 7:20 Arrived at Site: 7:30 Departed Site: 4:20 End Travel: 4:30
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use as modular block wall backfill .
GENERAL LOCATION: Modular block wall on the East side of 75th & 76th place at station 23+50.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials were
placed. in approximately 9" lifts uncompacted thickness and compacted with a plate compactor and a jumping jack.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and'the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
ACTIVITY BEING INSPECTED: Placement of Reinforcing Steel.
ITEM BEING CONSTRUCTED: Elevated sidewalk footing and wall
DETAILED LOCATION: West side of 75th Place W. between G.L. 44+00 to 45+00
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: Rebar was presented by the contractor as being,complete. This is a
preliminary inspection prior to closing formwork.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and measurements to
confirm bar sizes, number of bars, Correct placement, and adequate cover.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor place 9" of uncompacted clean crushed rock on top of the Geo-grid fabric behind the
modular block wall, followed by AG-2 CSBC. This work was located on the West side of 75th & 76th Place West at
location 23+50. Compaction was obtained using a plate compactor and a jumping jack.
Total time charged to the job for this visit is 4.5 hours including report writing.
SIGNATURES:
Sig ne Ifte_ Reviewed:
HWA i Representative HWA Project Engineer r �Rvgwer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 .of 2
19730-64th Avenue West, Suite 200
UJW Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-025
Date (mm/dd/yy):
12/24/2009
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
I
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report I
r__ In nrl_ % lr-11AI"'hIT TCC�TCI-1• nry o1,4 YonnrP -
Test
No.
Detailed Test Location
Elev'n
or
Depth
B.G."(in)
Probe
Depth
Lab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens.
Opt.
Moist.
Over
Size %
Total
pcf
Dry
pcf
Moist.
%
Field
Spec
1
Station 23+50, 8ft S. of power pole
and 3ft East of block wall
T.O.W
6"
AG-2
143.5
5.1
23
142.8
135.8
5.2
95
95
2
Station 23+50, 14ft S. of power pole
and 4ft East of block wall
T.O.W
6"
AG-2
143.5
5.1
23
144.1
135.7
6.2
95
95
3
Station 23+50, 2ft N. of power pole
and 2ft East of block wall
T.O.W
6"
AG-2
143.5
5.1
23
143.7
136.1
5.6
95
95
4
Station 23+50, 8ftS. of power pole
and 3ft East of block wall
T.O.W
6"
AG-2
143.5
5.1.
23
142.8
135.9
5.1
95
95
5
6
7
8
9
10
El
11
12
13
Test Method X ASTM D2922/D3017 (soil) ASTM D2950 (asphalt) Utner:
Dosimeter: Troxler 3440 _Troxler 3430 Troxler 3411-B x CPN MCI-DR-P
Serial #: 5617 Density Standard Count.: 38043 Moisture Standard Count: 9700
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. *"Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
I
1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. I I Page 2 of 2 1
'
�\ � TCA
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
'
HWAGEOSCIENCES INC.
Tel. 425-774-0106
F,..425-774-2714
H
E
ul
C
Field Report No.:
FR-026
Date (mm/dd/yft
12/28/2009
HWA Project No.:
2006-171-21
HWA Task No.:
500
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds.
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
I-ItLU Ktl'UM 1
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 8:20 Arrived at Site: 8:30 Departed Site: 13:50 End Travel: 14:00
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use as ecology block wall backfill .
GENERAL LOCATION: Ecology block wall on the West side of 75th & 76th place at station 23+50.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report'.
TYPE OF INSPECTION: Periodic
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials were
placed in approximately 2' lifts uncompacted thickness and compacted with a hoe -pack.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application of the final lift prior to testing,
for all tests. Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
ACTIVITY BEING INSPECTED: Concrete delivery and placement.
ITEM BEING CONSTRUCTED: Elevated sidewalk footing and wall
DETAILED LOCATION: West side of 75th Place West between G.L. 44+00 to 45+00
TYPE OF INSPECTION: Continuous
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: The concrete was being placed by tailgating. Consolidation
was accomplished with a concrete vibrator.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's 'Field and Laboratory Concrete Test Report'
for Set C-5 for a summary of inspection and test data.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in.
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA was able to observe both the lift placement and the compaction application of the final lift only prior to testing, for
all tests. HWA did not observe any lift placements or compaction applications between approximately -2' to -8' from top
of grade.
Total time charged to the job -for this visit is 6.5 hours including report writing.
SIGNATURES-
Signed: / Reviewed:�!'.o�s
HWA Field Representative HWA Project Engineer or
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer.
t
Page 1 of 2
19730-64th Avenue West, Suite 200
Uimm
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-026
Date (mm/dd/yy):
12/2812009
HWA Project No.:
2006-171-21
HWA Task No.:
500
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PR(11F(`T IhAPRr)\/F1IAFMT TF^gTFII cpp grrmmgnvinrn fiplrl rannrf
Test
No.
Detailed Test Location
Elev'n
or
Depth
B.G.—
Probe
Depth
(in)
ILab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens.
Opt.
Moist.
Over
Size %
Total
pcf
Dry
pcf
Moist.
%
Field
%
Spec
%
1
Station 16+00 4ft North of Culvert
pipe and 2ft East of back of block
T. 0. W
8"
AG-2
143.5
5.1
23
140.0
131.4
6.6
92
95
2
Station 16+00 4ft South of Culvert
pipe and 2ft East of back of block
T.O.W
8"
AG-2
143.5
5.1
23
145.9
137.4
6.2
96
95
3
Station 16+00 Eft North of Culvert
pipe and 2ft East of back of block
T O.W
8"
AG-2
143.5
5.1
23
144.4
136.8
5.6
95
95
4
Station 16+00 6ft South of Culvert
pipe and 2ft East of back of block
T.O.W
8"
AG-2
143.5
5.1
23
144.5
136.2
6.1
95
95
5
Retest of Test Number 1
T 0. W
8"
AG-2
143.5
5.1
23
144.4
135.9
6.3
95
95
6
7
8
9
10
11
12
13
Test Method X ASTM D2922/133017 (soil) ASTM D2950 (asphalt) Other:
Dosimeter: x Troxler 3440 . Troxler 3430 Troxler 3411-B CPN MCI-DR-P
Serial #: 28433 Density Standard Count.: 2154 Moisture Standard Count: 704
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 2
19730-64th Avenue West, suite 200
ULynnwood,\ `'C'; WA 96036
L
Field Report No.:
Date (mm/dd/yy):
FR-027
1212912009
Tel.42sa74-0106
HWA Project No.:
2006-171-21
HWAGECISCIENCES INC. Fax.425-774-2714
HWA Task No.:
500
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Clear
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
I-ILLU Kt:VUK 1
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 7:20 Arrived at Site: 7:30 Departed Site: 8:20 End.Travel: 8:30
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: HWA was on site to collect the test
cylinders cast on 12/28/2009 (designated C-5) and transport them to HWA's Lynnwood laboratory.
Total time charged to the job for this visit is 1.0 hours including report writing.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: Upon arrival I noticed that HWA's cure box
containing four concrete test cylinders had been slightly moved from original flat level surface to uneven ground. After
further inspection of concrete test cylinders at HWA lab, it is noted that the test cylinders will need to be capped to fill in
voids on top of cylinders prior to strength test.
SIGNATURES:
Sighed. i� Reviewed: r P
HWA Fiel pres ntative HWA Project Engineer or w
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer.
Page 1 of 1
19730-64th Avenue West, suite 200
ULTAl Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-028
Date (mm/dd/yy):
1/4/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400 f
Project Name
Location or Address of Project
Permit No. .
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather.
City of Edmonds
Jaime Hawkins
Rain
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
r-IGILv r«rvr�
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 8:20 Arrived at Site: 8:30 Departed Site: 10:20 End Travel: 10:30
Start Travel: 15:20 Arrived at Site: 15:30 Departed Site: 16:20 End Travel: 16:30
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use as modular block wall backtill .
GENERAL LOCATION: Modular block wall located in the park on the West side of 75th & 76th .place at station 32+75
and 33+25.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the.attached'Field
Compaction Test Report'.
TYPE OF INSPECTION: Periodic
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials were
placed in approximately 12" lifts uncompacted thickness and compacted with a plate compactor and a small double
drum vibrating roller.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached `Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
Total time charged to the job for this visit is 3.0 hours including report writing.
SIGNATURES:
Signed: Reviewed:
HWA Field Representative HWA Project Engineer or Reviewe
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
Ll
g e 1 of 2a '
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. P
t
19730-64th Avenue West, Suite 200
y, Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774.2714
Field Report No.:
FR-028
Date (mm/dd/yy):
1/4/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th_PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Rain
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
rrr.Trm iinrr fi-1,4 rnnnrf
NKUjLU
Test
No.
I rtvtrMUvr=iw[Z1'41 1 CO 1 w.
Detailed Test Location
QGG
Elev'n
or
Depth
B.G."
Probe
Depth
(in)
Lab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens. I
Opt.
Moist.
Over
Size %
Total
pcf I
Dry
pcf
Moist.
%
Field
%
Spec
%
1
Station 32+75, 10' East of block wall
T.O.W
8"
AG-2
143.5
5.1
23
145.6
136.8
6.5
95
95
2
Station.33+00, 10' East of block wall
T.O.W
8"
AG-2
143.5
5.1
23
146.4
136.7
7.1
95
95
3
Station 33+25, 15' East of block wall
T O.W
8"
AG-2
143.5
5.1
23
145.3
136.6
6.4
95
95
4
Station 33+00, 12' East of block wall
T.O.W
8"
AG-2
143.5
5.1
23
144.7
135.8
6.6
95
95
5
6
7
8
9
10
11
12
13
Test Method X ASTM D2922/D3017 (soil) - AS I M uzgbu taspnany . LIIUI.
Dosimeter: x Troxler 3440 Troxler 3430 Troxler 3411-B CPN MC1-DR-P
Serial #: 29276 Density Standard Count.: 2787 Moisture Standard Count: 729
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. —Depth B.G. indicates depth below grade. Grade means the design finish grade of the
' current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 2
ULWA 19730-84th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
fWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-029
Date (mm/dd/yy):
1/5/2010
HWA Project No.:
2006-171-21
HWA Task No.:
500
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
I
HWA Field Representative
Precision Earthworks
I Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 07:20 Arrived at Site: 07:30 Departed Site: 09:20 End Travel: 09:30
Start Travel: 10:50 Arrived at Site: 11:00 Departed Site: 13:50 End Travel: 14:00
ACTIVITY BEING INSPECTED: Excavation of soil.
GENERAL LOCATION OR AREA: SMH3 at Station 15+44 and 80' South to Station 14+00.
DETAILED LOCATION: 12" Storm pipe trench on the East shoulder of 75th Ave between SMH3 and 80' South to
Station 14+00.
TYPE OF INSPECTION: Continuous
CONTRACTOR ACTIVITIES RELATED TO THIS ITEM: Excavated trench area measured 80'x2'x3'
HWA ACTIVITI ES RELATED TO THIS ITEM: HWA carried out visual observation of the excavation. When necessary,
the sidewalls and base of the excavation were probed with a 1/2" diameter steel T-handled probe to confirm that
unsuitable soils had been removed, and that'only suitably firm soils remain.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
ACTIVITY BEING INSPECTED: Compaction of AG-2 CSBC for use -as trench backfill.
GENERAL LOCATION: SMH3 at Station 15+44 and 80' South to Station 14+00.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field
Compaction Test Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials were
placed in approximately 12" lifts uncompacted thickness and compacted with a Case 580 backhoe:
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report'.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
11
L�
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA observed the contractor place 1" of bedding, consisting of 1 1/4 gravel under 12"storm pipe, followed by 12" lift of ,
CSBC over and around the 12" storm pipe. Compaction was obtained using a Case 580 backhoe with medium pressure
on the first lift covering storm pipe. More compactive effort was exerted on the remaining lift causing the backhoe
outriggers to come off the ground.
Total time charged to the job for this visit is 5.0 hours including report writing
SIGNATURES:
Signed: Reviewed:
HWA FielpY ,p esent tive HWA Project Engineer or Re 'e*er '
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. I Page 1 of 3 1
F
19730-64thAvenue West, suite200 Field Report No.:. FR-029
Lynnwood, WA 98036 Date (mm/ddlyy): 1/5/2010
Tel.425-774-0106 HWA Project No.: 2006-171-21
HWVAGEOSCIENCES INC. Fax. 425-774-2714 HWA Task No.: 500
i
I
I
i
I
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
None at this time.
i
1
l
1
' This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 3
19730-64t
Lynnwood, Avenue West, Suite 200
ULWI I
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-029
Date (mm/dd/yy):
1/5/2010
'
HWA Project No.: 2006-171-21
HWA Task No.: 500
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Bent
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast/Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I ]Brian
Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PPr) [Pf'T IMPRCI\/FMFNT TFRTFIT .cep irrmmnanvinrn fplrl rPnnrf
Test
No.
Detailed Test Location
Elev'n
or
Depth
B.G."(in)
Probe
Depth
Lab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
# I
Max.
Dens.
Opt.
Moist.
Over
Size %
Total
. pcf
Dry
pcf
Moist.
%
Field
%
Spec
1
6ft South of SMH 3
-12"
8"
AG-2
143.5
5.1
23
145.3
136.5
6.5
95
95
2
60ft South of SMH 3
-12"
8°
AG-2
143.5
5.1
23
145.1.
136.9
6.0
95
95
3
12ft South of SMH 3
T.O.G
8"
AG-2
143.5
5.1
23
146.2
137.1
6.7
96
95
4
32ft south of SMH 3
T. O. G
8"
AG-2
143.5
5.1
23
143.7
136.3
5.5
95
95
5
40ft south of SMH 3
T O. G
8"
AG-2
143.5
5.1
.23
146.2
137.3
6.5
96
95
6
52ft south of SMH 3
T 0. G
8"
AG-2
143.5
5.1
23
144.6
136.6
5.9
95
95
7
8.
9
10
11
12
13
Test Method X ASTM D2922ID3017 (soil) ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 _Troxler 3430 Troxler 3411-B CPN MC1-DR-P
Serial #: 29276 Density Standard Count.: 2888 Moisture Standard Count: 819
*Lab Control: Standard Proctor x Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and.elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
it
'I
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 3 of .3
F
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
ULWA
Tel. 425-774-0106
fMAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-030
Date (mm/ddfyy):
1/6/2010
HWA Project No.:
2006-171-21
HWA Task No.:
500
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast]Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks I
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 01:20 Arrived at Site: 01:30 Departed Site: 15:20 End Travel: 15:30
ACTIVITY BEING INSPECTED: Excavation of soil.
GENERAL LOCATION OR AREA: Park Area, 2 to 4 man rock wall
DETAILED LOCATION: Between 10' and 20' West of park retaining wall at station 31+75
TYPE OF INSPECTION: Continuous
CONTRACTOR ACTIVITIES RELATED TO THIS ITEM: Excavated 2 to 4 man rock wall area located_ in the park
measured approximately 30'x30'x3'.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation of the excavation. When necessary,
the sidewalls and base of the excavation were probed with a 1/2" diameter steel T-handled probe to confirm that
unsuitable soils had been removed, and that only suitably firm soils remain.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
Total time charged to the job for this visit is 3.0 hours including report writing.
SIGNATURES:
Signe ,, 14, Reviewed:
HWA Field kepre�entative HWA Project Engineer or Revf er
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
19730-64th Avenue West, Suite 200
ULTV
Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Project Name Emonds.
ation or Aaaress c
76th Ave W/75th PI W Walkway WA
City of Edmonds liaime Hawkins
Minn Authoritv (enaineer or architect of record) IDesign Authority Repr
Precision Earthworks
Field Report No.: FR-031
Date (mm/dd/yy): .111312010
HWA Project No.: 2006-171-21
HWA Task No.: 500 .
Permit No.
Weather
Overcast/Cool
HWA Project Manager
Tony Martin
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 0820 Arrived at Site: 0830 Departed Site: 1145 End Travel: 1155
Martin
ACTIVITY BEING INSPECTED: Welding.
GENERAL LOCATION: Southern end of the elevated walkway.
DETAILED LOCATION: South end of elevated walkway.
TYPE OF INSPECTION: Periodic
DETAILS OF PLACEMENT OF THIS MATERIAL' The 3/8"x 3.5" continuous (approximately 12 feet lengths) Flat Bar
was being welded and/or tacked in place to the top of the 2" pipe piles to facilitate the upcoming placement of the
elevated precast concrete panels.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA verified the welders certification (John P. Flynn
WABO ID # W11696, expires April 1, 2010). Welding rod was verified to be 1/8" E7018 to/hi by Lincoln Electric and a
portable rod oven was on site. Electrode was transferred from a hermetically sealed container and placed into the rod
oven for storage until needed Welding complied with drawing S-7 and AWS D1.1 Code.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: Only the first pipe.pile at the far south end
of the proposed elevated walkway was welded to the Flat Bar. The contractor chose to tack weld the remaining pipe
piles to the Flat Bar until after delivery of the precast concrete panels.
Total time charged to the job for this visit is 4.0 hours including report writing.
SIGNATURES: ,
Signed. Reviewed: �-
HWA Fi d prese ltative HWA Project Engineer "r vi er
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
F1
Pa e1of1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
19730-64th Avenue West, Suite 200 Field Report No.: FR-032
Lynnwood, WA 98036 Date (mm/dd/yy): 112912010
�� Tel. 425-774-0106 HWA Project No.: 2006-171-21
HWAGEOSCIENCES INC. Fax.425-774-2714 HWA Task No.: 500
Project Name Location or Address of Project Permit No.
76th Ave W/75th PI W Walkway Edmonds, WA
client client Representative Weather
City of Edmonds Jaime Hawkins overcast/Cool
Design Authority (engineer or architect of record) Design Authority Representative HWA Project Manager
Ton Martin
General Contractor General Contractor Representative HWA Field Representative
Precision Earthworks FIELD REPORT Alix Rackleff
L
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 1220 Arrived at Site: 1230 Departed Site: 14011 End Travel: 1410
' ACTIVITY BEING INSPECTED: Concrete delivery and placement.
ITEM BEING CONSTRUCTED: Elevated sidewalk wall repair and retaining wall on the southern side of the walkway.
DETAILED LOCATION: West side of 75th Place West.
TYPE OF INSPECTION: Continuous
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: The concrete was being placed by tailgating. Consolidation
was accomplished with a concrete vibrator.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's 'Field and Laboratory Concrete Test Report'
for Set C-6 for a summary of inspection and test data.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
-The contractor ordered concrete mix 1997 from Cal Portland for constructing the elevated sidewalk wall repair and
connecting wing wall footing. Ed with the City of Edmonds was informed, he stated that mix 1997 was an approved
-concrete mix and that the elevated sidewalk wall repair and connecting wing wall footing had a specified minimum of
3000 psi that had been recently approved by an engineer.
S -A 10' foot section of concrete forming had blown out during concrete placement. Ed was notified and he indicated that
he was in -transit to the jobsite and that he did not require my presence to observe the form repair or the remaining
placement of concrete.
Total time charged to the job for this visit is 2.5 hours including report writing.
SIGNATURES:
Signed:
HWA Field Representative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
E
Reviewed:
HWA Project Engineer or Reviewer
I until signed b HWA field representative and HWA reviewer. Page 1 of 1
This report should only be reproduced in its entirety. Report is not final 9 Y
19730-64th Avenue West, Suite 200
• as Lynnwood, WA 98036
1 Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA
Client Client Representative
City of Edmonds Jaime Hawkins
naaian Authority (enoineer or architect of record) Design Authority Repr
Precision Earthworks
Field Report No.:
FR-033
Date (mm/dd/yft
1/30/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400 .
Overcast/Cool
HWA Project Manager
Tony Martin
HWA Field Represents
Alix Rackleff
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 1200 Arrived at Site: 1210 Departed Site: 1220 End Travel: 1230
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
A site visit was made to obtain cylinder set C-6 cast on 1 /29/10. The cylinders were transported to our office in
Lynnwood for testing.
Total time charged to the job for this visit is 1.0 hours including report writing.
SIGNATURES:
Signed:a.,
HWA Field Representative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
Reviewed:
HWA Project Engineer or Reviewer
1 of1 '
This report should only be reprbduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page
C
J
1,
I
19730-6411 Avenue West, Suite 200
=; Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-034
Date (mm/ddlyy):
2/17/2010
HWA Project No.:
2006-171-21
HWA Task No.:.
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Sunny, 50-55F
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Kimberly Swanson
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 1345 Arrived at Site: 1415 Departed Site: 1445 End Travel: 1530
ACTIVITY BEING INSPECTED: Excavation of unsuitable soils/Preparation of bearing soils.
ITEM BEING CONSTRUCTED: Walkway/Sidewalk stairs at new park
DETAILED LOCATION: South end of park next to existing roadway
TYPE OF INSPECTION: Periodic
STATUS AND DETAILS OF CONSTRUCTION: At the time of inspection, the stairs/walkway section had been over -
excavation by 12-inches per Mo (Superintendant) of Precision Earthworks. Placement of concrete is scheduled for .
tomorrow morning.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and probing with a 1/2" diameter steel
T-handled probe to check for areas of soft, loose, disturbed or otherwise unsuitable soils. Several areas along the slope
were probed. Resistance was met at approximately 18-inches to 24-inches. Soil is wet, sandy and silty, with organic
materials, e.g. plant roots, chunks of tree trunks and branches and a section of railroad tie.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in non-
conformance with approved plans, specifications and RFIs. I notified Mo of Precision Earthworks and Bryan Hawkins,
HWA GeoSciences project engineer. Based on conversations with Bryan Hawkins, Mo will excavate an additional 24
inches, put down a geotextile separation fabric and backfill with CSBC. Mo also canceled the concrete placement
scheduled for the morning of 2/18/10.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
Total time charged to the job for this visit is 2.5 hours including report writing.
SIGNATURES: —
Signed: Reviewed:
HWA Field/Representative HWA Project Engineer o Re wer
SUMMARY OF UNRESOLVED ISSUES
' Report# Item# Status
FR-034 1 Unresolved at this time - unsuitable bearing soils for new walkway sidewalk/stairs at south end of
park.
' This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
HWAGEOSCIENCES INC.
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
tTel. 425-774-0106
Fax. 425-774-2714
Field Report No.:
FR-035
Date (mm/dd/yy):
2/23/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI.W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast, Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
i
HWA Field Representative
Precision Earthworks
Matthew Spenner
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 0900 Arrived at Site: 0930 Departed Site: 1615 End Travel: 1645
ACTIVITY BEING INSPECTED: Excavation of unsuitable soils/Preparation of bearing soils, Welding.
ITEM BEING CONSTRUCTED: Walking. paths and Swing foundations
DETAILED LOCATION: Park area elevation 40.9 ft., south end through north end/Elevated Walkway
TYPE OF INSPECTION: Continuous
STATUS AND DETAILS OF CONSTRUCTION: Precision Earthworks was engaged in removal of unsuitable material
and backfilling with CSBC.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and probing with a 1/2" diameter steel
T-handled probe to check for areas of soft, loose, disturbed or otherwise unsuitable soils. Several areas along the above
elevation were probed and found to be unsuitable, the probe sank nearly entire length before hitting resistance. HWA
observed removal of this material to a level of minus eight inches and placing of CSBC backfill per HWA engineer
recommendations. HWA also observed in progress welding of pin pile to embed plates on the elevated walkway precast
panel.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the removal of unsuitable material was
found in conformance with approved. plans, specifications and RFIs. The welding inspected at the elevated walkway was
in progress and no conformance statement can be made at this time.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
The welder who performed the welding at the elevated walkway was Theodore L. Rapp, WABO #W01455. There were
several pile splices to be welded. I informed Mr. Rapp as well as Mo from Precision Earthworks that an RFI will be
needed for these splices as they are not specified in the contract drawings. It was also determined that Mr.Rapp will
need to qualify to the diameter of pipe and position used in these splices and submit a weld procedure specification for
these welds.
Total time charged to the job for this visit is 8.5 hours including report writing.
SIGNATURES:
Signed: .�"�— Reviewed: —'
HWA Field Representativ HWA Project Engineer or Revje er
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-034 1 Unresolved at this time - unsuitable bearing soils for new walkway sidewalk/stairs at south end of
park.
�I
I
P
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1 '
1
,. ;
19730-64th Avenue West, Suite 200
Lynnwood, WA 98036
Tel. 425-774-0106
'
HWAGEOSCIENCES INC.
Fax.425-774-2714
Project Name
Location or Address of Project
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA.
lient
Client Representative
City of Edmonds
Jaime.Hawkins
'
Design Authority (engineer or architect of record)
Design Authority Representative
General Contractor 77::IG!en�era:1C�ontreictorentative
—
Precision Earthworks
1
Field Report No.:
FR-036
Date (mm/dd/yy):
2/2412010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Overcast, Cool
HWA Project Manager
TonV Martin
Matthew Spenner
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
First Site Visit: Start Travel: 0800 Arrived at Site: 0815 Departed Site: 1500 End Travel:1530
ACTIVITY BEING INSPECTED: Placement and Compaction of CSBC.
ITEM BEING CONSTRUCTED: Walking paths and Grass area
DETAILED LOCATION: Park area elevation 40.9 ft., south end through north end.
TYPE OF INSPECTION: Continuous
STATUS AND DETAILS OF CONSTRUCTION: Precision Earthworks was engaged in the placement and compaction of
CSBC material.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA observed placement and performed nuclear density tests on CSBC
material placed at the above locations.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the placement and compaction of the
CSBC material,was found in conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
As requested, HWA performed nuclear compaction tests at finished sections of designated walk way and.grass area
sub -grade. Precision Earthworks placed CSBC in approximately six inch lifts and compacted each layer with a Bomag
142 D-2 vibratory compactor.
Total time charged to the job for this visit is 7.5 hours including report writing.
'SIGNATURES:
Signed: u/ Reviewed.
HWA Field Representative HWA Project Engineer og ewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-034 1 Unresolved at this time -unsuitable bearing soils for new walkway sidewalk/stairs at south end of
park.
I Page 1 of 2
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
19730-64th Avenue West, Suite 200 Field Report No.: FR-036
Lynnwood, WA 98036 Date (mm/dd/yy): 2/24/2010
Tel. 425-774-0106 HWA Project No.: 2006-171-21
.HWAGEOSCIENCES INC. Fax. 425-774-2714 HWA Task No.: 400
Project Name
Location or Address of Project
Permit No.
76th Ave W175th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
bent Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast, Cool
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
I
Matthew Spenner
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED: see accompanying field report
Test
No.
Detailed Test Location
Elev'n
or
Depth
B.G."
Probe
Depth
(in)
Lab Control*
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Density
Moist.
ID
#
Max.
Dens.
Opt.
Moist.
Over
Size %
Total
pcf
Dry
pcf
Moist.
%
Field
%
Spec
%
1
Center of grass area
T.O.R
10
AG-2
143.5
5.1
23
136.5
132.2
3.3
92
95
2
Swing set area
T.O.R
10
AG-2
143.5
5.1
23
135.6
130.9
3.9
91
95
1A
Retest of Center of grass area
T.O.R
12
AG-2
143.5
5.1
23
140.6
136:4
3.1
95
95
2a
Restest of Swing set area
T.O.R
12
AG-2
143.5
5.1
23
140.2
135.7
3.3
95
95
3
North side of walkway
T.O.R
10
AG-2
143.5
5.1
23
140.2
136.0
3.0
95
95
4
West side of walkway
T.O.R
10
AG-2
143.5
5.1
23
140.9
136.7
3.1
95
95
5
North east side of walkway
T.O.R
10
AG-2
143.5
5.1
23
142.1
138.3
2.7
96
95
6
7
8
9
10
11
Test Method X ASTM D2922/D3017 (soil) ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-B CPN MC1-DR-P
Serial #: 29279 Density Standard Count.: 2501 Moisture Standard Count: 625
*Lab Control: Standard Proctor X Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Matthew Spenner Reviewed By: Tony Martin
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 2 of 2
21312 30th Drive SE Suite 110
,►
Bothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC.
Fax.425-774-2714
1
7
L
F
L_
n
P
Project Name
76th Ave W/75th PI W Walkway and
162nd St SW Project
Client
City of Edmonds
Design Authority (engineer or architect of record)
General Contractor
Precision Earthworks
Location or Aaaress Or
Edmonds, WA
Client Representative
Jaime Hawkins
Design Authority Repr
General Contractor Ri
Moe
Field Report No.:
Date (mm/ddlyy):
HWA Project No.:
HWA Task No.:
Sunny, 52F
Martin
Brian Coker
FR-037
31ll/2010
2006-171-21
400
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 09:30 Arrived at Site: 10:00 Departed Site: 1200 End Travel:1230
ACTIVITY BEING INSPECTED: Preparation of Bearing Soils.
ITEM BEING CONSTRUCTED: Gravity Block Retaining Wall.
DETAILED LOCATION: West side of park behind pump house and 75 feet north. Approved plans do not give specific
gridline.
TYPE OF INSPECTION: Periodic
e
STATUS AND DETAILS OF CONSTRUCTION: At the timof our inspection, the native soils excavation had been
feet in length of excavation on the West side of the park had
discontinued until HWA's observation. A 5 feet wide by 75
been`completed.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and probing with a 6 feet, 1/2 inch
diameter steel T-handled probe to check for areas of soft, loose, disturbed or otherwise unsuitable soils.
CONFORMANCE OF THIS ITEM: The soil inspected was found to consist of very loose saturated silty clay like material
and is unsuitable for the intended purpose.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
As requested by City of Edmonds representative, Jaime Hawkins, HWA made a site visit to perform a subgrade soil
inspection on the excavation along the West side of the park behind the pump house for the retaining wall. Based on the
depth the T-handle probe penetrated the soils (4-feet) and conversations with the engineer, it is HWA's recommendation
that the existing native soils be over excavated 4 feet deep.by 5 feet wide and place a 2 foot base of compacted 6"x 8"
spalls followed by 1 foot of 2"x 4" spalls covered by fabric and compacted CSBC.
Total time charged to the job for this visit is 2.5 hours including report writing.
SIGNATUR;F'
S:
Signe -%�'� ' VIA
HWA Rieprdsentative
Reviewed: /
HWA Project Engineer or Reviewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-034 1 Resolved: This item was resolved by the contractor over -excavating the unsuitable soils and
placement of structural fill per HWA recommendations on 2/17/10.
1. Pa e1of1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
HWAGEOSCIENCES INC.
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel,425-774-0106
Fax.425-774-2714 a
Field Report No.:
FR-038
Date (mm/dd/yy):
313//2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Protect Name
Location orAddress of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
lient
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast, 48F
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 11:30 Arrived at Site: 12:00 Departed Site: 13:00 End Travel:14:00
ACTIVITY BEING INSPECTED: Placement of Reinforcing Steel.
ITEM BEING CONSTRUCTED: Stairs and landing on the South side of the park area.
DETAILED LOCATION: Stairs and landing on the South side of the park area. (Approved plans do not give specific
gridline)
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: This was a preliminary inspection prior to closing formwork. A final
inspection is required once rebar and formwork is complete.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and measurements to
confirm bar sizes, number of bars, correct placement, and adequate cover.
1
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in I
conformance with approved plans, specifications and RFIs. .
Total time charged to the job for this visit is 2.5 hours including report writing. '
SIGNATURES:
Signe T/R� Reviewed:
HWA Fie epres ntative HWA Project Engineer or Re4j er
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
None at this time.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1 ,
H
11
7
ULT""AA
HWAGEOSCIENCES INC.
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
Fax.425-774-2714
Field Report No.:
FR-039
Date (mm/dd/yy):
. 3/412010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Bent
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast, 52 degrees
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Moe
Matthew Spenner
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 0830 Arrived at Site: 0900 Departed Site: 1000 End Travel:1030
ACTIVITY BEING INSPECTED: Welding Inspection.
ITEM BEING CONSTRUCTED: Elevated walkway.
DETAILED LOCATION: 75th Ave stations 44+00 through 45+00
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: Welding was presented as complete.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual welding inspection of pile to embed
plate connections at the above locations.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list below.
Item"I - Unacceptable welds have been observed at the elevated walkway pile to embed connections, 75th Ave stations
44+00 through 45+00. The welds at these location were painted prior to visual inspection and numerous welds appeared
to exhibit lack of fusion, excessive porosity, and were undersized. All coatings will need to be removed and.welds will
need to be ground and rewelded, or have additional weld metal deposited in conformance with AWS D1.1 and the
contract documents. -
The contractor and client have been informed of the condition of welding at this location. The welder, Theodore L.
Rapps WABO cert#W01455, has also been informed.
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURE
HWA Field Representative MATHEW M. SKINER
CWl M4061
Reviewed:
HWA Project Engineer or Kewewer
SUMMARY OF UNRESOLVED I ' S QC1 EP 04MVIT
Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, 75th Ave stations 44+00 through 45+00. These welds will need to be removed of all coatings and
unacceptable material, and rewelded in conformance to AWS D1.1 and the contract documents.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Pag@ 1 of 1
ULMA
HWAGEOSCIENCES INC.
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
Fax.425-774-2714
Field Report No.:
FR-040
Date (mm/dd/yy):
3/10112010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast, 42F
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 11:30 Arrived at Site: 11:45 Departed Site: 12:15 End Travel:12:30
ACTIVITY BEING INSPECTED: Placement of Reinforcing Steel.
ITEM BEING CONSTRUCTED: Stairs and landing on the South side of the park area..
DETAILED LOCATION: Stairs and landing on the South side of the park area. (Approved plans do not give specific
gridlines.)
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: This was follow up inspection. A final inspection is required once
rebar and formwork is complete. This is a preliminary re -inspection after onsite meeting modifications approved by the
City of Edmonds.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and measurements to
confirm bar sizes, number of bars, correct placement, and adequate cover.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list below.
Item 1 - Rebar and formwork that were previously inspected and approved in Field. Report FIR 038 are now in non-,
conformance with the approved plans. Rebar within the forms is now indirect contact with. the ground, the formwork and
rebar for the two landings between the three sections of stairs, have been removed. Precision Earthwork representative
Mo was advised of the non-conformance issues. No corrective action was taken at the time.of my visit.
Total time charged to the job for this visit is 1.0 hours including report writing.
SIGNATURES:
v �
Signed. 4�i /J�//�� Reviewed: �11
HWA 2�Aeprlesentative HWA Project Engineer or Fke sewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, 75th Ave stations 44+00 through 45+00. These welds will need to.be removed of all coatings and
unacceptable material, and rewelded in conformance to AWS D1.1 and the contract documents.
FR-040 1 Unresolved at this time - Rebar and formwork must be placed in accordance with approved plans and
specifications prior to concrete placement along with a final re -inspection and acceptance.
I
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
I
h
ULWA
HWAGEOSCIENCES INC.
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
Fax.425-774-2714
Field Report No.:
FR-041
Date (mm/dd/yy):
3/1612010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Bent
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast, 52 degrees.
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative.
HWA Field Representative
Precision Earthworks
Moe
Matthew Spenner
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 0900 Arrived at Site: 0915 Departed Site: 1000 End Travel:1030
ACTIVITY BEING INSPECTED: Welding Inspection.
ITEM BEING CONSTRUCTED: Elevated walkway.
DETAILED LOCATION: 75th Ave stations 31+88 through 34+35
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: Welding was presented as in progress.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual welding inspection of flat bar to
embed plate 3116" fillet weld connections at the above locations.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFls, with the exception of any non-conformance items list below.
Upon arrival, it was observed that slag had not been removed from the completed fillet welds at the above locations. I
informed Moe with Precision Earthworks that all slag would have to be removed before final inspection can be made.
There were no welds inspected for acceptance today.
Total time charged to the job for this visit is 2.0 hours including report writing.
ISIGNATUR
HWA FiNd Representativ MATHEW M. SPINNER
rf CWI 09040161
r /'!
Reviewed:
HWA Project Engineer or r
SUMMARY OF UNRESOLVED;F.I9SUESKI Fft.Q0V1J
Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, 75th Ave stations 44+00 through 45+00. These welds will need to be removed of all coatings and
unacceptable material, and rewelded in conformance to AWS D1.1 and the contract documents.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
19730-64th Avenue West, Suite 200
�1A Lynnwood, WA 96036
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Location or Address c
Project Name
76th Ave W/75th PI W Walkway Edmonds, WA
City of Edmonds
Jaime Hawkins
Field Report No.: FR-042
Date (mm/ddlyft 3/1612010
HWA Project No.: 2006-171-21
HWA Task No.: 400
TPermit.
ast/Cooi
design Authority (engineer or architect of record) uesign HurnunLY n-F'
. LH
ony Martin
General Contractor Representative WAField Representative
3eneral Contractor rian Coker
Precision Earthworks FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 08:00 Arrived at Site: 08:10 Departed Site: 14:50 End Travel: 15:00
ACTIVITY BEING INSPECTED: Class 1/2" HMA Asphaltic Concrete Pavement delivery, placement, and compaction. .
GENERAL LOCATION: Driveways on 75th and 76th Avenue West.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached `Field
Compaction Test Report'.
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: The HMA was placed using wheelbarrows. Compaction was applied
using a 5-ton DD28HF vibratory steel break -down roller, and a finish roller.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation, periodic temperature
monitoring, and compaction testing of the completed pavement. Compaction test results are summarized on the
attached 'Field Compaction Test Report'. A sample of the HMA mix was sampled from the haul vehicle on site. It is my
understanding that the HMA mix was obtained from Cemex plant in Kenmore.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list below.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: Cumulative Quantity of 112" HMA is 26.04
tons.
Total time charged to the job for this visit is 6.0 hours including report writing.
SIGNATURES:
Signed:
HWA Field Representative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
Reviewed:—
HWA Project Engineer or er
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, 75th Ave �ations mater a� and hewelded+00 trough 5 n00. onfoese mancelds will need to be to AWS D1 1 andthe
removed
of all coatings and unacceptable
contract documents.
�J�
11
LI
L
D
Pa e 1 of 2
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
' 19730-64th Avenue West, Suite 200
A ; Lynnwood, WA 98036
Tel. 425-774-0106
HWAGEOSCYENCES INC. Fax.425-774-2714
Location or ddress of Project
Field Report No.:
FR-042
Date (mm/dd/yy):
3/1612010
HWA Project No.:
2006471-21
HWA Task No.:
400
76th Ave W/75th PI W Walkway Edmonds, WA
C lent Representative Weather
Client overcast/Cool
City of Edmonds Jaime Hawkins
HWA Project Manager
Design Authority (engineer or architect of record) Design Authority Representative Tony Martin
General Contractor General Contractor Representative HWA Field Representative
Precision Earthworks Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
PROJECT IMPROVEMENT TESTED: see accompanying field report
Lab Control". Field Test
Relative
Compaction
Field Spec
� o
% °
EIII ev'n
or Probe (Proctor/Rice/Marshall) Density Moist.
Test Depth Depth ID Max. Opt. Over Total Dry Moist.
No. Detailed Test Location B.G." (in) # Dens. Moist. Size % pcf pcf %
North Lane of Driveway @ Station
1 26+25 on 75th Ave W,18ft East of T.O. G B/S "MA ? 54.6 142.3
92 91
Centerline
North Lane of Driveway @ Station 141.7
2 26+25 on 75th Avenue West, 12ft T.O. G B/S HMA 154. 6
92 91
East of Centerline
Residence Driveway @ 15806 on T.O.G B/S HMA 154.6 141.9
3 76th Ave West/See attached sheet
92 91
92 91
Residence Driveway @ 15806 on T.O.G B/S HMA 154.6 142.1
4 76th Ave West/See attached sheet
Residence Driveway @ 15806 on T.O.G B/S HMA 154,6 141.1
5 76th Ave West/See attached sheet
91 91
Residence Driveway @ 15806 on T.O. G B/S HMA 154.E 141.5
6 76th Ave West/See attached sheet
92 91
7 .
8
9
10
11
12
Test Method ASTM D2922/D3017 (soil) x ASTM D2950 (asphalt) Other:
Densometer: x Troxler 3440 _Troxler 3430 Troxler 3411-B CPN MCI-DR-P
Serial #: 37406 Density Standard Count.: 2809 Moisture Standard Count: 660
"Lab Control: Standard Proctor Modified Proctor
Asphalt Marshall Density x Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. ""Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
Pa e2of2
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. 9
ZZCC_MC_x
Northwest Division
P.O. BOX 2037, EVERETT, WA 98213 . (425) 355-2111
Ticket #
Date
Plant Plant Desc
Ticket Time
I.! ' IC,; r.") 10
'{l t f 11r1?t_}t;.5ofl-Iit
-1111
Zone Map ID
Project #
Job #
PO #
{tGI•Sc:�
Customer # Sold to
Truck #
it" T Nil . P.",tt
Delivery Addressii
Hauler/Truck Description
t CC 1 {{
I�'�<��'.e-dtrri?�.9t �-`cFtrf'E•;.,,atjt.
WeighMaster
Instructions
26
in 9
LOAD CUMULATIVE # OF PRODUCT PRODUCT UNIT
QUANTITY QUANTITY LOADS
AMOUNT
CODE DESCRIPTION PRICE
•I kel 1aw6... uk.S Pi_f ,., 1_'I'. ft F'` f
SUB -TOTAL
TAX TICKET
TOTAL
The undersigned promises to pay all costs, including reasonable
PROPERTY DAMAGE RELEASE (r0 BE SIGNED IF DELIVERY IS TO BE MADE INSIDE CURB LINE)
attorney's fees, incurred in collecting any sums owed.
Dear Customer. The driver of this truck is presenting this RELEASE to you for your signature is of the opinion that the size and weight of his truck
may possibly cause damage to the premises and/or adjacent property if he places the material in this load where you desire it. It is our wish to help
All accounts not
o aid within 30 days of delivery i e will bear interest
p y ry
you in eve wa that we can, but ( r a u n order to do this the driver is requesting that u sign
Y it Y o n this RELEASE him and this supplier from
9 9 man
Y 9 9 PP Y
from
at the rate of 180/o per annum.
res onsibili an damage that m occur th s, drain
p ry Y 9 may ccu W e premises and/or adjacent property,.builtlings, sidewalks, drive -ways, curbs, etc by the delivery
of this material and that you also agree to help him remove mud from the wheels of his vehicle so that he will not litter the public street. Further, as
additional consideration, the undersigned agrees to indemnify and hold harmless the driver of this truck and this supplier for any and all damage to
Not Responsible for Reactive Aggregate or Color Quality. No
the premises and/or adjacent property which may be claimed by anyone to have arisen out of delivery of this order.
SIGNED
Claim Allowed Unless Made at Time Material is Delivered.
A $40.00 Service Charge and Loss of the Cash Discount will be
. o . • -
11 10
collected on all Returned Checks.
LOAD RECEIVED BY:
Standby
Time Initials
X
AUTHORIZED SIGNATURE
065'5
ir�I
HWAGEOSCIENCES INC.
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
Fax. 425-774-2714
Field Report No.:
FR-043
Date (mm/dd/yy):
3/18/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name.
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Sunny, 52F
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Moe
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 09:30 Arrived at Site: 10:00 Departed Site: 12:00 End Travel:12:30
ACTIVITY BEING INSPECTED: Preparation of Bearing Soils.
ITEM BEING CONSTRUCTED: Play structure footings in the North end of the park
DETAILED LOCATION: Play structure footings in the North end of the park. Approved plans do not give specific gridline
TYPE OF INSPECTION: Periodic
STATUS AND DETAILS OF CONSTRUCTION: At the time of our inspection, the native soils excavation had been
discontinued until HWA's observation. A 20 foot by 20 foot section was probed with a 112 inch diameter steel T-handle
probe on the North side of the park in the play structure area had been completed.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and probing with a 3 feet, 1/2 inch
diameter steel T-handle probe to check for areas of soft, loose, disturbed or otherwise unsuitable soils.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list below.
Item 1 - As requested by City of Edmonds representative, Ed Siebel, HWA made a site visit to perform a subgrade soil
inspection on the excavation along the North side of the park where the play structure is to be located. Based on the
depth the T-handle probe penetrated the soils (18-inches) and conversations with the engineer, the soil inspected was
found to consist of very loose saturated silty clay like material and is unsuitable for the intended purpose, it is HWA's
recommendation that the existing native soils be over excavated 18 inches by 20 feet by 20 feet and place a 18-inch
base of compacted CSBC.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
Total time charged to the job for this visit is 3.0 hours including report writing.
I�
SIGNATURES: Signed: _A/�
HWA Field Representative
Reviewed:
HWA Project Engineer or Reviewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, 75th Ave stations 44+00 through 45+00. These welds will need to be removed of all coatings and
unacceptable material, and rewelded in conformance to AWS D1.1 and the contract documents.
FR-040 1 Unresolved at this time - Rebar and formwork must be placed in accordance with approved plans and
specifications prior to concrete placement along with a final re -inspection and acceptance.
FR-043 1 Unresolved Unsuitable bearing soils for play structure footings at the North end of park.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
[i
'
��
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC.
Fax.425-774-2714
Project Name
Location or Address of Project
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
City of Edmonds
Jaime Hawkins
Design Authority (engineer or architect of record)
Design Authority Representati
Precision Earthworks
Moe
Field Report No.: ,
FR-044
Date (mm/ddlyft
3/19/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 09:00 Arrived at Site: 09:30 Departed Site: 11:00 End Travel:11:30
50F
Martin
Brian Coker
ACTIVITY BEING INSPECTED: Preparation of Bearing Soils.
ITEM BEING CONSTRUCTED: Play structure footings in the North end of the park
DETAILED LOCATION: Play structure footings in the North end of the park. Approved plans do not give specific gridline.
TYPE OF INSPECTION: Periodic
STATUS AND DETAILS OF CONSTRUCTION: At the time of our inspection, the native soils excavation had been
discontinued until HWA's arrival on site. A 20 feet wide by 20 feet in length area was probed with a 112 inch diameter
steel T-handle probe on the North side of the park, in the play structure area.
HWA ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and probing with a 3 feet, 1/2 inch
diameter steel T-handle probe to check for areas of soft, loose, disturbed or otherwise unsuitable soils.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list below.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: As requested by the City of Edmonds
representative, Ed Sibrel, HWA made a site visit to perform a rebar inspection for the play slide along the North side of
the park below the elevated sidewalk.
Total time charged to the job for this visit is 2.5 hours including report writing.
SIGNATURES: '
Sign
Reviewe 1 ✓
HWA 4ielepr enta iv HWA Project Engineer or Reviewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item#. Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
00 through 45+00. These welds will need to be removed
embed connections, 75th Ave stations 44+
of all coatings and unacceptable material, and rewelded in conformance to AWS D1.1 and the
contract documents.
F.R-043 1 Unresolved Unsuitable bearing soils for play structure footings at the North end of park.
' Page1of1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer.
21312 301h Drive SE Suite 110
jrLT" Bothell, WA 98021
Al Tel. 425-774-0106
HWAGECISCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-045
Date (mm/dd/yy):.
4/7/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Overcast, 50F
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Moe
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 14:00 Arrived at Site: 14:30 Departed Site: 15:00 End Travel: 15:30
ACTIVITY BEING INSPECTED: Placement of Reinforcing Steel.
ITEM BEING CONSTRUCTED: Play slide on the South side of the park area.
DETAILED LOCATION: Play slide and landing on the South side of the park area per revised detail 6 of L-17. (Approved
plans do not give specific gridline)
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: This was a preliminary inspection prior to closing formwork. A final
inspection is required once rebar and formwork is complete.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and measurements to
confirm bar sizes, number of bars, correct placement, and adequate cover.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: As requested by the City of Edmonds
representative, Ed Sibrel, HWA made a site visit to perform a rebar inspection for the -play slide along the South side of
the park below the elevated sidewalk.
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURES:
Signed:
HWA Field Representative
II
1�
Reviewed:
HWA Project Engi�orRr '
SUMMARY OF UNRESOLVED ISSUES '
Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, 75th Ave stations 44+00 through 45+00. These welds will need to be removed
of all coatings and unacceptable material, and rewelded in conformance to AWS D1.1 and the
contract documents.
FR-043 1 Unresolved: Unsuitable bearing soils for play structure footings at the North end of park.
This report should only be reproduced In its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1 I
D
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA
Client Client Representative
City of Edmonds Jaime Hawkins
nc¢inn Authority tenaineer or architect of record) Design Authority Repre:
Precision Earthworks JMoe
Field Report No.:
FR-046
Date (mm/ddlyy):
4/1212010
HWA Project No.:
2006-171-21
HWA Task No.:
400
JHWA
mit No.
ather
vercast, 50F
Project Manager
onv Martin
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 13:00 - Arrived at Site: 13:30 Departed Site: 14:30 End Travel:15:30
Brian Coker
ACTIVITY BEING INSPECTED: Preparation of Bearing Soils.
ITEM BEING CONSTRUCTED: Slide play area footings in the South end of the park.
DETAILED LOCATION: Slide area circular footings in the South end of the park. Approved plans do not give specific
gridline.
TYPE OF INSPECTION: Periodic
STATUS AND DETAILS OF CONSTRUCTION: At the time of our inspection, the native soils excavation had been
discontinued until HWA`s arrival on site. An over excavated area, 3 feet wide by 50 feet long by 3 feet in depth was
probed with a 1/2 inch diameter steel T-handle probe on the South side of the park in the slide structure area.
: HWA carried out visual observation and probing with a 4 feet, 1/2 inch
HWA ACTIVITIES RELATED TO THIS ITEMof soft, loose, disturbed or otherwise unsuitable soils.
diameter steel T-handle probe to check for areas
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list below.
Item 1 - Probing indicated that material was soft and unsuitable for the slide play structure footings at south end of Park
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
Total time charged to the job for this visit is 2.5 hours including report writing.
SIGNATURES:
Sign
HWA Fie d epre ntative
Reviewe .
HWA Project Engineer or Reviewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, 75th Ave stations 44+00 through 45+00. These welds will need to be removed
of all coatings and unacceptable material, and rewelded in conformance to AWS D1.1 and the
contract documents.
FR-040 1 Unresolved at this time - Rebar and formwork must be placed in accordance with approved plans and
specifications prior to concrete placement along with a final re -inspection and acceptance.
FR-643 1 Unresolved Unsuitable bearing soils for play structure footings at the North end of park.
FR-046 1 Unresolved Unsuitable bearing soils for slide play structure footings at the South end of park.
I
e 1 of 1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page
21312 30th Drive SE Suite 110 Field Report No.: FR-047
ULM
Bothell, WA 98021 Date (mm/dd/yy):4114/2010
Tel.425-774-0106 HWA Project No.: 2006-171-21
HWAGEOSCIENCES INC. Fax. 425-774-2714 HWA Task No.: 400
Project Name
Location or Haaress of nui-
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Weather
Client
Client Representative
Jaime Hawkins
Clear, 58 degrees
Cityof Edmonds
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Matthew Spenner
Precision Earthworks
Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON
PROJECT TODAY:
Start Travel: 0930 Arrived at Site: 1000
Departed Site: 1030 End Travel:1100
ACTIVITY BEING INSPECTED: Welding Inspection.
ITEM BEING CONSTRUCTED: Elevated walkway.
DETAILED LOCATION: 75th Ave stations 31+88 through 34+35
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: Welding was presented as complete in these locations.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual welding inspection of flat bar to
embed plate and pin pile to embed plate 3/16" fillet weld connections at the above locations.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any no items list below.
ive
Item 1: Unresolved at this time- Pile to embed fillet weld
ion
l need to bexrelmloved and eeweldednn conformancte to
areas were marked with yellow crayon. The defective areas w I
AWS D1.1 and the contract documents.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
Welding at these locations appeared to exhibit visually acceptable size, length, "and profile except at one location, station
31+90 pile to embed plate connection, in which unacceptable undercut was observed. This defect was marked with
yellow crayon. All other welding appeared to be visually acceptable per AWS D1.1 table 61 Y and figure 5.4, pand the
contract drawing general notes S-1. FCAW process was used. All weldingperformed erformed b Theodore RapWABO
cert#01455.
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURES:
Signe
HWA F'el Rep sentative
Reviewed:
HWA Project Engineer evlewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, t Aations mater a� and+00 theweldedrough 5 0 onfo0. rmancese lto AWS Ds will dto be 1 1 andthe
removed
of all coatings and unacceptable
contract documents.
FR-040 1 Unresolved at this time - Rebar and formwork must be placed in accordance with approved plans
and specifications prior to concrete placement along with a final re -inspection and acceptance.
FR-043 1 Unresolved: Unsuitable bearing soils for play structure footings at the North end of park.
d
Pa e1of2
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
21312 30th Drive SE Suite 110
lrLWA Bothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-047
Date (mm/dd/yy):
4/14/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project.
Edmonds, WA
ClientClient
Representative
Weather
City of Edmonds
Jaime Hawkins
Clear, 58 degrees
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Moe
Matthew Spenner
FR-046 1 . Unresolved: Unsuitable bearing soils for slide play structure footings at the South end of park..
FR-047 1 Unresolved: Repair unacceptable welding.
UiW 21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax 425-774-2714
Field Report No.:
FR-048
Date (mm/dd/yy):
4/13/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Sunny, 47F
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Moe
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 10:00 Arrived at Site: 10:20 Departed Site: 13:40 End Travel:14:00
1.
ACTIVITY BEING INSPECTED: Compaction of CSBC (AG-2) for use as slide play structure footing subgrade. .
GENERAL LOCATION: Slide Play area circular footings in the South end of the park.
DETAILED LOCATION: The specific locations and elevations tested are summarized on the attached 'Field Compaction
Test Report'. t
TYPE OF INSPECTION: Continuous
DETAILS OF PLACEMENT OF THIS MATERIAL: Based on information provided by visual observation, materials were
placed in approximately 12" lifts uncompacted thickness and compacted with a Case 580 backhoe.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and compaction
testing. HWA was able to observe both the lift placement and the compaction application prior to testing, for all tests.
Test results are summarized on the attached 'Field Compaction Test Report'. '
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: While on site HWA made six test cylinders ,
of grout per the approved mix design that will be used for the play structure. Grout mixture was hand mixed on site by
Eric with Precision Earthworks. '
Total time charged to the job for this visit is 4.0 hours including report writing.
SIGNATURES:
— e �
Signe �,�'i Reviewed:
HWA ' i Repr sentative HWA Project Engineer or er ,
SUMMARY OF UNRESOLVED ISSUES
'
Report#
FR-039
Item# Status
1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
connections, 75th Ave stations 44+00 through 45+00. These welds will need to be removed.
embed
of all coatings and unacceptable material, and rewelded in conformance to AWS DI A and the
FR-040
contract documents.
1 Unresolved at this time - Rebar and formwork must be placed in accordance -with approved plans and
specifications prior to concrete placement along with a final re -inspection and acceptance.
FR-043
1 Unresolved: Unsuitable bearing soils for play structure footings at the North end of park.
FR-046
1 Unresolved: Unsuitable bearing soils for slide play structure footings at the South end of park.
-
FR-047
1 Unresolved: Repair unacceptable welding.
'
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 2 '
1
U
21312 3011 Drive SE Suite 110
Bothell, WA 98021
'
Tel. 425-774-0106
I-IWAGEOSCIENCES INC.
Fax.425-774-2714
Project Name Location or Address or
76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA
Client client Representative
City of Edmonds Jaime Hawkins
Design Authority (engineer or architect of record) Design Authority Repr
Precision Earthworks
Moe
Field Report No.:
FR-048
Date (mm/dd/yy):
4/1312010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Sunny,47F
HWA Project Manager
Tony Martin
HWA Field Represent
Brian Coker
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: see accompanying field report
--r iri+r 1Kfin0f-%%1 hAV:K1T TFCTFn• CPP arrmmnanvina field report
Detailed Test Location
10 foot West of play slide
Elev'n
or
Depth
B.G."
Probe
Depth
(in)
Lab Control"
(Proctor/Rice/Marshall)
Field Test
Relative
Compaction
Test
No.
Density
Moist.
ID
#
Max.
Dens.
Opt..
Moist.
Over
Size %
Total
pcf
Dry
pcf
Moist.
%
Field
%
Spec
%
1
T.O. G.
8
AG-2
143.5
5.1
23
141.2
136.6
3.4
95
95
20 foot South west of play slide
T.O. G.
8
AG-2
143.5
5.1
23
141.7
136.3
4.0
95
95
2
3
40 foot South of play slide
T.O.G.
8
AG-2
143.5
5.1
23
140.7
136.4
3.2
95
95
4
5
6
7
8
9
10
11
12
13
Test Method X ASTM D2922/D3017 (soil) ASTM D2950 (aspnair) vu 1V1
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-B CPN MC1-DR-P
Serial #: 37406 Density Standard Count.: 2809 Moisture Standard Count: 660
'Lab Control: Standard Proctor X Modified Proctor
Asphalt Marshall Density Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. ""Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Brian Coker Reviewed By: Tony Martin
Pa e2of2
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
21312 30th Drive SE Suite 110
Field Report No.:
FR-049
Date mm/ddlyy):
4/14/2010
�
Bothell, WA 98021
HWA Project No.:
2006-171-21
1 1V p/AGEOSCIENCES INC.
Tel. 425-774-0106
Fax. 425-774-2714
HWA Task No.: .
400
Location or Address of
o.
Project Name
76th Ave W/75th PI W Walkway and
=:::;;;
162nd St SW Project
Edmonds, WA
r
Client
Client Representative
Jaime Hawkins
y, 51F
City of Edmonds
Design Authority (engineer or architect of record)
Design Authority Representative'
HWA Project Manager
Tonv Martin —
General contractor """' --I'-----'
Precision Earthworks
Moe Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 13:40 Arrived at Site: 14:00 Departed Site: 15:00 End Travel:15:20
ACTIVITY BEING INSPECTED: Placement of Reinforcing Steel.
ITEM BEING CONSTRUCTED: Slide play structure and stairs and landing on the South side of the park area and swing
set area on the North side of the park.
DETAILED LOCATION: Slide play structure and stairs and landing on the South side of the park area and swing set
area on the North side of the park. (Approved plans do not give specific gridlines.)
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: This is a preliminary inspection prior to closing formwork.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and measurements to
confirm bar sizes, number of bars, correct placement, and adequate cover.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, .specifications and RFIs, with the exception of any non-conformance items list below
Item 1- Final inspection to be performed prior to concrete placement.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURES:
Sig 71,
HW iel 4Reprentative
Reviewed: �-
HWA Project Engineer or Revie
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, 75th Ave stations 44+00 through 45+00. These welds will need to be removed
of all coatings and unacceptable material, and rewelded in conformance to AWS D1.1 and the
contract documents.
FR-040 1 Unresolved at this time - Rebar and formwork must be placed in accordance with approved plans and
specifications prior to concrete placement along with a final re -inspection and acceptance.
FR-043 1 Unresolved: Unsuitable bearing soils for play structure footings at the North end of park.
FR-046 1 Unresolved: Unsuitable bearing soils for slide play structure footings at the South end of park..
FR-047 1 Unresolved: Repair unacceptable welding.
FR-049 1 Unresolved: Rebar and formwork must be placed in accordance with approved plans and
specifications and a final re -inspection and acceptance prior to concrete placement.
Pa e1of1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
1
C
n
n
21312 30th Drive SE Suite 110
UM
LTA
Bothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax.425-774-2714
Field Report No.:
FR-050
Date (mm/dd/yy):
4/15/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Jaime Hawkins
Sunny, 47F
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks
Moe
Brian Coker
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 07:40 Arrived at Site: 08:00 Departed Site: 09:00 End Travel:09:20
ACTIVITY BEING INSPECTED: Placement of Reinforcing Steel.
ITEM BEING CONSTRUCTED: Slide play structure and stairs and landing on the South side of the park area and swing
set area on the North side of the park.
DETAILED LOCATION: Slide play structure and stairs and landing on the South side of the park area and swing set
area on the North side of the park. (Approved plans do not give specific gridlines.)
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: Both rebar and formwork was presented by the contractor as being
complete. This is a final inspection.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and measurements to
confirm bar sizes, number of bars, correct placement, and adequate cover.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: HWA made six additional test cylinders of
grout as referenced in FR-048, per the approved mix design that will be used for the play structure.. Grout mixture was
hand mixed on site by Eric with Precision Earthworks.
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURES:
Signed: Reviewed: U-�6�--
HWA Field Representative HWA Project Engineer QRweaver
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, 75th Ave stations 44+00 through 45+00. These welds will need to be removed
of all coatings and unacceptable material, and rewelded in conformance to AWS D1.1 and the
contract documents.
FR-040 1 Resolved: - Rebar was placed in accordance with approved plans and specification.
FR-043 1 Unresolved: Unsuitable bearing soils for play structure footings at the North end of park.
FR-046 1 Unresolved: Unsuitable bearing soils for slide play structure footings at the South end of park..
FR-047 1 Unresolved- Repair unacceptable welding.
FR-049 1 Resolved: Rebar and formwork were in place and found acceptable per the approved plans and
specifications..
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
21312 30th Drive SE Suite 110
Field Report No.:
Bothell, WA 98021
Date (mm/dd/yy):
HWA Project No.:
HWAGEOSCIENCES INC.
Tel.425-774-0106
Fax.425-774-2714
HWA Task No.:
Location or Address A
No.
Project Name
76th Ave W/75th PI W Walkway and
=::q;
162nd St SW Project
Edmonds, WA
Client Representative
er
Client
City of Edmonds
Jaime Hawkins
ny, 47F
HWA Project man;
Design Authority (engineer or architect or record)
Design Authority Representative
Tony Martin
General contractor
General Contractor Representative
HWA Field Repre:
Brian Coker
Precision Earthworks
Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY.
Start Travel: 07:40 Arrived at Site: 08:00
Departed Site: 09:00 End Travel:09:20
FR-060/Revised
4/15/2010
2006-171-21
400
ACTIVITY BEING INSPECTED: Placement of Reinforcing Steel.
ITEM BEING CONSTRUCTED: Slide play structure and stairs and landing on the South side of the park area and swing
set area on the North side of the park.
and stairs and landing on the South side of the park area and swing set
DETAILED LOCATION: Slide play structure
area on the North side of the park. (Approved plans do not give specific gridlines.)
TYPE OF INSPECTION: Periodic
IA Both rebar and formwork was presented by the contractor as being
STATUS OF PLACEMENT OF THIS MATER
complete. This is a final inspection.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and measurements to
confirm bar sizes, number of bars, correct placement, and adequate cover.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: HWA made four additional grout cylinders
(designated G-2) of the proposed grout, because the grout cylinders mentioned in FR-048 (designated G-1) failed to
meet the strength requirements of the mix design. Grout mixture was hand mixed on site by Eric of Precision
Earthworks and is a trial batch and will not be placed.
HWA re -inspected the bearing soils for the slide play structure footings at the South end of park; The 1/2 diameter steel
T-handle probe penetrated soils approximately 1/2 inch to 2 inches with 220 pounds of pressure applied.
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURES:
Signed:
HWA Field Representative
Reviewed: t " a
HWA Project Engineer or
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connection tceAve
stations
mater a� and rewelded o onformanceao AWS D1 10be andremoved
of all coatings and
unacceptable
contract documents.
entwas found to be in accordance with approved plans and
FR-040 1 Resolved: - Re -inspection of rebar placem
specification.
FR-046 1 Resolved: - Re -inspection of bearing soils with a 1/2 inch steel T-handled probe for slide play
structure footings at the South end of park were found to be dense.
FR-047 1 Unresolved: Repair unacceptable welding.
FR-049 1 Resolved: Rebar and formwork were in place and found acceptable per the approved plans and
Page1 of
This report should only be reproduced in its entirety: Report is not final until signed by HWA field representative and HWA reviewer.
1
1
II
11
A 21312 30th Drive SE Suite 110
ffBothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC. Fax. 425-774-2714
76th Ave W/75th PI W Walkway and
162nd St SW Project
City of Edmonds
Design Authority (engineer or architect of record)
General Contractor
Precision Earthworks
I
1
1
-ocation or Haaress ur rwjccL
Edmonds, WA
lient Representative
Jaime Hawkins
Design Authority Representative
General Contractor Representative.
Moe
FIELD REPORT
Field Report No.:
FR-051
Date (mm/dd/yy):
4/15/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 0800 Arrived at Site: 0845 Departed Site: 1415 End Travel:1500
Sunny, 47F
Martin
Kimberly Swanson
ACTIVITY BEING INSPECTED: Concrete delivery and placement.
ITEM BEING CONSTRUCTED: Wall footings, stairways
DETAILED LOCATION: Wall footings for the swings play area in northwest section of park and play area at climbing
rock jumble/slide, play area wall at slide, and stairways immediately north and south of rock jumble/slide play area.
TYPE OF INSPECTION: Continuous
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: The concrete was placed both by pump truck and.directly
from the chute. Consolidation was accomplished with a concrete vibrator and manually by spading and rodding. Per
instruction from Jim Roberts, City of Edmonds (onsite), testing was performed on first truck only and maximum slump of
3-inches was increased to 4-inches.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's'Field and Laboratory Concrete Test Report'
for Set C-7 for a summary of inspection and test data.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the items inspected were found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: CalPortland delivered 49 ya- of concrete
mix design #3136, placed both by pump and directly from the chute. Concrete was consolidated both mechanically, with
a concrete vibrator and manually by rodding and spading.
Total time charged to the job for this visit is 7.50 hours including report writing.
SIGNATURES:"
Signea .J AA2�
HWA Fi Representative
.`�
Reviewed:
HWA Project Engineer or Reviewer
SUMMARY OF UNRESOLVED ISSUES
' Report# Item# Status
FR-039 1 Unresolved at this time- Unacceptable welds have been observed at the elevated walkway pile to
embed connections, 75th Ave stations 44+00 through 45+00. These welds will need to be removed
of all coatings and unacceptable material, and rewelded in conformance to AWS D1.1 and the
' contract documents.
FR-047 1 Unresolved: Repair unacceptable welding.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer.. Page 1 of 1
Field Re o
21312 30th Drive SE Suite 110 Fieprt No.: FR-052 ,
7 BotheII,WA98021 Date (mmlddlyy): 4/1512010
��, Bothell,
ell,W 4-0106 HWA Project No.: 2006-171-21
TelHWAGEOSCIENCES INC. Fax. 425-774-2714 HWA Task NO.: 400
Protect Name
Location or Address of Protect Permit No. ,
76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA
Client Representative Weather
lient Mostly Sunny, 47F
City of Edmonds Jaime Hawkins
Design Authority Representative
HWA Project Manager
Design Authority (engineer or architect of record) g p Tony Martin '
General Contractor Representative HWA Field Representative
General Contractor Matthew Spanner
Precision Earthworks Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 1330 Arrived at Site:1400 Departed Site: 1430 End Travel:1500
ACTIVITY BEING INSPECTED: Welding Inspection. r
ITEM BEING CONSTRUCTED: Elevated walkway.
DETAILED LOCATION: 75th Ave stations 44+00 to 45+00, 31+90
TYPE OF INSPECTION: Periodic '
STATUS OF PLACEMENT OF THIS MATERIAL: Welding was presented as complete in these locations.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual welding inspection of flat bar to
embed plate and pin pile to embed plate 3/16" fillet weld connections at the above locations. '
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: file. As of this time, 100% of all '
Welding at these locations appeared.to exhibit visually acceptable size, length, and pro
welding has been visually inspected. All welding appeared to be visually acceptable per AWS D1.1 table 6.1 and figure
5.4, and the contract drawing general notes S-1. FCAW process was used with E71T-8 filler metal. All welding was '
performed by Theodore Rapp, WABO cert#01455. Pin pile sleeve splices have not been welded as they are not
specified in the contract documents.
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURES:
Signe
In.A 7r Reviewed:
HWA i Rep sentative HWA Project Engineer or Reviewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-039 1 Resolved: Unacceptable welds at the elevated walkway stations 44+00 to 45+00 have
been rewelded and appear to be visually acceptable per AWS D1.1 and the contract. documents.
FR-047 1 Resolved: - Unacceptable welds at station 31+90 have been rewelded and appear to be visually ,
acceptable per AWS D1.1 and the contract documents.
P
Pa e1of1 1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. 9
'
��
21312 30th Drive SE suite 110if
Field Report No.: FR-053
Date (mmldd/yy): 411612010
,
Bothell, WA 98021
HWA Project NO.: 006-171-21
'
HWAGEOSCIENCES INC.
Tel.425-774-0106
Fax. 425-774 -2714
HWA Task No.: 400
Location or Address of Project
Permit o.
Project Name
76th Ave W175th PI W Walkway and
162nd St SW Project
Edmonds, WA
earner
Client
lent Representative
Jaime. Hawkins
Sunny, clear, 55F
'
City of Edmonds
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Kimberly Swanson
Precision Earthworks
Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON
PROJECT TODAY:
Start Travel' 0800 Arrived at Site: 0820
Departed Site: 0830 End Trave1:0900
TIES OBSERVATIONS AND/OR COMMENTS: HWA representative arrived at.the park to
MISCELLANEOUS ACTIVI
retrieve four 4x8 inch concrete cylinders sampled from the 04/15/2010 concrete placement. The concrete samples were
transported to the HWA laboratory in Bothell for testing.
Total time charged to the job for this visit is 2.0 hours including logging and processing concrete samples and report
writing.
SIGNATURES:
•.Signe
HWA Fie Representative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
n
Reviewed: \ �
HWA Project Engineer or Reviewer
Page1of1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer.
Field Report NO.: FR-054
21312 30th Drive SE Suite 110
Date (mmlddlyy): 4/1912010
Bothell, WA 98021
HWA Project No.: 2006-171-21
HWAGEOSCIENCES INC.
Te1.425-774-0106
Fax.425-774-2714
HWA Task No,: 400
Location or Ad ress of roject
ermit No.
Project Name
76th Ave W/75th PI W Walkway and
162nd St SW Project
lient
Edmonds, WA
lient Representative
Weather
Mostly Sunny, 47F
City of Edmonds
Jaime Hawkins
Design Authority Representative
.
HWA Project Manager
Design Authority (engineer or architect of record)
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Brian Coker
Precision Earthworks
Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON
PROJECT TODAY:
Start Travel: 1330 Arrived at Site: 1400
Departed Site: 1530 End Travel:1600
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: HWAmaae a sne vIZ51< <U 1ar-.,w� .,.�
proposed placement of 14 steel grout tubes, 7 foot and 10 foot in length per the direction of HWA engineer Ralph
Boirum as well as witness the installation of the steel grout tubes into the quarry spalls throughout the rock climbing wall
at the South end of the park. e hammered down into the Based on my inspection, installation of the grout tubes w r to observe the grouting of the Ivoids itdepth with the
nth spals.
bucket of a 311 excavator. HWA will be on site on 4-20
Total time charged to the job for this visit is 2.5 hours including report writing.
SIGNATURES:
A /A AJ
Signe
HWA I d Repotive
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
A"Revie,�e,,"�
Reviewed:HWA Project Engine
Page1of1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer.
21312 sots Drive SE suite 110 Field Report No.: FR-055
' Date (mm/dd/yy): 4I2012010
Borneo, WA 98021 Tel. HWA Project No.: 2006-171-21
M01
HWAGEOSCIENCES INC. Fax. 425-774-2714 HWA Task NO.: 400
_ Permit No.
' 76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA Weather
Bent bent Representative
Jaime Hawkins Overcast, 43F
City of Edmonds HWA Project Manager
' Design Authority (engineer or architect of record) Design Authority Representative
Tony Martin
HWA Field Representative
General Contractor General ContractorRti
Contractor epresentave Brian Coker
Precision Earthworks Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 0700 Arrived at Site: 0730 Departed Site: 1600 End Travel:1630
' MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: HWA made a site visit to observe the
placement of grout into the quarry spalls through 7 foot and 10 foot in length steel grout tubes that were placed 6 foot
into the spalls. Based on my inspection, Five (5) tubes were filled with grout by means of a Paco 14hp grout pump: The
grouting operation was stopped when grout started to surface through the quarry spalls. The contractor placed,
ut for the day and removed the grout tubes for cleaning. HWA will be on site
approximately 105, 941bs bags of mixed gro
on 4-21-10 to observe the steel pipe being re-inserted into the same holes grout was placed. The contractor will
' foot and place the next lift placement of grout in the
penetrate grout tubes until resistance, then lift approximately 2
spalls.
' Total time charged to the job for this visit is 10 hours including report'writing.
SIGNATURES:
Signed:
.;- Reviewed:
HWA Field Representative HWA Project Engineer or Reviewer
I
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No Items at this time.
Ii
—'
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page1 of
21312 30th Drive SE Suite 110
1FLWA,
Bothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC.
Fax.425-774-2714
Project Name Location or Aaaress or
76th Ave W/75th PI W Walkway and
162rid St SW Project Edmonds, WA
lient lient Representative
City of Edmonds Jaime Hawkins
nesian Authority (engineer or architect of record) Design Authority Repr
Precision Earthworks
Moe
FIELD REPORT
Field Report No.:
FR-056
Date (mm/ddlyy):
4/21/2010
HWA Project No.:
2006-171-21
HWA Task No.:.
400
Heavy Rain, 42F
HWA Project Manager
Tony Martin
HWA Field Representative
Brian Coker
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 0700 Arrived at Site: 0730 Departed Site: 0800 End Travel:0830
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: HWA made a site visit to observe the
placement of grout into the quarry spalls of the climbing rocks at the South end of the park, through 7 foot and 10 foot in
length steel grout tubes that were placed 6 foot into the spalls. Due to weather and a phone conversation with Ed Sibrel
with the City of Edmonds, it was determined that today's grout placement will be postponed until 4-22-10.
Total time charged to the job for this visit is 1 hours including report writing.
SIGNATURES:
Signe v"-o, 3A, A J
HWA to Repr sentative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
Reviewed:
HWA Project Engineer or Reviewer
ge1of1a ,
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. -P
21312 30th Drive SE Suite 110
ABothell, WA 98021
Tel. 425-774-0106
' HWAGEOSCIENCES INC. Fax, 425-774-2714
76th Ave W/75th PI W Walkway and
'
162nd St SW Project
Edmonds, WA
Bent Representative
lient
City of Edmonds
Jaime Hawkins
Design Authority (engineer or architect of record)
Design Authority Repre
General Contractor Re
General Contractor
Moe
Precision Earthworks
F
F
Field Report No.: FIR-057
Date (mmiddlyy): 4/2212010
HWA Project No.: 2006-171-21
HWA Task No.: 400
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 0630 Arrived at Site: 0700 Departed Site: 1100 End Travel:1130
Sunny, 48F
HWA Project Man
Tony Martin
HWA Field Repre
Brian Coker
he
MISCELLANEOUS ACTIVITIES, OBSERVATIONS bAn D/0 Rs Ot tth�e South end of heMENTS: HWA dpa k, through 7 foot ande a site visit to observe t10 foot in
placement of grout into the quarry spalis of the9The grouting
length by 2 inch in diameter steel grout tubes that nsweplaced
ect on,4 f`oot into the nessed 6 t libels s. be ng filled w th grout by means of a
ration ceased
upon visual evidence of visible grout. Based o y p
Paco 14hp grout pump. Contractor placed approximately 70, 94lbs bags of mixed grout. Four 4" x 8" grout cylinders (G-
3) Were cast from this grouting operation.
Total time charged to the job for this visit is 5 hours including report writing.
SIGNATUR4F'Rep
Signe��HWA sentative
. SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
Reviewed:
HWA Project Engineer or Reviewe`r`�.,�
representative and HWA reviewer. Page 1 of 1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC.
Fax.425-774-2714
76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA
(rent Rent Representative
City of Edmonds Jaime Hawkins
naci.n Authority (engineer or architect of record) Design Authority Repr
Pri=riSion Earthworks
Moe
FIELD REPORT
Field Report No.: FR-058
Date (mmldd/yy): 4/23/2010
HWA Project No.: , 20:06-171-21
HWA Task No.: 400
T
ercast, 45F
A Project Manag
ny MartinA Field Represe
ian Coker
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 0630 Arrived at Site: 0700 Departed Site: 0730 End Trave1:0800
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: HWA representative arrived at the job site to
retrieve the four 4x8 inch grout cylinders cast on 04/22/2010 representing the grout placement for that day. The grout
samples were transported to the HWA laboratory in Bothell for testing.
Total time charged to the job for this visit is 1.0 hours including report writing.
SIGNATURES:
Signed: !
HWA Fi d epresentative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time.
Reviewed:
HWA Project Engineer or Reviewer
Pa e 1 of 1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
'
HWAGEOSCIENCES INC.
Fax. 425- 774-2714
Project Name
Location or A ress of Project
76th Ave W/75th PI W Walkway and
1
162nd St SW Project
Edmonds, WA
bent
lient Representative
City of Edmonds
Jaime Hawkins
■
Design Authority (engineer or architect of record)
Design Authority Representab
r
L
F1
Field Report No.:
FR-069
Date (mmldd/yft
412612010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Overcast, 45F
HWA Project Manager
Tony Martin
HWA Field Representative
Kimberly Swanson
Precision Earthworks Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 0715 Arrived at Site: 0800 Departed Site: 0815 End Travel:0900
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: HWA representative arrived at the job site to
perform concrete placement observation and testing. Upon arrival, I was informed that the concrete placement had
been rescheduled for tomorrow, 04/27/2010 at 8 am.
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURES:
Signed.
HWA Fiel epresentative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
No items at this time..
Reviewed:
HWA Project Engineer or Reviewer
' a
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Pge1of1
t
Report No.: FR-060
Field Re
21312 30th Drive SE Suite 110 Fiep
�� Bothell, WA 913021 Date mmldd/yy): 4/23/2010
ir"HWA Project No.: 2006-171-21
Tel.425-n4-0106
HWAGEOSCIENCES INC. Fax. 425-774-2714 HWA Task No.: 400
Location or Address of Project Permit No.
Project Name
,
76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA Weather
lient Representative
'
Client
Jaime Hawkins Overcast, 46F
City of Edmonds HWA Project Manager
Design Authority (engineer or architect of record) Design Authority Representative
Tony Martin
General Contractor Representative HWA Field Representative
General Contractor Brian Coker
,
Precision Earthworks Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 1430 Arrived at Site: 1500 Departed Site: 1600 End Travel:1630
ACTIVITY BEING INSPECTED: Placement of Reinforcing Steel. area.
Walls for the swings play area and climbing rock/slide a
,
ITEM BEING CONSTRUCTED:
DETAILED LOCATION: Walls for the swings play area in northwest section of park and play area at climbing rock/slide,
plans do not give
play area wall at slide, and stairway landings immediately north of rock slide play area.(Approved
specific gridlines.)
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: This is a preliminary inspection prior to closing formwork.
observation and measurements to
'
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM. HWA carried out visual
confirm bar sizes, number of bars, correct placement, and adequate cover.
OF THIS ITEM: To the best of the inspector's knowledge, the item in was found in
below.
CONFORMANCE
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items- list
Item 1- Final inspection to be performed prior to concrete placement.
,
Total time charged to the job for this visit is 2.0 hours including report writing.
SIGNATURES:
Signed: Reviewed:
HWA Project Engineer or Reviewer
'
HWA Field Representative
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-060 1 Unresolved: Rebar and formwork must be placed in accordance with approved plans and
specifications and a final re -inspection and acceptance prior to concrete placement.
,
J
Pa '
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewerage 1of1
.
i
21312 loth Drive SE Suite 110 .
'
A, ;
Bothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC.
Fax.425-774-2714
Location or Address of Project
roject Name
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
lient -
lient Representative
City of Edmonds
Jaime Hawkins
Design Authority (engineer or architect of record)
Design Authority Representative
'resentative
ll
Precision Earthworks
Moe
Field Report No.:
FR-061
Date (mmldd/yy):
4/26/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
FIELD REPORT.
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 1430 Arrived at Site: 1445 Departed Site: 1515 End Travel:1530
44F
Tony Martin
FW-W-FieldRepre
Brian Coker
ACTIVITY BEING INSPECTED: Placement of Reinforcing Steel.
ITEM BEING CONSTRUCTED: Walls for the swings play area and climbing rock/slide area.
DETAILED LOCATION: Walls for thswings
lay area in northwest section of park and play area at slide play area.(Approved plans dolng not give
slide,
play area wall at slide, and stairway landings immediately north of rock
specific gridlines.)
TYPE OF INSPECTION: Periodic
STATUS OF PLACEMENT OF THIS MATERIAL: This is a final inspection.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation and measurements to
confirm bar sizes, number of bars, correct placement, and adequate cover.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
Total time charged to the job for this visit is 1.5 hours including report writing.
SIGNATURES:
Signed:
HWA Field Representative
Reviewed:
HWA Project Engineer or Reviewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-060 1 Resolved: Rebar and formwork were in place and found acceptable per the approved plans
and specifications.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer.
Page 1 of 1
21312 30th Drive se suite 110
Field Report NO.: FR-062
Date (mmldd/yy): 4/2712010
ir"%
Bothell, WAgao21
HWA Project No.: 2006-171-21
HWAGEOSCIENCES INC.
Tel.425-774-0106
Fax. 425-774-2714
HWA Task No.: 400.
Location or A dress of Project
Permit No.
Project Name
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
lient Representative
ea er
Client
Edward Sibrel
Partly cloudy, 50F
City of Edmonds
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
'General Contractor
General Contractor Representative
HWA Field Representative
Kimberly Swanson
Precision Earthworks
Moe
FIELD REPORT
OF FIELD TIME SPENT ON
PROJECT TODAY:
SUMMARY
Start Travel: 0715 Arrived at Site: 0745
Departed Site: 1145 End Travel:1230
ACTIVITY BEING INSPECTED: Concrete delivery and placement.
ITEM BEING CONSTRUCTED: Short walls and sidewalk
DETAILED LOCATION: Walls around swings play area, rock jumble/slide area, and lower sidewalk in north east section
of park.
TYPE OF INSPECTION: Continuous laced
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: CalPoltland delivered 44.5 yds3 of mix design #3136, p
d by rodding; spading and externally vibrating
both by pump and directly from the chute, and was manually consolidate
the forms due to fears the forms would blow out/leak.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's 'Field and Laboratory Concrete Test Report'
for Set C-8 for a summary of inspection and test data. Field consistency testing of first load was 1/2 inch over specified
4 inches, both contractor and City of Edmonds representative were notified and both accepted the load.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs with the following exceptions:
Item #1 - First load of concrete was measured at a 4.5 inch slump, specified maximum is 4 inches.
Total time charged to the job for this visit is 5.5 hours including report writing.
SIGNATURES: ,
Signe Reviewed:
HWA I d Representative HWA Project Engineer or Reviewer
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-062 1 . Resolved -The City of Edmonds representative accepted the load.
Pag e 1 of 1 ,
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer.
' 111123011, Drive SE suite 110 Field Report No.: FR-063
Bothell, WA 98021 Date (mm/ddlyft 412812010
Tel_ 425-774-0106 HWA Project No.: 2006-171-21
HWAGEOSCIENCES INC. Fax. 425-774-2714 HWA Task No.: 400
Project Location or Address of Project Permit No.
me
76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA Weather
Client lient Representative
Jaime Hawkins Clouds, 40 degrees F
City of Edmonds HWA Project Manager
uy
Design Authority (engineer or architect of record) Design AthoritRepresentative
Tony Martin
General Contractor Representative HWA Field Representative
General Contractor Kimberly Swanson
Precision Earthworks Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY. '
Start Travel: 0800 Arrived at Site: 0820 Departed Site: 0830 End Travel:0900
rMISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: HWA representative arrived at the park to
retrieve four 4x8 inch concrete cylinders sampled from the 04/27/2010 concrete placement. The concrete samples were
transported to the HWA laboratory in Bothell for testing.
Total time charged to the job for this visit is 2.0 hours including logging and processing concrete samples and report
writing.
SIGNATURES:
Signed Reviewed:
HWA Fie Representative HWA Project Engineer or Reviewer
SUMMARY OF UNRESOLVED ISSUES
y Report# Item# Status
1
Pa e 1 of 1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
21312 30th brive SE suite 110 Field Report No.: FR-064
Bothell, WA sao21 Date (mmlddlyy): 5/612010
A98 21
'
Bothell,
HWA Project No. 2006A71-21
HWAGEOSCIENCES INC. Fax. 425-774-2714 HWA Task No.: 400
Location or A ress of Project Permit No.
project Name
76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA weather
Bent Bent Representative
Partly Cloudy, 60 degrees
'
Jaime Hawkins
City of Edmonds HWA Project Manager
Design Authority (engineer or architect of record) Design Authority Representative
Tony Martin
HWA Field Representative
General Contractor General Contractor Representative Matthew Spenner
Precision Earthworks Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 2:00. Arrived at Site:2:30 Departed Site: 3:00 End Travel: 3:30
ACTIVITY BEING INSPECTED: Removal of unstable sub -grade material
r
GENERAL LOCATION: Southwest radius of the pedestrian walkway
TYPE OF INSPECTION: Periodic
ITEM: To the best of the inspector's knowledge, the item inspected was found in
'
CONFORMANCE OF THIS
and RFIs, with the exception of any non-conformance items list below.
conformance with approved plans, specifications
Item 1 - Unsuitable sub -grade material was observed at this location.
'
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
unstable sub -grade material from
HWA representative Matthew Spenner arrived onsite to provide visual observation of
Using a 1/2" diameter steel "T" handle probe, I Was able to conclude
the south west radius of the pedestrian walkway.
need to be over excavated to a depth of.minus 2 feet below finish grade.. The
that material from this area would
contractor elected to proceed this way and stated that they would place geo-fabric at this depth and backfill with clean
but has not witnessed placement of geo-fabric or backfill at this time.
I
CSBC material. HWA observed initial excavation,
Total time charged to the job for this visit is 2.0 hours report writing.
SIGNATURES:
Reviewed.
Si ne �%v
g HWA Project Engineer or Reviewer
HWA Fi pres ntative
i
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-64 1 Unresolved. The contractor will need to remove the unsuitable sub -grade material from the southwest radius
of the pedestrian walkway and backfill with a suitable material.
r
Pae1of1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
21312 30th Drive SE Suite 110
Field Report No.: FR-066511812010
Date (mm/dd/yft
Bothell, WA 98021
HWA Piojeet No.: 2006-171-21
,.
f�1
HWAGEOSCIENCES INC.
Tel.425-774-0106
Fax.425-774-2714
HWA Task No.: 400
Project Name
ocation or Address of Project
Permit o.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Bather
Client
lient Representative
Jaime Hawkins
Partly cloudy, 60 degrees
City of Edmonds
Design thority (engineer or architect of record)
Au
Design Authority Representative
HWA Project Manager
Tony Martin
General contractor
General Contractor Representative
HWA Field Representative
Matthew Spenner
Precision Earthworks
Moe
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 1:30 Arrived at Site: 2:00
Departed Site: 3:00 End Travel: 3:30
1
11
I
ACTIVITY BEING INSPECTED: Pedestrian Walkway
GENERAL LOCATION: Southwest radius of the pedestrian walkway
TYPE OF INSPECTION: Periodic
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
Is, with the exception of any non-conformance items list below.
conformance with approved plans, specifications and RF
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS:
HWA representative Matthew Spenner arrived onsite to provide inspection of the suitability of the pedestrian walkway
subgrade. Upon my arrival, I was informed by the contractor that the unstable subgrade material reported in HWA field
report number FR-064 had not been replaced per direction of The City of Edmonds. I spoke with City of Edmonds
representative Ed and he confirmed what the contractor had told me. I asked that the City forward this information in
writing to HWA and Ed informed me that he would oblige.
Total time charged to the job for this visit is 2.5 hours report writing.
SIGNATURE
CIO
Signed:
HWA Field Representativ
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
Reviewed:�—
HWA Project En�ee-r_Reviewer
FR-64 1 Resolved. The City of Edmonds has accepted the condition of the subgrade as is.
Pa e1of1
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
21312 30th Drive SE Suite 110
Report No.:
Field Re
Fiep
Date (mm/dd/yy):
FR-066
5124/2010
U
Bothell, WA 98021
HWA Project No.:
2006-171-21
HWAGEOSCIENCES INC.
Tel. 425-774-0106
Fax.425-774-2714
HWA Task No.:
400
. A l irccc of rniert
Permit No.
76th Ave W/75th PI W Walkway and
lient Representative
162nd St SW Project Edmonds, WA weathE7d
Client
City of Edmonds Jaime Hawkins Sungrees
Desi n Authori Re resentative HWA ager
Design Authority (engineer or architect of record) g p Ton
General Contractor Representative HWA Field Representative
General contractor Kimberly Swanson
Precision Earthworks/Hot Mix Pavers, Inc. Moe
FIELD REPORT
'
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel: 8:45 Arrived at Site: 9:15 Departed Site: 16:00 End Travel: 16:30
ACTIVITY BEING INSPECTED: HMA Class 1/2" Pavement delivery, placement, and compaction.
for locations.
'
GENERAL LOCATION: Walking trails/walkways in park. See attached map exact
locations and elevations tested are summarized on the attached 'Field Compaction
DETAILED LOCATION: The specific
Test Repot.
f
TYPE OF INSPECTION: Continuous
OF PLACEMENT OF THIS MATERIAL: Hot Mix Pavers, Inc. delivered a total of 82 tons of Cemex HMA Class
DETAILS
1/2 inch mix design 1341862. The HMA was placed using a self-propelled paving machine. Compaction was
1 ton steel intermediate roller, and a plate
accomplished using a 5 ton vibratory steel break -down roller, a vibratory
compactor.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: HWA carried out visual observation, periodic temperature
test results are summarized on the
monitoring, and compaction testing of the completed pavement. Compaction
'Field Compaction Test Report'. Ed Sibrel from City of Edmonds accepted compaction at 85% or better of the
Ed
attached
specified Rice density, except for the section at the south end of the east path near the entrance to the park, which
sampled from the paver onsite.
,
accepted at 84% of Rice density. A sample of the HMA mix designated HMA-8 was,
Pavers, Inc. representative, batched at 1030a, sampled at. 1130am, truck
Sampling was performed by Hot Mix
#203098, ticket #1901107616, temp. 210 degrees at time of sampling, at 59 tons cumulative. Sample HMA-8 was
transported to HWA's lab in Bothell for testing. ected was found in
OF THIS ITEM: To the best of the inspector's knowledge, the item insp
'
CONFORMANCE
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list below.
ion of
Item 1 - Compaction results of the sloped walking trail in the far northwest section of the park and the/o pslopedsectnested by
85 of Rice density q
162nd. St. W that runs along the south end of the park failed to meet the minimum
HWA recommended that the paving contractor run vibratory rollers immediately
Ed Sibrel with the City of Edmonds.
after placing the HMA, but contractor was uncooperative.
A total of 9 hours will be charged to this project today including sample processing and report writing.
SIGNATURES:
p Reviewed:
,
Signe
HW i d Representative HWA Project Engineer v er
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-066 1 Unresolved - Sloped sections of asphalt paving - one at the northwest section of park and the other at the south
end, failed to meet the specified 85% compaction.
Page e 1 of 3 '
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. P
iI
� I
L
� I
� I
� I
� I
21312 30th Drive SE Suite 110 Field Report No.: FR-066
Bothell, WA 98021 Date (mm/dd/yy): 5/24/2010
ULTWAA Tel.425-774-0106 HWA Project No.: 2006-171-21
HWAGEOSCIENCES INC. Fax. 425-774-2714 HWA Task No.: 400
76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA
Client Representative Weather
Client Sunny, 70 degrees
City of Edmonds Jaime Hawkins
n Authority Re resentative HWA Project Manager
Design Authority (engineer or architect of record) Design � p Tony Martin
General Contractor Representative HWA Field Representative
General Contractor Kimberly Swanson
Precision Earthworks/Hot Mix Pavers, Inc. Moe
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD
MATERIAL BEING PLACED: 112 inch HMA
rt
PROJECT.IMPROVEMENT TESTED: see accompanying field repo
Elev'n
Lab Control"
Field Test
Relative
or Probe
(Proctor/Rice/Marshall)
Density Moist.
Compaction
Depth Depth
ID
Max. Opt. Over Total
Dry Moist.
Field Spec
Test
No.
Detailed Test Location B.G.**
(in)
#
Dens. Moist. Size %
pcf pcf %
%
%
North path, directly across from Grade
BS
HMA
154.6 134.8
87
85
1
swings
North eastern path, along curve, Grade
BS
HMA
154.6 139.6
go
85
2 above
slide play area
3 NE stairs, next to slide Grade
BS
HMA
154.6 132.2
$6
85
4 East path, at north end of jungle gym Grade
BS
HMA
154.6 133.8
$7
85
5 East path, at south end of jungle gym Grade
BS
HMA
154.E
135.3
$$
85
6 At bottom of south stairs
Grade
BS
HMA
154.6
135.5
88
85
7 NW path, bottom of slope
Grade
BS
HMA
154.6
128.3
83
85
8
West path, behind pump station
Grade
BS
HMA
154.E
133.7
86
85
9 -
West path, across from jungle gym
Grade
BS
HMA
154.6
136.3
$$
85
10
West path, south end near entrance
Grade
BS
HMA
154.E
135.3
$8
85
Grade
BS
HMA
154.6
127.7
83
85
11 NW path, top of slope
Grade
BS
HMA
154.6
131.0
85
85
East path. south end near entrance-
12
accepted by Ed Sibrel, City of Edmonds
Grade
BS
HMA
154.6
133.0
$6
85
13
Entrance driveway, bottom of slope
Other.
Test Method ASTM D2922/u3u7 r tsoul
Densometer: x Troxler 3440 Troxler 3430 Troxler 3411-B
CPN MC1-DR-P
Serial #: 28433 Density Standard Count.: 2071 Moisture Standard Count: 693
'Lab Control: Standard Proctor Modified Proctor
Asphalt Marshall Density X Asphalt Maximum Theoretical Density (Rice)
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed. Bolded results indicate compaction below specified value.
Completed By: Kimberly Swanson Reviewed By: Tony Martin
Pa e2of3
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
�,• ;
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
HWAGEOSCIENCES INC.
Fax.425-714-2714
76th Ave W/75th PI W Walkway and
162nd St SW Project Edmonds, WA
Client Client Representative
City of Edmonds Jaime Hawkins
naeinn Ai thnnty (enoineer or architect of record) Design Authority Repr
Precision Earthworks/Hot Mix Pavers, Inc. IMoe
Field Report No.:
FR-066
Date (mm/dd/yft
5/2412010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Sunny, 70 degrees
HWA Project Manager
Tony Martin
HWA Field Representative
Kimberly Swanson
FIELD COMPACTION TEST REPORT - NUCLEAR METHOD (continued)
MATERIAL BEING PLACED: 112 inch HMA
�n,TPcTFn• cap nrcomDanyina field report
Detailed Test Location
Entrance driveway, top of slope
162nd.St. W, top of slope at 76thP1
W.
162nd.St. W, mid -slope
162nd. St. W, bottom of slope at park
entrance driveway
Elev.
or
Depth
(ft)
Probe
Depth
(in)
Lab Control* Field Test ve Relati
(Proctor/Rice/Marshall) Density Moist. Compaction
Test
No.
ID
#
Max. Opt.
Dens. Moist.
Over Total Dry Moist. Field Spec
Size % pcf pcf % % %
14
Grade
BS
HMA
154.6
132.5 86 85
Grade
BS
HMA
154.6
127.7 83 85
15
Grade
BS
HMA
154.6
130.1 84 85
16
Grade
BS
HMA
154.6
128.8 83 85
17
18
19
20
E22
23
24
Test Method: see previous page.
Densometer: see previous page.
*Lab Control: see previous page.
COMMENTS: Test locations and elevations are approximate. Testing provides data only for a specific test location and to a limited depth.
Accompanying field report provides additional information. **Depth B.G. indicates depth below grade. Grade means the design finish grade of the
current type of fill material being placed.
Completed By: Kimberly Swanson Reviewed By: Tony Martin
Pa e3of3
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. g
HWAGEOSCIENCES INC.
21312 30th Drive SE Suite 110
Bothell, WA 98021
Tel. 425-774-0106
Fax 425-774-2714
Field Report No.:
FR-067
Date (mm/dd/yy):
7/13/2010
HWA Project. No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Edward Sibrel
Sunny, 70 degrees
Design Authority (engineer or architect of record) _
Design Authority Representative
HWA Project Manager
Tony Martin
!General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks/Hot Mix Pavers, Inc
Moe
Jessica Herrera
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel:1000 Arrived at Site: 1030 Departed Site: 1130 End Travel: 1150
ACTIVITY BEING INSPECTED: Concrete delivery and placement.
ITEM BEING CONSTRUCTED: Sidewalk Overlay.
DETAILED LOCATION: Approximate stations 31+80 to 32+90.
TYPE OF INSPECTION: Periodic
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: The concrete was being placed by tailgating. No
consolidation was observed.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's `Field and Laboratory Concrete Test Report'
for Set C-9 for a summary of inspection and test data.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs, with the exception of any non-conformance items list
below.
A total of 3.0 hours including report writing will be charged to this project today. ,
SIGNATURES:
- 1
Signed: Reviewed: 1 L c
HWA Feld Represent tie HWA Project Engineer or ev ew r ,
SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-066 1 Unresolved - Sloped sections of asphalt paving - one at the northwest section of park and the other at the south
end, failed to meet the specified 85% compaction. '
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1 I
'
21312 30th Drive SE Suite 110
Bothell, WA 98021
'
HWAGEOSCIENCES INC.
Tel. 425-774-0106
Fax.425-774-2714
Field Report No.:
FR-068
Date (mm/dd/yy):
7/14/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client .
Client Representative
Weather
City of Edmonds
Edward Sibrel
Sunny, 70 degrees
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
HWA Field Representative
Precision Earthworks/Hot Mix Pavers, Inc.
Moe
Alix Rackleff
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
Start Travel:0830 Arrived at Site: 0900 Departed Site: 1000 End Travel: 1030
ACTIVITY BEING INSPECTED: Concrete delivery and placement.
ITEM BEING CONSTRUCTED: Sidewalk Overlay.
DETAILED. LOCATION: Approximate stations 32+90 to 33+20.
TYPE OF INSPECTION: Periodic
STATUS AND DETAILS OF PLACEMENT OF MATERIAL: The concrete was being placed by tailgating. No
' consolidation was observed.
HWA INSPECTION ACTIVITIES RELATED TO THIS ITEM: See HWA's'Field and Laboratory Concrete Test Report'
for Set C-10 for a summary of inspection and test data.
CONFORMANCE OF THIS ITEM: To the best of the inspector's knowledge, the item inspected was found in
conformance with approved plans, specifications and RFIs.
Concrete cylinder set C-9 was picked up and transported to HWA's lab for processing.
A total of 2.5 hours including report writing will be charged to this project today.
SIGNATURES:
P n
Signed: Reviewed:
1 HWA Field Representative HWA Project Engineer orlAe�i er
' SUMMARY OF UNRESOLVED ISSUES
Report# Item# Status
FR-066 1 Unresolved - Sloped sections of asphalt paving - one at the northwest section of park and the other at the south
end, failed to meet the specified 85% compaction.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1
21312 30th Drive SE Suite 110
",
Bothell, WA 98021
HWAGEOSCIENCES INC.
TeI.425-774-0106
F...425-774-2714
Field Report No.:
FR-069
Date (mm/dd/yy):
7/15/2010
HWA Project No.:
2006-171-21
HWA Task No.:
400
Project Name
Location or Address of Project
Permit No.
76th Ave W/75th PI W Walkway and
162nd St SW Project
Edmonds, WA
Client
Client Representative
Weather
City of Edmonds
Edward Sibrel
Sunny, clear, 72°F
Design Authority (engineer or architect of record)
Design Authority Representative
HWA Project Manager
Tony Martin
General Contractor
General Contractor Representative
1HWA Field. Representative
Precision Earthworks/Hot Mix Pavers, Inc.
I Moe
I Kimberly Swanson
FIELD REPORT
SUMMARY OF FIELD TIME SPENT ON PROJECT TODAY:
7
Start Travel:0730 Arrived at Site: 0800 Departed Site: 0805 End Travel: 0830
MISCELLANEOUS ACTIVITIES, OBSERVATIONS AND/OR COMMENTS: '
HWA representative Kimberly Swanson picked up concrete cylinder set C-10 samples made on 7/14/2010 and delivered
them to HWA's lab in Bothell, Wa for compressive strength testing.
Total time charged to the job for this visit is 1.0 hours including report writing.
SIGNATURES:
Signed:
;%��—
HWA Fiel Representative
Reviewed:
HWA Project Engineer or R6vi er
SUMMARY OF UNRESOLVED ISSUES '
Report# Item# Status
FR-066 1 Unresolved - Sloped sections of asphalt paving - one at the northwest section of park and the other at the south
end, failed to meet the specified 85% compaction.
This report should only be reproduced in its entirety. Report is not final until signed by HWA field representative and HWA reviewer. Page 1 of 1 t
APPENDIX B
GEOTECHNICAL ENGINEERING
LABORATORY RESULTS
' LABORATORY COMPACTION CHARACTERISTICS OF SOIL
CLIENT: City of Edmonds HWAGEOSCIENCES INC.
PROJECT: 76th Ave W/75th PI W Walkway and 162nd St SW SAMPLE ID: AG-1
PROJECT NO: 2006-171-21 T- 300 Sampled By: AR Tested By: EJB
Date Sampled: 1013012009 Date Received: 1013012009 Date Tested: 1613112009
MATERIAL TYPE OR DESCRIPTION:
Crushed Surfacing Top Course
MATERIAL SOURCE, SAMPLE LOCATION AND DEPTH:
Glacier, Kenmore
Designation: QASTM D 698 QX ASTM D 1557 Natural Moisture Content: 4.3 %
Method: F_]A F-1B QX C Oversize: - 0 % retained on: 314 in.
Preparation: Dry QX Moist. Rammer:[X]Auto Manual Assumed S.G.: 2.8
Test Data
Dry Density (pcf)
129.7
1 135.8
1 136.9
134.3
Moisture Content (%)
4.3
1 5.9
1 7.9
10.4
145
140
_ Rock Corrected Curve
"- per ASTM D4718
0 Lab Proctor Curve
....... 100% Saturation Line
III
I
I
I
I
I
I
I
I
(
I
I
I
I
I
I
III
II
II
II
II'I
17-F
I
III
I
III
I
I
III
I
li
i
I
I
III
II
II
y
135
III
III
II
III
III
•II
III
II
o
III
I
II
V
I
I
I
I
I
I
I
I
I
I
III
III
I
I
II
I��
III
II
I
I
I
III
I
I
I �•
I
I
I
��
I
I
III
III
I
I
III
I
I
I
I
I
130
®I
I
III
III
III
I
I
kill
II
lil
III
III
I
I
I•�.I
II
III
III
.III
III
II
Ir�.l
II
II
II
III
III
I
I
III
II��'�II
125
II
III
III
III
II
II
I
II
0 .2 4 6_ 8 10 12 14 16
Moisture Content (%)
Data Summar *
Percent Oversize
<5%
Max. Dry Density (pcf)*
137.1
Optimum Moisture (%)*
7.3
Test Values At Other Oversize Percentages
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
137.1
138.6
140.1
141.7
.143.3
144.9
146.6
7.3
7.0
6.7
6.4
6.0
5.7
5.4
values corrected for oversize material per ASTM D4718, using assumed Specific Gravity shown d der ize moirstur content of 1%
Reviewed By: FIGURE 1
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
o
1.-0
o
(D
C)
c6i
M Co
CD
0
U-
0,
0
0,
:t'-
CD
CD
(0
"Ol
0-1
E
CO
111
0
N
6
14-
C�
0-
co
ri
en
9
m
cro
0
cn
2 (n
C�
C)
F-
1--
(0
m
0
a) m
c D
C6
00
LO
C�
Cf)
an
N
CCD
CD
0
CD
CD
CD
C)
C)
C)
C�
U)
o
o
o
0
5
o
E
o
s
S
L)
co
T.-
Tf
(N
M
'IT
U)
(D
00
0
—
0
N
s
E
s
5
I
0
0
6
6
6
6
0
0
0
0
>
00
r-
(a
Lr)
"T
ce)
T-
N
—
—
It
I—
00
z
z
z
z
z
z
Z
Z
Z
Z
6
Z
6
Z
.q)
U)
--
N
c1r)
LO
(Y)
2
M
z
< F=
U)
w
N
U)
]ID w
>
w
0
Z
U)
rn
m
0
U)
w
-j
m
co
0
C-)
D4—
iz
1M�
p-
.M
MEP Wom
;m ,,..Mmmmmmmmm
C) 0 C) C) C) 0 0 0 0 0 0
O 0) co r- (0 LO Ce) N —
IH!DIEIAA,kg �EINI=l IN�IMADd
01
z
W
C:
a)
E
0
2
0- LD
E m
>, �:
-0 U-a�
co 0
0
a) E
w
co
LO
I-
wV
NPZ
O con
UJ
w
W4
D
LL
CD
0
' LABORATORY COMPACTION CHARACTERISTICS OF SOIL
CLIENT: City of Edmonds H-.kkGEOSCIENCES INC.
' PROJECT: 76th Ave W/75th PI W Walkway and 162nd St SW SAMPLE ID: AG-2
PROJECT NO: 2006-171-21 T- 300 Sampled By: BC Tested By: AAC
Date Sampled: 121812009 Date Received: 121812009 Date Tested: 121812009
u
1-1
0
MATERIAL TYPE OR DESCRIPTION:
Crushed Surfacing Base Course
MATERIAL SOURCE, SAMPLE LOCATION AND DEPTH:
Glacier, Kenmore
Designation: F-]ASTM D 698
Method: F-]A B
Preparation: Dry . QX Moist
❑X ASTM D 1557 Natural Moisture Content: 3.4 %
OX C Oversize: 23.3 % retained on: 314 in.
Rammer:OX Auto Manual Assumed S.G.: 2.8
Test Data
Dry Density (pcf)
129.8
135.5
1 135.4
131.4
Moisture Content (%)
3.477
5.3
1 7.5
9.6
Rock Corrected Curve
Proctor Curve
,, , Saturation Line
■■■■■Lab
■��■■i
■■■■■■�
�n�■A►Q■
®■■■ra■�uii
■■■
■gin
■n
■m
-■
■m
■■
MMEMEEMEMM
■�■■■nn■�i■�
ii■�ri■■ro■
Data Summa *
Percent Oversize
23.3%
Max. Dry Density (pcf)*
143.5
Optimum Moisture (%)*
5.1
Test Values At Other Oversize Percentages
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
136.1
137.6
139.2
140.8
142.4
144.1
145.8
6.3
6.0
5.8
5.5
5.2
5.0
4.7
values correctea Tor oversize material per A51 M 04718, using assumed Specific Gravity shown o ze moi content of 1%a
Reviewed By: FIGURE 1
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
' APPENDIX C
PORTLAND CEMENT CONCRETE TESTING
RESULTS
r,l
11
FIELD AND LABORATORY CONCRETE TEST REPORTEKI ,
ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 j jWAGEOSCIENCES INC.
❑ AASHTO T23, T22, Tl l9, T141, T152, T309
CLIENT: City of Edmonds TEST/SET # $CDF-1
PROJECT: 76th Ave W175th PI W Walkway and 162nd St SW DATE CAST: 811112009
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 811212009
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Wall 1 Piles 1, 3, 5 and 7
COMPRESSIVE
STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-$CDF-1A
7
12352.3
8118109
6X12
6.00
28.27
7380
260
2
EJB
2006-171-21-$CDF-18
28
12375.7
918109
6X12
6.00
28.27
11710
410
4
AC
2006-171-21-$CDF-1C
- 28
12364.4
918109
6X12
6.01
28.37
11980
420
2
AC
2006-171-21-$CDF-1D
H
Specified Minimum:] 1000 IDg[�jIA1�j [[fl
1 2 3 4 5
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/dd/yy)
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. Specified Minlmum:l
INFO. FROM SUPPLIER TICKET
Supplier Name: Salmon Bay Sand and Gravel Max: Agg. Size (in): 80-20 Pea
Time Batched: 10:48AA4
Plant Number: Cement Type:
Arrival Time:
Mix Code / No.: M15120 Load Volume (yd3): 10
Start Unloading:
Truck Number: 37 Cum. Volume (yd3): 10
End Unloading:
Ticket Number: Y6006246 Admixtures: Fly Ash, MBAE80
FIELD TEST DATA
Slump (inches): 6 Specified Slump (min -max): 6 to 8
Time Sampled: 12:25PM
Entrained Air (%): NA Specified Ent. Air (min -max): NA
Time Cyl.s Cast: 12:30
Conc. Temp. (F): 70 Ambient Air Temperature (F): 61
Cast By: ESW
Density (pcf): Initial Curing Temp (min -max): 62-74
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Concrete Placement Method: Tailgating
Field test results reported to
(Contractor Representative on Site)
Field test results reported to Jaimie HawkinsQim Roberts
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the following truckloads:
Additional air tests on the following truckloads:
Reviewed By:
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORT
0 ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 HWAGEOSCIENCES INC.
AASHTO T23, T22, T119, T141, T152, T309
CLIENT: City of Edmonds TEST/SET # $CDF-2
PROJECT: 76th Ave W/75th PI W Walkway and 162nd St SW DATE CAST: 811212009
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 811312009
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Wall 1 Piles 6, 8 and 10.
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"A")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-$CDF-2A
7
12448.9
8119109
6x12
6.01
28.37
11320
400
2
EJB
2006-171-21-$CDF-28
28
12509
919109,
6x12
6.00
28.27
20680
730
2
AC
2006-171-21-$CDF-2C
28
1 12466.3
919109
6X12
6.00
28.27
21120
750
2
AC
2006-171-21-$CDF-2D
H
12491.2
5pecitiea Ivunlmum:L 2uuu NL�jLx W
1 2 3 4 5
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/dd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. SpeClTlea minimum:
INFO. FROM SUPPLIER TICKET
Supplier Name: Salmon Bay Sand and Gravel Max: Agg. Size (in): 80-20 Pea
Time Batched: 8:37AM
Plant Number: Cement Type: !-I/
Arrival Time: 9:30AM
Mix Code / No.: M20120 Load Volume (yd3): 6
Start Unloading:
Truck Number: 77 Cum. Volume (yd3): 6
End Unloading:
Ticket Number: Y6006294 Admixtures: Fly Ash, MBAE80
FIELD TEST DATA
Slump (inches): 6.5 Specified Slump (min -max): 6 to 8
Time Sampled: 10:35AM
Entrained Air (%): NA Specified Ent. Air (min -max): NA
Time Cyl.s Cast: 10:43AM
Conc. Temp. (F): 69 Ambient Air Temperature (F): 62
Cast By: ESW
Density (pcf): Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Concrete Placement Method: Tailgating
Field test results reported to
(Contractor Representative on Site)
Field test results reported to Jaimie Hawkins/Jim Roberts
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the following truckloads:
Additional air tests on the following truckloads:
Reviewed By:
This report applies only to the items tested, and maybe reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORT Im,
❑X ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 HWAGEOSCIENCES INC.
❑ AASHTO T23, T22, Tl l9, T141, T152, T309
CLIENT: City of Edmonds TEST/SET # SCDF-3
PROJECT: 76th Ave W175th P► W Walkway and 162nd St SW , DATE CAST: 812712009
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 8/128/2009
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Wall 4,Pile Numbers 15, 17 and 19
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-$CDF-3A
7
11605
913109
6x12
6.00
28.27
8470
300
2
AC
2006-171-21-$COF-3a
28
11597.1
9124109
6x12
6.00
28.27
12720
450
2
AC
2006-171-21-$CDF-3C
28
1 11617.9
9124109
6x12
6.01
28.37
11830
420
5
EJB
2006-171-21-$CDF-3D
H
11591.1
5pecitied Minimum:) 300
1 9 'A d S
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/ddlyy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. 5pecitied Mlnlmum:l
INFO. FROM SUPPLIER TICKET
Supplier Name: Salmon Bay Sand and Gravel Max: Agg. Size (in): 60-20 Pea
Time Batched: 6:57AM
-Plant Number:
Cement Type: /41
Arrival Time: 7:45AM
Mix Code / No.: M20120
Load Volume (yd3): 10
Start Unloading:
Truck Number: 73
Cum. Volume (yd3): 10
End Unloading:
Ticket Number: Y606922
Admixtures: Fly Ash, MBAE80
FIELD TEST DATA
Slump (inches): 10
Specified Slump (min -max): 6 to 8
Time Sampled: 8:30AM
Entrained Air (%): NA
Specified Ent. Air (min -max): NA
Time Cyl.s Cast: 8:45AM
Conc. Temp. (F): 70
Ambient Air Temperature (F): 62
Cast By: JH
Density (pcf):
Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION ! COMMENTS
Contractor / SubContractor:
Kulchin Foundation Drilling
Concrete Placement Method:
Pump
Field test results reported to
Brian
(Contractor Representative on Site)
Field test results reported to
Jaime Hawkins
(Client/Owner's Rep. on Site)
Additonal slump tests on the
following truckloads:
HWA also visually assessed the
following truckloads:
Additional air tests on the following truckloads:
Reviewed By: �L11W,1,21 IFO, -A
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORT
❑X ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 HWAGEOSCIENCES INC.
❑ AASHTO T23, T22, T119, T141, T152, T309
CLIENT: City of Edmonds TEST/SET # G-1
PROJECT: 76th Ave W/75th P/ W Walkway and 162nd St SW DATE CAST: 411312010
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 411912010
EDESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Test Cylinders with 6 gallons of water per 100 pound bag, ( hand mixed on site by Eric with Precision)
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-G-1A
7
2775.4
4120110
4x8
4.01
12.63
31290
2480
2
AC
2006-171-21-G-1B
7
2785.5
4120110
48
4.01
12.63
31590
2500
2
AC
2006-171-21-G-1C
2006-171-21-G-1O
Specified Minimum:) 300 IZII�O /zn
1 2 1 4 5
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/dd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. 5pecitled Mlnlmum:I
INFO. FROM SUPPLIER TICKET
Supplier Name: Cemex
Max: Agg. Size (in): N/A
Time Batched: 14:10
Plant Number: Everett
Cement Type: Type 1///
Arrival Time:
Mix Code / No.: 1189027
Load Volume (ycl): 94lbs
Start Unloading: 14:30
Truck Number: Hand Mixed Cum. Volume (yd3): 94lbs
End Unloading:
Ticket Number:
Admixtures:
FIELD TEST DATA
Slump (inches): 9
Specified Slump (min -max): 9 (+-1')
Time Sampled: 14:30
Entrained Air (%):
Specified Ent. Air (min -max): na
Time Cyl.s Cast: 14:35
Conc. Temp. (F):
Ambient Air Temperature (F): 53
Cast By: BC
Density (pco:
Initial Curing Temp (min -max): Field Cure
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Precision Earthworks/NTN Construction
Concrete Placement Method:
Field test results reported to
(Contractor Representative on Site)
Field test results reported to
' (Client/Owner's Rep. on Site)
Additonal slump tests on the
following truckloads:
HWA also visually assessed the following truckloads:
Additional air tests on the following truckloads:
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORTFXJ ,
ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 HWAGEOSCIENCES INC.
El AASHTO T23, T22, T119, T141, T152, T309
CLIENT: City of Edmonds TEST/SET # G-2
PROJECT: 76th Ave W175th P/ W Walkway and 162nd St SW DATE CAST: 411512010
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 411912010
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Test Cylinders with 5 gallons of wafer per 100 pound bag, ( hand mixed on site by Eric with Precision)
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
LD.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-G-2A
7
2595.3
4122110
4x8
3.99
12.50
15780
1260
3
AC
2006-171-21-C-78
7
2653.7
4122110
4x8
3.99
12.50
17070
1370
3
AC
2006-171-21-C-7C
2006-171-21-C-70
Specified Minimum: 300 INNIA M
1 2 3 4 5
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/dd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. JpeClTleu iviinimum:l
INFO. FROM SUPPLIER TICKET
Supplier Name: Cemex
Max: Agg. Size (in): NIA
Time Batched: 11:40
Plant Number: Everett
Cement Type: Type llll
Arrival Time:
Mix Code / No.: 1189027
Load Volume (yd3): 94lbs
Start Unloading: 12:00.
Truck Number: Hand Mixed Cum. Volume (yd3): 94lbs
End Unloading:
Ticket Number:
Admixtures:
FIELD TEST DATA
Slump (inches): 9
Specified Slump (min -max): 9 (+1 to -1)
Time Sampled: 12:00
Entrained Air (%):
Specified Ent. Air (min -max): 1.0%
Time Cyl.s Cast: 12:35
Conc. Temp. (F):
Ambient Air Temperature (F): 48
Cast By: BC
Density (pcf):
Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Precision EarthworkslNTN Construction
Concrete Placement Method:
Field test results reported to
(Contractor Representative on Site)
Field test results reported to
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the following truckloads:
Additional air tests on the following truckloads:
11 let
Reviewed By: 62�,
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORTEXI �,
ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 HWAGEOSCIENCES INC.
AASHTO T23, T22, Tl l9, T141, T152, T309
CLIENT: City of Edmonds TEST/SET # G-3
PROJECT: 76th Ave W175th PI W Walkway and 162nd St SW DATE CAST: 412212010
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 412312010
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Rock climbing wa)Y Play slide area.
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xi")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH,
2006-171-21-G-3A
1
2880.3
4123110
4x8
4.03
12.76
8440
660
2
AAC
2006-171-21-G-3B
1
2908.6
4123110
48
3.99
12.50
11030
880
2
AAC
2006-171-21-G-3C
4
2835.5
4126110
4x8
4.01
12.63
17160
1360
3
JH
2006-171-21-G-3D
4
2860.6
4126110
48
4.02
12.69
21780
1720
5
JH
5pecinea minimum:) juu iNie&i0E[W
1 2 3 4 5
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/dd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. Specitiea Mlnlmum:l
INFO. FROM SUPPLIER TICKET
Supplier Name: Mason Supply Max: Agg. Size (in): N/A
Time Batched: 7.00
Plant Number: Lynnwood Cement Type: Type 1/ll
Arrival Time:
Mix Code / No.: 1189027 Load Volume (yd3): 94/bs
Start Unloading: 7:15
Truck Number: Paco 14hp Mixer Cum. Volume (yd3): 94/bs
End Unloading:
Ticket Number: Admixtures:
FIELD TEST DATA
Slump (inches): 10 Specified Slump (min -max): 9 (+1 to -1)
Time Sampled: 7:15
Entrained Air (%): Specified Ent. Air (min -max): 1.0%
Time Cyl.s Cast: 7:20
Conc. Temp. (F): Ambient Air Temperature (F): 45
Cast By: BC
Density (pcf): Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor: Precision Earthworks/NTN Construction
Concrete Placement Method:
Field test results reported to
(Contractor. Representative on Site)
Field test results reported to
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the following truckloads:
Additional air tests on the following truckloads:
Reviewed By: l a 1
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
FIELD AND LABORATORY CONCRETE TEST REPORT
M ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 HWAGEOSCIENCES INC.
❑ AASHTO T23, T22, T119, T141, T152. T309
CLIENT: City of Edmonds TEST/SET # gc-1
PROJECT: 76th Ave W175th PI W Walkway and 162nd St SW DATE CAST: 1013012009
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 1013112009
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Driveway Right of Center Line on 76th Ave at address 16411.
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl')
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-$C-1A
7
3909.8
1116109
4x8
4.00
12.57
53890
4290
2
EJB
2006-171-21-$C-18
28
3923
11127109
4x8
4.00
12.57
68180
5430
2
EJB
2006-171-21-$C-1C
28
1 3882.1
11127109
4x8
1 4.01
12.63
68670
5450
2
EJB
5pecinea Ivllnimum:l 4uuu j jNt�jAE[W
1 2 3 4 5
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mmfdd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH,
Li
i -
i
I
i
i
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. Specmed Mlnlmum:l
INFO. FROM SUPPLIER TICKET
Supplier Name: Glacier
Max: Agg. Size (in): 314"
Time Batched: 9:52AM
Plant Number: 260
Cement Type: 1-11
Arrival Time: 10:20AM
Mix Code / No.: 3717
Load Volume (yd3): 10.5 '
Start Unloading:
Truck Number: 7666
Cum. Volume (yd3): 10.5
End Unloading:
Ticket Number: 294680
Admixtures: AEA, WRA
FIELD TEST DATA
Slump (inches): 4.5
Specified Slump (min -max): 4.5
Time Sampled: 11:00AM
Entrained Air (%): 5.5
Specified Ent. Air (min -max): 4.5-7.5
Time Cyl.s Cast: 11:05AM
Cone. Temp. (F): 70
Ambient Air Temperature (F): 62
Cast By: AR
Density (pcf):
Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Concrete Placement Method:
Tail gating
Field test results reported to
(Contractor Representative on Site)
Field test results reported to
(Client/Owner's Rep. on Site)
Additional slump tests on the following truckloads:
HWA also visually assessed the
following truckloads:
Additional air tests on the following truckloads:
Reviewed By: `
r - /-- 6
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORT,
❑X ASTM C 31, C 39, C76, C 143, C172, C231, C1064, C1231 MAGEOSCIENCES INC.
Q AASHTO T23, T22, T119, T141, T152, T309
CLIENT: City of Edmonds TEST/SET # C-2
PROJECT: 76th Ave W175th PI W Walkway and 162nd St SW DATE CAST: 1112312009
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 1112412009
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Elevated sidewalk footing and wall along West edge of 75th between stations 32+00 and 34+50
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-C-2A
7
4018.3
11130109
4x8
4.01
12.63
100650
7970
1
EJB
2006-171-21-C-2B
28
3982.9
12121109
4x8
4.02
12.69
124740
9830
2
HS
2006-171-21-C-2C
28
4004.5
12121109
4x8
4.02
12.69
126240
9950
6
HB
2006-171-21-C-2D
H
3980.2
bpeCi lea Ivunlmum:L ouuu I�I��IJWJ
1 2 3 4 5
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/ddlyy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
El
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. JpeClTlea iviinimum:l
INFO. FROM SUPPLIER TICKET
Supplier Name: Cal Portland Max: Agg. Size (in): 314"
Time Batched: 9:40
Plant Number: 261
Cement Type: /41
Arrival Time: 10:45
Mix Code / No.: 1517
Load Volume (yd): 9.5
Start Unloading: 11:30
Truck Number: 7184
Cum. Volume (yd): 9.5
End Unloading:
Ticket Number: 297823
Admixtures: AEA, WRA, ADVA
FIELD TEST DATA
Slump (inches): 3.5
Specified Slump (min -max): 5.5
Time Sampled: 11:40
Entrained Air (%): 6.3
Specified Ent. Air (min -max): 4.5-7.5
Time Cyl.s Cast: 11:45
Conc. Temp. (F): 71
Ambient Air Temperature (F): 51
Cast By: BC
Density (pcf):
Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Concrete Placement Method:
Tail gating.
Field test results reported to
(Contractor Representative on Site)
Field test results reported to
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the
following truckloads:
Additional air tests on the following truckloads: a
Reviewed By:
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORT
❑X ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 HWAGEOSCIENCES INC.
AASHTO T23, T22, T119, T141, T152, T309
CLIENT: City of Edmonds TEST/SET # C-3
PROJECT: 76th Ave W175th P/ W Walkway and 162nd St SW DATE CAST: 1112312009
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE RECD: 1112412009
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Elevated sidewalk footing and wall along West edge of 75th between stations 32+00 and 34+50
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xi")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-C-3A
7
3909.8
11130109
4x8
4.01
12.63
98180
7770
1
EJB
2006-171-21-C-38
28
3923
12121109
4x8
4.01
12.63
125150
9910
2
HB
2006-171-21-C-3C
28
3882.1
12121109
4x8
4.02
12.69
123470
9730
1
HB
2006-171-21-C-3D
H
Specified Minimum: 5� 000 MAIA[fj1W
1 2 3 4 5
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/dd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. Specifed Minimum:)
INFO. FROM SUPPLIER TICKET
Supplier Name: Cal Portland Max: Agg. Size (in): 314"
Time Batched: 13:35
Plant Number: 261 Cement Type: 1-1/
Arrival Time: 14:40
Mix Code / No.: 1517 Load Volume (yd): 9
Start Unloading: 15.04
Truck Number: 7166 Cum. Volume (yd3): 57.5
End Unloading:
Ticket Number: 297948 Admixtures: AEA, WRA. ADVA
FIELD TEST DATA
Slump (inches): 5.5 Specified Slump (min -max): 5.5
Time Sampled: 15:15
Entrained Air (%): 6.0 Specified Ent. Air (min -max): 4.5-7.5
Time Cyl.s Cast: 15.25
Conc. Temp. (F): 70 Ambient Air Temperature (F): 56
Cast By: BC
Density (pcf): Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Concrete Placement. Method: Tail gating
Field test results reported to
(Contractor Representative on Site)
Field test results reported to
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the following truckloads:
Additional air tests on the following truckloads:
Reviewed By:
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORT IF",
El ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 HWAGEOSCIENCES INC.
❑ AASHTO T23, T22, T119, T141, T152, T309
CLIENT: City of Edmonds TEST/SET#C-4
PROJECT: 76th Ave W175th P,1 W Walkway and 162nd St SW DATE CAST: 1112712009
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 1112812009
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Contractor supplied cores of reinforced concrete (cores contain rebar).
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-C-4A
B
9899.5
11130109
10
5.70
25.54
73490
2880
2
EJB
2006-171-21-C-4B
9979.2
11130109
10
5.70
25.52
72790
2850
2
EJB
Specified Minimum: l 4000 j[XN I& kiH
1 2 3 4 5
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
mmidd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. Specitiea iviinlmum: j
INFO. FROM SUPPLIER TICKET
Supplier Name: Cal Portland Max: Agg. Size (in):
Time Batched:
Plant Number: Cement Type:
Arrival Time:
Mix Code / No.: Load Volume (yd3):
Start Unloading:
Truck Number: Cum. Volume (yd):
End Unloading:
Ticket Number: Admixtures: AEA, WRA. ADVA
FIELD TEST DATA
Slump (inches): Specified Slump (min -max):
Time Sampled:
Entrained Air (%): Specified Ent. Air (min -max):
Time Cyl.s Cast:
Conc. Temp. (F): Ambient Air Temperature (F):
Cast By:
Density (pcf): Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Concrete Placement Method: Tail gating
Field test results reported to.
(Contractor Representative on Site)
Field test results reported to .
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the following truckloads:
Additional air tests on the following truckloads:
Reviewed By:
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORT i'",
El ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 IIWAGEOSCIENCESINC.
0 AASHTO T23, T22, T119, T141, T152, T309
CLIENT: City of Edmonds TEST/SET # C-5
PROJECT: 76th Ave W175th PI W Walkway and 162nd St SW DATE CAST: 1212812009
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 12/29/2009
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Elevated sidewalk footing and wall along West side of 75th Place West between stations 44+00 and 45+00
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-C-5A
3
12131109
4x8
4.01
12.63
72630
5750
2
AAC
2006-171-21-C-5C
7
3891.1
114110
4x8
4.02
12.69
93940
7400
5
AAC
2006-171-21-C-5D
28
3920.6
1125110
4x8
4.01
12.63
125070
9900
1 1
AAC
2006-171-21-C-5E
28
3894
1125110
4x8
4.03
12.76
121740
9540
1
AAC
5pecirlea iwnlmum:l ouuu jNL1 1[&j[ U
4 1 'Y d F
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/dd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN *
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. Specifed Mlnlmum:l
INFO. FROM SUPPLIER TICKET
Supplier Name: Cal Portland Max: Agg. Size (in): 314"
Time Batched: 9:25
Plant Number: 261
Cement Type: /-ll
Arrival Time: 10:15
Mix Code / No.: 1517
Load Volume (yd3): 9.5
Start Unloading: 10:30
Truck Number: 7357
Cum. Volume (yd3): 24
End Unloading:
Ticket Number:. 301984
Admixtures: AEA, WRA. ADVA
FIELD TEST DATA
Slump (inches): 3.5
Specified Slump (min -max): 5.5
Time Sampled: 10:35
Entrained Air (%): 6.1
Specified Ent. Air (min -max): 4.5-7.5
Time Cyl.s Cast: 10:45
Conc. Temp. (F): 66
Ambient Air Temperature (F): 47
Cast By: BC
Density (pcf):
Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Concrete Placement Method:
Tail gating
Field test results reported to
(Contractor Representative on Site)
Field test results reported to
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the
following truckloads:
Additional air tests on the following truckloads:
f
Reviewed By:
This report applies only to the hems tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORT
❑X ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 HWAGEOSCIENCES INC.
AASHTO T23, T22, T119, T141, T152, T309 '
CLIENT: City of Edmonds TEST/SET # C-6
PROJECT: 76th Ave W175th PI W Walkway and 162nd St SW DATE CAST: 112912010
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 113012010
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Elevated sidewalk wall repair and retaining wall on the southern side of the walkway.
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-C-6A
7
3894.1
215110
4x8
4.01
12.63
69500
5500
2
AAC
2006-171-21-C-6C
28
4000.3
2126110
4x8
4.00
12.57
82830
6590
2
AR
2006-171-21-C-6D
28
3945.6
2126110
48
4.02
12.69
84410
6650
2
AR
speclnea Mlnimum:l suuu INL&611��LW
1 2 3 4 5
- FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mmidd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. Specifea minimum:1
INFO. FROM SUPPLIER TICKET
Supplier Name: Cal Portland Max: Agg. Size (in): 314"
Time Batched: 12:09
Plant Number: 261
Cement Type: 1-11
Arrival Time: 1:00
Mix Code / No.: 1997
Load Volume (yd): 9.5
Start Unloading: 1:15
Truck Number: 7675
Cum. Volume (yd3): 9.5
End Unloading:
Ticket Number: 306304
Admixtures: AEA, WRA. ADVA
FIELD TEST DATA
Slump (inches): 4.5
Specified Slump (min -max): 5.5
Time Sampled: 1:20
Entrained Air (%): 4.5
Specified Ent. Air (min -max): 4.5-7.5
Time Cyl.s Cast: 1:30.
Conc. Temp. (F): 70
Ambient Air Temperature (F): 50
Cast By: AR
Density (pcf):
Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor.
Concrete Placement Method:
Tail gating
Field test results reported to -
(Contractor Representative on Site)
Field test results reported to
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the following truckloads:
Additional air tests on the following truckloads:
Reviewed
r
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
FIELD AND LABORATORY CONCRETE TEST REPORT
0 ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231 HWAGEOSCIENCES INC.
AASHTO T23, T22, T119, T141, T152, T309
CLIENT: City of Edmonds TEST/SET # C-7
PROJECT: 76th Ave W175th PI W Walkway and 162nd St SW DATE CAST: 411512010
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 113012010
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Wall footings for the swings play area in northwest section of park and play area at climbing rock jumble/slide,
play area wall at slide, and stairways immediately north and south of rock jumble/slide play area.
COMPRESSIVE STRENGTH
TEST DATA"
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL.
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-C-7A
7
3959
4122110
4x8
4.00
12.57
68340
5440
5
AC
2006-171-21-C-7B
28
3968
5113110
4x8
4.00
12.57
88880
7070
2
AC
2006-171-21-C-7C
28
3945
5113110
4x8
4.01
12.63
86020
6810
2
AC
2006-171-21-C-7D
H
3968
HOLD
4x8
5pecinea Ivllnlmum:l 3uuu jINL�jL611�l[W
1 7 'A d 5
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/dd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.)
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. Specaiea iviinlmum: l
INFO. FROM SUPPLIER TICKET
Supplier Name: Cal Portland Max: Agg. Size (in): 314"
Time Batched: 8:15
Plant Number: 282
Cement Type: 1-11
Arrival Time: 9.20
Mix Code / No.: 3136
Load Volume (yd3): 10
Start Unloading: 9:30
Truck Number: 7625
Cum. Volume (yd3): 10
End Unloading: 9.45
Ticket Number: 317029
Admixtures: AEA, WRA, Fly Ash
FIELD TEST DATA
Slump (inches): 4
Specified Slump (min -max): 4
Time Sampled: 9:35
Entrained Air (%): 5.0
Specified Ent. Air (min -max): 5-7%
Time Cyl.s Cast: 9:50
Conc. Temp. (F): 60
Ambient Air Temperature (F): 47
Cast By: KJS
Density (pcf):
Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Precision Earthworks/NTN Construction
Concrete Placement Method:
Brundage Bone Concrete Pump truck and directly from chute
Field test results reported to
Moe of Precision Earthworks
(Contractor Representative on Site)
Field test results reported to
Jim Roberts, City of Edmonds
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the
following truckloads: 2-5
Additional air tests on the following truckloads:
Reviewed By:
This report applies only to the items tested, and may be reproduced In full, with written approval of HWA GEOSCIENCES INC.
-FIELD AND LABORATORY CONCRETE TEST REPORT
ASTM C 31, C 39, C78, C 143, C172, C231, C1064, C1231
❑ AASHTO "23, T22, T119, T141, T152, T309
CLIENT: City of Edmonds
PROJECT: 76th Ave W175th P1 W Walkway and 162nd St SW
it
HWAGEOSCIENCES INC.
TEST/SET # C-8
DATE CAST: 412712010
HWA PROJECT NO: 2006-171-21 HWA TASK NO.: 400 DATE REC'D: 412812010
DESCRIPTION OF CONCRETE PLACEMENT REPRESENTED BY THIS TEST:
Walls at the swings play area and at climbing rock jumble/slide, and lower sidewalk in northeast section of park.
COMPRESSIVE STRENGTH
TEST DATA
CYLINDER
I.D.
NUMBER
AGE
(days)
CYL,
WEIGHT
(grams)
TEST
DATE
(mm/dd/yy)
CYL.
TYPE
(d"xl")
DIAMETER
(inches)
X-SECT.
AREA
(sq. in.)
MAX.
LOAD
(Ibs)
COMPR.
STRENGTH
(psi)
FRAC.
TYPE
TECH.
2006-171-21-C-8A
7
3880
514110
4x8
4.01
12.63
46110
3650
1
AC
2006-171-21-C-8B
28
3867
5125110
4x8
4.01
12.63
69820
5530
1
AC
2006-171-21-C-8C
28
3857
5125110
4x8
4.01
12.63
69710
5520
1
AC
2006-171-21-C-8D
28,
3846
5125110
4x8
4.00
12.57
70090
5580
2
AC
5pecitied Minimum:1 3000 JNJ,�JUZUE
1 7 i d ri
FLEXURAL STRENGTH TEST DATA
BEAM
I.D.
NUMBER
AGE
(days)
TEST
DATE
(mm/dd/yy
AVG.
WIDTH
b (in.)
AVG.
DEPTH
d (in.)
SPAN
L (in.) .
FRACTURE
LOCATION
a (in.)
MAXIMUM
LOAD
P (Ibs)
MODULUS OF
RUPTURE
R (psi)
TECH.
F�
Unless otherwise indicated, samples are tested in a moist surface condition using leather shims. 5pecitied Mlnlmum: l
INFO. FROM SUPPLIER TICKET
Supplier Name: Cal Portland Max: Agg. Size (in): 314"
Time Batched: 7.15
Plant Number: 261
Cement Type: 1-1l
Arrival Time: 8:00
Mix Code / No.: 3136
Load Volume (yd3): 10
Start Unloading: 8:05
Truck Number: 7665
Cum. Volume (yd3): 10
End Unloading: 9:30
Ticket Number: 318704
Admixtures: AEA, WRA, Fly Ash
FIELD TEST DATA
Slump (inches): 4.5
Specified Slump (min -max): 4
Time Sampled: 8:15
Entrained Air (%): 5.5
Specified Ent. Air (min -max): 5-7%
Time Cyl.s Cast: 8:25
Conc. Temp. (F): 70
Ambient Air Temperature (F): 50
Cast By: KJS
Density (pcf):
Initial Curing Temp (min -max):
Mold Type: Plastic
MISCELLANEOUS INFORMATION / COMMENTS
Contractor / SubContractor:
Precision Earthworks/NTN Construction
Concrete Placement Method:
Brundage Bone Concrete Pump truck and directly from chute
Field test results reported to
Moe of Precision Earthworks
(Contractor Representative on Site)
Field test results reported to
Edward Sibrel, City of Edmonds
(Client/Owner's Rep. on Site)
Additonal slump tests on the following truckloads:
HWA also visually assessed the following truckloads: 2-5
Additional air tests on the following truckloads:
Reviewed By:
This report applies only to the items tested, and may be reproduced in full, with written approval of HWA GEOSCIENCES INC.
I APPENDIX D
I HOT MIX ASPHALT PAVEMENT TESTING
RESULTS
RICE DENSITY RESULTS OF HOT MIX ASPHALT SAMPLES i` "MIV,
CLIENT: City of Edmonds HWAGEOSCIENCES INC.
PROJECT: 76th Ave W175th Pi W Walkway and 162nd St SW
PROJECT NO: 2006-171-21 T-.300
Sam le ID
Sampled
Date.
Sample Description
Sample Source
Rice Density
(pcf)
HMA -1
11/24/2009
HMA Class 1/2-inch
CEMEX, Kenmore
154.7
HMA -3
11/25/20091
HMA Class 1/2-inch
CEMEX, Kenmore
154.9
HMA -4
11/30/2009
HMA Class 1/2-inch .
CEMEX, Kenmore
155.3
HMA -5
12/1/2009
HMA Class 1/2-inch
CEMEX, Kenmore
155.3
HMA -6
12/2/2009
HMA Class 1/2-inch
CEMEX, Kenmore
155.3
HMA -7
3/17/2010
HMA Class 1/2-inch
CEMEX, Kenmore
154.6
HMA -8
5/26/2010
HMA Class 1/2-inch
CEMEX, Kenmore
154.6
Note: Sample HMA-2 does not exist. This sample designation was skipped inadvertently.
E
C:)
x
00
wo
E
C:) cu LO
1 2
IN
_j
C)
00
00
"o
0
N
cNi
0
U)
U)
C)
CO
C)
a) .C:
- --
�0',
C-i
L cn
C/)
C)
CD
-LO N
C)
(0
cy�
m
0)
m
NT
Sri
n
ce)
9
0
(D
U)
0 0
C)
LO
C)
C)
LU
0
0
0
CN
0--a
U) C:
U)
>
N
Ncy)
C'*l 00 Z
o
Z z z
o
z
6
C/)
0
U)
CY)
z
o
D
?=
Z
<
I
L
z
0
0
0
CN
[L-
Fn
U)
C;
LL
C)
LO
.... .
......
0
......
cn
E
.........
:3
..........
.......
w
..........
...............
cn
z
x
a)
...
.........
Of
o...
... ..
..........
..........
.
W
o
U)
CO
C6
-- — —
— — —
— — —
— — —
C)
--I-! r-i --i"
w
XV1,:�r
<
ce)
(D
cu—
— —
— — —
— — —--
— —
0
>
I
:,
C, CD CD C, C) 0 C) 0 c,
O 0) co
rl- (0 LO
m
N
O
U)
w
HOIAMAE] 2:ONI=l IN�0bgd
—1
00
2IL
<
2
U)
LO
r
-
z
0
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
RESUB RECEIVE[
JUL 10 2000
BU MAY 3 0 2008
ENGNEERMG DIVISION
REVISED GEOTECHNICAL REPORT
76th Avenue West ,& 75th Place West
Walkway Improvements
Edmonds, Washington
HWA Project No. 2006-171-21
Prepared for
Gray & Osborne, Inc.
November 16, 2007 (Revised May 30, 2008)
HWAGEOSCIENCES INC.
• Geotechnical Engineering
• Hydrogeol ogy
• Geoenvironmental Services
• Inspection & Testing
�T11, HWA GEOSCIENCES INC.
Geotechnical & Pavement Engineering • Hydrogeology • Geoenvironmental • Inspection & Testing
May 30, 2008
HWA Project No. 2006-171-21
Gray & Osborne, Inc.
701 Dexter Avenue North, Suite 200
Seattle, Washington 98109
Attn: Ms. Tani Stafford P.E.
Project Manager
REVISED GEOTECHNICAL REPORT
' 76TH AVENUE WEST AND 75TH PLACE WEST WALKWAY IMPROVEMENTS
EDMONDS, WASHINGTON
IDear Tani:
_ As requested, HWA GeoSciences Inc. completed stability analyses studies for the
proposed park improvements at 162na Street and included their results into this revised
geotechnical report for 76th Avenue West and 75th Place West Walkway Improvements.
The results of our investigations and geotechnical recommendations for the proposed
facilities are presented in this report.
We appreciate the opportunity to provide geotechnical services on this project.
Sincerely,
HWA GEOSCIENCES INC.
Ralph N. oirum, P.E.
Geotechnical Engineer
Principal
Enclosure: Revised Geotechnical Report
19730 - 64th Avenue W.
Suite 200
Lynnwood, WA 98036.5957
Tel: 425.774.0106
Fax: 425.774.2714
www.hwageo.com
1
ll
TABLE OF CONTENTS
t1.
INTRODUCTION.......................................................................................................
Page
1.1 SITE AND PROJECT DESCRIPTION.................................................................1
2. EXPLORATIONS AND GEOLOGIC CONDITIONS............................................................2
2.1 SUBSURFACE EXPLORATIONS.......................................................................2
2.2 GENERAL GEOLOGIC CONDITIONS...............................................................3
2.3 LANDSLIDE HISTORY.....................................................................................3
2.3 SUBSURFACE CONDITIONS............................................................................4
'
2.5 GROUND WATER CONDITIONS......................................................................5
2.6 LABORATORY TESTING .................................................................................5
1.1 SITE AND PROJECT DESCRIPTION.................................................................1
' 3. RECOMMENDATIONS..................................................................................................6
3.1 GENERAL ..6
3.2 EARTH RETAINING STRUCTURES.................................................................6
3.3 PILE SUPPORTED WALKWAYS.....................................................................7
3.4 PAVEMENTS...................................................................................................7
3.5 PARK DESIGN................................................................................................8
3.5.1 Stability..........................................................................................8
3.5.2 Park Drainage..............................................................................9
3.5.3 Foundation Design.......................................................................9
3.5.4 Park Pavement.............................................................................10
4.0 CONDITIONS AND LIMITATIONS................................................................................10
LIST OF FIGURES (FOLLOWING TEXT
Figure 1
Vicinity Map
Figures 2-4
Site and Exploration Plan
'
Figure 5
Park Property Exploration Plan
Figure 6
Proposed Park Plan
Figure 7
Cross Section A -A'
'
Figure 8
Log of Previous Test Boring HWA-1
Figure 9A & 9B
Boring HWA-3 Inclinometer Plot
Figure 10
Boring BH-1 Inclinometer Plot
Figure 11
Stability Analysis of Existing Slope
Figure 12
Stability Analysis with Proposed Buttress
11
11
Appendices
Appendix A: Field Exploration
Figure A-1. Legend of Terms and Symbols Used on Exploration Logs
Figures A-2 - A-13 Logs of Test Borings BH-1 through BH-3 and Hand
Borings HH-1 through HH-9
Appendix B: Laboratory Testing
Figure B-1 Particle Size Distribution Test Results
Figure B-2 Liquid Limit, Plastic Limit, and Plasticity Index of Soils
(Atterberg Limits)
11
REVISEDGEOTECHNICAL REPORT
WALKWAY IMPROVEMENTS
76TH AVENUE WEST AND 75TH PLACE WEST
EDMONDS, WASHINGTON
1. INTRODUCTION
This report presents geotechnical recommendations for design and construction of the proposed
walkway improvements to 76th Avenue West and 75th Place West in Edmonds, Washington. The
purpose of this work was to assess geotechnical conditions along the project alignment and
provide recommendations for design and construction of the proposed improvements.
1.1 Site and Project Description
The project is located in the Meadowdale area of Edmonds, which is located along the shoreline
of Puget Sound north of the city. The area is indicated on the Vicinity Map, Figure 1.
The project will include construction of a walkway along 76th Avenue West and 75th Place West
extending from Meadowdale Beach Road north to North Meadowdale Road, with some
additional improvements north to the King County Park. The project will include development
of a park at the north-west corner of 75th Place West and 162° Street SW.
Three conceptual designs for the proposed improvements were developed during preliminary
studies. We understand Concept 1 was selected for final design and construction. Under the
selected concept, the new sidewalk will be located along the east (upslope) side of the roadway
from Meadowdale Beach Road north to 162" d Street SW. Cuts into the hillside will be required
for the new sidewalk in much of this area. The cuts will be typically 3 to 4 feet in height but will
be up to 12 feet high in some areas.
From 162nd Street SW north to North Meadowdale Road the new walkway will be located on the
' western side of the road. Since placing fill along the top of the slope could reduce the stability of
the slope and is to be avoided, the new sidewalk will be supported on small diameter pipe piles
where there is insufficient existing flat area. North of North Meadowdale Road two pull-outs
will be constructed on the east side of the road for vehicle parking, and one 130-foot-long section
of pile -supported walkway is planned on the west side of the road.
Development of the proposed park will include regrading the site and construction of a driveway,
walkways, lawn and play areas. We understand an interpretive overlook is planned adjacent to
75th Place West. A plan of the proposed park is presented on Figure 6.
May 30 2008
HWA Project No. 2006-171-21
2. EXPLORATIONS AND GEOLOGIC CONDITIONS
2.1 Subsurface Explorations
' Subsurface. information for the project was obtained by advancing three hollow stem auger
borings designated BH-1 through BH-3; nine hand borings designated HH-1 through HH-9; and
three DCP soundings performed in concert with hand borings HH-7 HH-8 and HH-9. Boring
BH-1 was conducted by Davies Drilling Inc. using a track mounted CME-75 drill rig with a 3.25
inch OD hollow stem auger. Borings BH-2 and BH-3 were drilled by Environmental Drilling
using a truck mounted B-61 drill rig with an 8 inch OD hollow stem auger.
' BoringBH-1 is located in the northeast section of the proposed new ark. Borings BH-2 and
p p p g
BH-3 are located along the pr7osed sidewalk alignment where a new solider pile wall will be
installed on the east side of 76 Avenue West and 75t' Place West. Hand holes HH-1 through
HH-6 are located along the east side of 76th Avenue West and 75u' Place West along the
alignment of the proposed sidewalk. Hand holes H 1-7 through HH-9 along with their associated
DCP soundings are located along the west side of 75t' Place west between 162" a Street West and
North Meadowdale beach road. Borings were advanced either at the edge the City right of way,
or in the middle of the right travel lane, as shown in Figures 2-4.
A 2-inch diameter ground water monitoring well was installed in BH-2 with screen from a depth
of 15 to 25 feet and a silica sand filter from a depth of 12 to 30 feet. A slope inclinometer casing
was installed in BH-1 after the completion of the boring. The casing was installed to a depth of
35 feet below the ground surface and was incased in cement grout. A baseline reading for future
measurements was taken on October 24ffi 2007. Readings were subsequently taken February 22,
2008. Plots of the readings from BH-1 are presented on Figure 10.
Borings were located using a site map provided by Gray & Osborne inc. by measuring from
existing structures shown on the base map provided. A legend of the terms and symbols used on
the boring logs is presented in Figure A-1. Summary boring logs are presented in Figures A-2
through A-13 .
Standard Penetration tests were performed at 2.5-foot or 5-foot intervals in all three borings. The
Standard Penetration test consists of driving a 2-inch O.D. split -spoon sampler a distance of 18
inches into the bottom of the borehole with a 140-pound hammer falling 30 inches. The number
of blows required driving the sampler each of three 6-inch increments was recorded, and number
of blows required to cause the last 12 inches of penetration was termed the Standard Penetration
Resistance (N-value). This value is an indicator of the relative density or consistency of the
soils. Whenever 50 or more blows were required to cause 6 inches of penetration, driving was
stopped and the number of blows and corresponding penetration were recorded. Samples
recovered from the split spoon sampler were disturbed but were representative of the soils
encountered.
1 200617121 Revised Geotechnical Report.doc 2 HWA GeoSciences Inc.
May 30 2008
HWA Project No. 2006-171-21
An HWA geologist monitored the drilling and logged the borings. Soil samples were obtained
from the borings at intervals of 2.5 to 5.0 feet, classified in the field, and representative portions
were placed in plastic bags. These soil samples were taken to our Lynnwood, Washington,
laboratory for further examination and testing. Pertinent information including soil sample
depths, stratigraphy, soil engineering characteristics, and ground water occurrence were recorded
on the exploration logs. The stratigraphic contacts shown on the individual boring logs represent
the approximate boundaries between soil types; actual transitions may be more gradual. The soil
' and ground water conditions depicted are only for the specific date and locations reported and,
therefore, are not necessarily representative of other locations and times.
2.2 General Geologic Conditions
Geologic information for the project site was obtained from the published geologic map for the
area; Booth, D. B., Cox, B. F., Troost, K. G., and Shimel, S. A., 2004, Composite geologic map
of the Sno-King area: University of Washington, Seattle Area Geologic Mapping Project, scale
1:24,000. This map indicates that the surficial geology of the area consists of Pre -Fraser
terrestrial deposits, overlain by Vashon-stade advance outwash, a unit of mostly clean sand with
some gravel, overlain by Vashon-stade glacial till a non -stratified and non -sorted mixture of
clay, silt, sand, and gravel. The terrestrial deposits reside mainly in the northern portion of the
sidewalk alignment while the till and advance deposits are seen in the southern portion of the
alignment. The area is also overlain by landslide colluvium deposited by the ancient
Meadowdale slide. The landslide deposits occur throughout most of the site and are surficial
above the glacial and pre -glacial terrestrial deposits.
2.3 Landslide History
The majority of the project alignment lies within the North Edmonds Earth Subsidence and
Landslide Hazard Area, which is described in detail in a report titled "Landslide Hazards
Investigation, Meadowdale Area, Edmonds, Washington" prepared by Roger Lowe Associates in
1979.
According to the Roger Lowe Associates report, this area of Meadowdale experienced large-
scale ground movement between two and three thousand years ago. This slide was
approximately 3,200 feet long and up to 650 feet wide. The head scarp is easily distinguishable
above 751h Place West. The cause of this large-scale earth movement is inferred to be
progressive shoreline erosion by wave action; the waves eroded the toe of the slope, which over -
steepened it and evenwally led to land sliding. Construction of the Great Northern Railroad,
which is currently owned by Burlington Northern Santa Fe, along the beach, has halted the
shoreline erosion process since ii armors the toe of the slope from wave erosion.
tNo large-scale earth movements have been recorded for this area in modern times. However,
subsequent to the ancient slide, the mass of soil within the body of the slide has experienced
numerous small-scale adjustments. This type of post -slide adjustment is common and typically
occurs in the form of shallow earth slumps.
1 200617121 Revised Geotechnical Report.doc 3 HWA GeoSciences Inc.
May 30 2008
HWA Project No. 2006-171-21
More recently, sliding occurred in the area in January 1997, after heavy snowfall was followed
immediately by several inches of rain. Sliding occurred at several locations on the eastern side
of 75 h Place West and debris from one slide flowed across the street and came to rest on the
western side the road. Landslides occurred throughout the Puget Sound Region at that time and
are described in more detail in the paper by Gerstel et al. titled "Puget Sound Bluffs: The Where,
Why, and When of Landslides Following the Holiday 1996/97 Storms" (in Washington Geology,
vol. 25, no. 1, March 1997).
The study by Roger Lowe Associates also indicates that the stability of the Meadowdale area is
highly sensitive to groundwater levels. Improvements to local site drainage, including the
installation of sewers and storm drains, have had a positive impact on the stability of the area.
For several years sliding has been occurring at the northeast corner of the proposed 162na Street
park property. This sliding has been very slow, but is visible in cracks and subsidence in the
pavement of 75t' Place West. HWA has been monitoring this slide for several years for the
property owner to the north of the park. HWA installed an inclinometer casing in the shoulder of
75t' Place West several years ago. Measurements in this casing indicate a shear plane at depths
of 16 to 20 feet. The toe of the slide appears to be at the base of the steep portion of the slope.
2.4 Subsurface Conditions
Based on the results of our exploration program, the soils underlying the project area were
observed to consist of Pre -Fraser terrestrial deposits overlain by colluvial deposits and small
localized quantities of fill. This observation is consistent with the soils unit mapped in the area
by Booth ET. Al., by Roger Lowe Associates, and as encountered during previous drilling
undertaken by HWA to evaluate the subsurface conditions for other projects in this area in the
' past. (HWA, 2003).
Following are descriptions of the soil deposits encountered in our explorations in the order of
stratigraphic (depth) sequence by which they were deposited or placed, with the youngest unit
described first. Detailed descriptions of the soils are presented in the exploration logs in
Appendix A. A legend of the terms and symbols used on the boring logs is presented in Figure
A-1. Summary boring logs are presented in Figures A-2 through A-13.
Fill — Fill, consisting of loose to medium dense silty sand to sandy silt was identified in the
locations of BH-1, BH-3, HH-1 and HH-7 through HH-9, and ranged from 1.25 to 7 feet thick.
The fill was usually identified adjacent to the road, most likely from the grading of the roadway
during the initial construction.
Topsoil — Topsoil consisting of light brown to dark brow, silty sand with gravel was identified in
HH-1 through HH-5. In all of the hand holes the topsoil consisted of loose to medium dense
surficial material with abundant roots and rootlets being present. Depths ranged from 0.5 to 2.0
feet in depth.
' 200617121 Revised Geotechnical Report.doc 4 HWA GeoSciences Inc.
I
L
May 30, 2008
HWA Project No. 2006-17I-21
Colluvium — Colluvium was encountered in all of the borings and in hand holes HH-2, HH-6
and HH-9. It generally consisted of very soft to medium stiff clays and silts with interspersed
pieces of colluvial clays and silts, with seams of sand. The majority of the colluvium has
experienced some oxidation mottling, and the seams of sand tended to be wetter than the
surrounding fine grained material.
Colluvial Blocks — Colluvial blocks were encountered in Borings 1314-2 and BH-3 under the
softer colluvial material that overlies it. In the case of these explorations colluvial blocks refers
to disturbed native soils that are denser then the overlying material, but still exhibit some
variability in density and an irregularity in the soil that does not correspond with native
undisturbed glacial and pre -glacial terrestrial deposits. For example in BH-3 loose poorly graded
sand was encountered from 18 to 26 feet between very stiff clay and a hard laminated silt. It is
not known when or how these materials were mobilized in the past, but they do exhibit some
signs of disturbance.
Recessional Outwash — Loose to medium dense glacial outwash consisting of light brown silty
sand with gravel to gravelly sand with silt was identified in HH-3 through HH-5. The
recessional outwash was encountered on the uphill (east) side of the sidewalk alignment in the
area where a slope cut will occur for the new sidewalk. At the locations of TP-1 and TP-16, thin
layers of silty sand were encountered from 0.5 to 1.0 foot thick, which appeared to consist of
recessional outwash. These soils were loose to medium dense and directly overlie the glacial till.
2.5 Ground Water Conditions
Ground water seepage was encountered in borings BH-1, BH-2 and HH-2. We expect, however,
that actual ground water depths will vary depending on the season, variation in local subsurface
conditions, and other factors.
The project alignment is near the toe of the hillside, which is a ground water discharge area.
Consequently, springs and seeps occur at numerous locations along the alignment where
groundwater emerges from the ground.
2.6 Laboratory Testing
Representative soil samples obtained from the subsurface explorations were returned to the
HWA laboratory for further examination and testing. Laboratory tests, as described below, were
conducted on selected soil samples to characterize relevant engineering properties of the on -site
soils.
Moisture Content of Soil: The natural moisture.content of all soil samples (percent by dry
mass) was determined in general accordance with ASTM D 2216. The results are shown at the
sampled intervals on the test pit logs in Appendix A.
200617121 Revised Geotechnical Report.doc 5 HWA GeoSciences Inc.
May 30 2008
' HWA Project No. 2006-171-21
Particle Size Analysis of Soils: Selected samples were tested to determine the particle size
distribution of material in general accordance with ASTM D 422. The results are summarized on
Figure B-1, Appendix B, which also provides information regarding the classification of the
samples and the moisture content at the time of testing.
Liquid Limit, Plastic Limit, and Plasticity Index of Soils (Atterberg Limits): Selected
samples were tested using method ASTM D 4318, multi -point method. The results are reported
on the attached Liquid Limit, Plastic Limit, and Plasticity Index reports, Figure B-2.
3. RECOMMENDATIONS
' 3.1 GENERAL
L Construction of a walkway along 76th Avenue West and 75th Place West will require excavation
into the toe of the slope on the up -slope (eastern) side of the roadway in some areas, and
placement of fill or a pile supported partially -elevated walkway on the downslope side of the
road. Because placement of fill on the downslope side of the road would add to the weight of a
potential landslide, reducing the stability of the slope, we recommend that filling be avoided to
the extent possible. As a result, we recommend that walkways and walkway approach structures
on the downslope side of the road be pile -supported wherever there is insufficient existing flat
terrain.
Development of the propose park will include regrading the site and construction of a driveway,
walkways, lawn and play areas. We understand an interpretive overlook is planned adjacent to
75th Place West. Because of the relatively high ground water level and the presence of an
existing landslide on the property, we recommend the installation of a trench subdrain across the
park. HWA has evaluated measurements taken in an inclinometer casing installed on the park
property and performed stability analyses to evaluate the effectiveness of placing a buttressing
fill along the toe of the slope. The results of these studies indicate that the existing slide
daylights at the toe of the road embankment, and that placement of fill along this toe will
increase the stability of the slope. Results of the stability analyses and more detailed
recommendations for park design are presented in Section 3.5.
3.2 EARTH RETAINING STRUCTURES
Cuts along much of the eastern side of the roadway alignment will be 3 to 4 feet tall. In our
' opinion, the most cost-effective way of retaining these shallow cuts would be with modular
block walls such as Keystone blocks, or with rockeries. Block walls up to about 4 feet high
(twice the depth of the block) may be made by stacking blocks without need for geogrid
reinforcing. Block walls higher than twice the block depth should include geogrid reinforcing
which extends back from the face of the wall a horizontal distance equal to at least 0.7 times the
free-standing wall height. Geogrid reinforcing should be placed between every second layer of
blocks. We recommend the use of Tensar BX1200 geogrid, or equivalent, wherever geogrid
reinforcing is needed.
,� 200617121 Revised Geotechnical Report.d6c 6 HWA GeoSciences Inc.
May 30 2008
HWA Project No. 2006-171-21
Because of the horizontal space required for block walls, it may be desirable to use soldier pile
and lagging walls where the retained height of the cut exceeds about 4 feet. Soldier pile and
lagging walls would consist of 4-inch or larger H piles set in concrete in pre -drilled holes.
Lagging consisting of treated timber or precast concrete panels would be placed between the
soldier piles. The size of the H-pile section would depend on the height of the wall and the
horizontal spacing of the piles. Soldier piles should be designed to resist an equivalent fluid
I pressure equal to 55 pounds per cubic foot (pcf) plus one pcf for each degree of upward
inclination of the backslope. Passive resistance approximated by a 300 pcf equivalent fluid.
pressure may be used against the buried portion of structures to resist lateral forces. We .
recommend the soldier pile walls be tall enough that the backslope inclination does not exceed
2H to 1 V. Fill could be placed behind the soldier pile walls as necessary to flatten the slope.
Soldier piles which are set into concrete in predrilled holes should penetrate below finished grade
at least 1.5 times the wall's free-standing height. We do not recommend driving soldier piles
because: 1) driving and maintaining pile alignment may be difficult in dense gravelly soils, 2)
tvibrations from pile driving can cause landslides, and 3) a concrete -filled hole provides better
lateral resistance than a driven pile. Piles which are driven in place would need to extend to a
depth equal to twice their free-standing height.
Backfill behind the lagging should consist of 1'/4-inch minus crushed rock. Soldier pile and
lagging walls constructed as recommended above are typically permeable and will allow the
passage of moderate amounts of seepage. Where significant volumes of water are expected, such
as at existing springs, a slotted drain pipe and crushed rock backfill should be placed to intercept
the flow and convey it through the wall to the storm drain system.
3.3 PILE SUPPORTED WALKWAYS
Where pile support of walkways and approach structures is required, we recommend the use of
2-inch diameter extra -strong steel pipe. When driven to less than 1 inch of penetration in 1
' minute of driving with a 90 psi jackhammer, each pile should be capable of supporting 2 tons of
vertical load (allowable capacity) with an adequate factor of safety. Pile installation can actually
be accomplished with a backhoe-mounted compactor (hoepac), but testing to verify capacity
should be done with a jackhammer. Piles will develop their bearing in native soils below any
fill, and pile lengths will vary considerably. Pile lengths could average 20 to 25 feet.
3.4 PAVEMENTS
Where new street pavement is required, the pavement subgrade should be proof -rolled to verify
1 that it is dense and unyielding. Any soft or spongy material should be replaced with 1'/4-inch-
minus crushed rock. The pavement section should consist of at least 6 inches of crushed rock
(CSBC) and 3 inches of asphalt.
' 200617121 Revised Geotechnical Report.doc 7 HWA GeoSciences Inc.
May 30 2008
HWA Project No. 2006-171-21
3.5 PARK DESIGN
A plan showing the park ropertywith existing ground surface contours and the location
on of
boring BH-1 is presented on Figure 5. A cross section through the park property showing BH-1,
the previous boring HWA-3, and the assumed failure plane of the existing landslide is shown in
Figure 7. The proposed layout of park facilities is shown on
Figure 6.
I3.5.1 Stability
' As indicated on Figure 5, the park property slopes downward from 75th Place West about 2H to
1 V for approximately 20 vertical feet. The site then slopes gradually to 75th Avenue West. Our
previous studies indicate that a landslide exists on the north end of the park property and the
adjacent property to the north. The slide is still moving as evidenced by renewed cracking in the
pavement of 75t Place West. Readings from an inclinometer casing installed in the street right-
of-way in front of the adjacent property to the north, shown in figure 9A and 9B indicate that the
slide is about 18 feet deep at the western side of 75th Place West. As part of the current study,
HWA installed an inclinometer casing in BH-1 so that any earth movements at that location can
be detected. The results of measurements in this casing indicate that the existing slide terminates
at the toe of the slope on the east side of the park and does not involve most of the park site.
1 Because the existing landslide is confined to the north end of the slope on the eastern side of the
park, the proposed park development can proceed without stabilizing the slide, providing the
City is willing to accept that portions of the park, as well as the roadway and the utilities within
its right-of-way, will continue to be affected by the sliding.
Current plans for park development include placing fill along the toe of the slope below the
roadway, which will tend to increase the stability of the slide. In order to evaluate the stabilizing
influence of such fill, HWA performed a series of computer -model stability analyses. An
analysis was first performed to estimate the strength of existing soils on the hillside by assuming
' a factor of safety of 1.0 for the existing slope. The results of this analysis are shown on Figure
11. Soil strength parameters developed from this model were then used to determine the changes
in factor of safety for various buttress fill configurations. The results of one such analysis is
shown on Figure 12. These analyses indicated that the planned 5-foot high buttressing fill along
the toe of the slope will increase the stability of the slope by about 17 percent. These analyses
also indicated that:
' The buttressing fill should extend to the top of the slope (as shown on Figure 12) to
prevent failure planes with lower factors of safety from day -lighting higher up on the
slope above the buttress.
■ Buttress fills thicker than 5 feet will produce correspondingly higher factors of safety.
200617121 Revised Geotechnical Report.doc 8 HWA GeoSciences Inc.
J
May 30, 2008
HWA Project No. 2006-171-21
■ Because the proposed fill extends only part way across the toe of the slide, the actual
increase in factor of safety from a 5-foot fill will be less than 17 percent. To maximize
the increase in stability, we suggest placing as much fill as the park configuration will
allow, including placement of fill on the adjacent property to the north.
We understand that for the purpose of park space utilization, it is desirable to retain the
buttressing fill with a retaining structure. To further increase the stability of the slope we
recommend that this retaining structure be founded on drilled piers which extend vertically
downward (approximately 10 feet) to extend through the soft clay into the underlying medium
stiff clay. These piles, consisting of 24-inch diameter concrete cylinders on 6- to 8-foot centers
will provide additional shearing resistance across potential slide planes in the soft clay. The
result will be a significant increase in the stability of the slope.
A reinforced concrete footing can be cast along the tops of the piers and the retaining structure
can be constructed of Keystone -type blocks. We recommend that geogrid reinforcement be
included in the buttress fill in accordance with Section 3.2.
3.5.2 Park Drainage
We believe the installation of a trench subdrain across the park property is necessary to remove
excessive moisture for park development and enhance the stability of the lower portion of the
park. We recommend the construction of a trench subdrain across the park. The subdrain would
consist of a 4 to 5-foot-deep trench extending roughly north -south along the toe of the eastern
slope and then turning westward near the north property line to daylight at the western edge of
the park. Finger drains extending up -slope from the trench drain, spaced about 25 feet apart will
further increase drainage. The approximate location of the proposed trench drain is shown on
Figure 6. A 6-inch diameter slotted plastic pipe would be placed in the bottom of the trench and
the trench would be backfilled with 1'/4-inch-minus crushed rock. The trench subdrain would
intercept and remove ground water seepage from the site.
3.5.3 Foundation Design
Structures in the park may be supported on spread footings providing they can tolerate some
settlement. The soils are capable of supporting structures at allowable bearing pressures up to
1,500 psf; however, some settlement is likely due to the loose, soft and variable nature of the
soils. Structures that can not tolerate 2 inches of total and 1 inch of differential settlement should
be supported on small diameter pipe piles as described in Section 3.3.
Column footings should have a minimum width of 24 inches and wall footings should have a
minimum width of 18 inches. Footings should bear at least 18 inches below the lowest adjacent
finished grade.
200617121 Revised Geotechnical Report.doc 9 HWA GeoSciences Inc.
' May 30 2008
HWA Project No. 2006-171-21
�J
3.5.4 Park Pavement
' Any pavements within the park that will carry vehicular traffic should be constructed as
accordance with the recommendations in Section 3.4. We recommend that pavements for
1 walkways and trails consist of 6 inches of 1'/4-inch minus crushed rock overlain by 1'/Z inches of
asphalt.
' 4.0 CONDITIONS AND LIMITATIONS
We have prepared this report for Gray & Osborne and the City of Edmonds for use on this
' project. This data and report should be provided to prospective contractors for their bidding or
estimating purposes, but the conclusions and interpretations presented should not be construed as
a warranty of the subsurface conditions. Experience has shown soil and ground water conditions
' can vary significantly over small distances. Inconsistent conditions can occur between
explorations and may not be detected by a geotechnical study. If, during future site operations,
subsurface conditions are encountered which vary appreciably from those described herein,
HWA should be notified for review of the recommendations of this report, and revision of such
if necessary.
We recommend that HWA GeoSciences be retained to provide monitoring of construction
sufficient to verify that the construction of retaining walls and the driving of foundation piles is
accomplished in accordance with our recommendations and with the approved plans and
specifications.
The scope of work did not include environmental assessments or evaluations regarding the
presence or absence of hazardous substances in the soil, surface water, or ground water at this
site.
HWA does not practice or consult in the field of safety engineering. We do not direct the
' contractor's operations, and we cannot be responsible for the safety of personnel other than our
own on the site; the safety of others is the responsibility of the contractor. The contractor should
' notify the owner if he considers any of the recommended actions presented herein unsafe.
1 200617121 Revised Geotechnical Report.doc 10 HWA GeoSciences Inc.
May 30, 2008
HWA Project No. 2006-171-21
We appreciate the opportunity to be of service.
Sincerely,
HWA GEOSCIENCES INC.
Ralph N. Boirum, P.E.
Geotechnical Engineer, Principal
Principal
200617121 Revised Geotechnical Report.doc 11
HWA GeoSciences Inc.
May 30 2008
HWA Project No. 2006-171-21
References
Roger Lowe Associates Inc., 1979, Final Report, Landslide Hazards Investigation, Meadowdale
Area, Edmonds, Washington, for the City of Edmonds, consultant report dated October 16,
1979.
Gerstel et al. "Puget Sound Bluffs: The Where, Why, and When of Landslides Following the
Holiday 1996/97 Storms" (in Washington Geology, vol. 25, no. 1, March 1997).
HWA Geosciences Inc., 2002-099-21, Geotechnical Report, Nguyen Property Slope
Stabalization 16018 75`h Place West Edmonds, Washington, consultant report dated
November 8, 2002.
Booth, D. B., Cox, B. F., Troost, K. G., and Shimel, S. A., 2004, Composite geologic map of the
Sno-King area: University of Washington, Seattle -Area Geologic Mapping Project, scale
1:24,000
200617121 Revised Geoteclmical Report.doc 12 HWA GeoSciences Inc.
N
N
o
o 0
O >
N rc
n
WWW O
�
it
�
� 8 V
N
£ 3NnDI-J 3NI3HOlaW
O
�
a
O
Q q Z
ui
a
tip
Ln 0.
c
a
E
2.2
13
1RACT 93
MEADDWDALE BEACH
0-
E
TRACT
COMMON A
9
PARCEL 8
PARCEL A
Sp S 47-76
0
p
E
O
-----�
LU
^ W
TRACT 95
m>• MEADCWDALE BE
lfl
--T-}
N W
O
77,
cn
Y
�
o
13
/T, 1fiA3ECOR
TRACT
RE
5a9W'WE
W.76
s�
- EA og
RE �/�RD
q Cy LE
z
R� AQ
168TH PL.
wo
5ffi
Z
f z
O
b
bJ.
6
d
d
H
<
Z
N
Z
O O
M m
0 O_
x
w a
m
Z
Lp 01
Lp
M
m
t, 38nDi3 3NI-lH31VW b-
2 3NnDI3 3NIIH31VW
En
E
cn
E
U)
>1 �m
90
E
Ln 'D
LU
ko
N
o >
N � c �
� O
y Cl!
it
0
yVj Z
-- is t $ �' • Q O
LOT i %.,F-, z Q z
a
LU0a
SHORT PLAT v7 Q.
S-04-103
LOT 2
.. C
N
oil Nc
O
cn ,mY fl- c
N a tip$_ E
0 9 Y
> O
4-1
� W
h
„sue
i oc 1A�n C/.1
.YES:.
r
g�a
f
.4E
i
SURVEY AS
5 z
O
rn m HP
_ NORT. o
O wa O 8 8 ¢
0
E 3angI3 3NI3HOldW a z
E z
° a
z
� p w
¢ z p
0
o
z z
d yOy
J W
Q
z M
W a, 9
_� ��
T
o
Z T
0anZ U
W ' O
N
a
VJ
z0 z
LU
o LI L
d ti O U
w
�a0
�20
><
ELQ
O
d ~
z
H
v
W
1
1
1
1
U
U)
Z -�: Z
J J W
d IL 2LU
Q 0�
a Sao
w ��O
v) w}5
a QQ0
O =
r
a �<
N
P, � a
0
r N
(1333) NOIldn333 ) 212
o
� h � II� Vo- Co"l (o1J o
�
Vi o
N a
eN pNO
a
uj
N V N N V)
1N3W3AVd d0 T39(I3--,-` o0..e''y' l l l l l l l l w o N C:
1N3W3AVd 3❑ 30Q qq::,. .'•• ( ( 1 5q
(S ,S'/) Q3133 Md)
t=-dMH ° of
Q c
3Nd Id 3df13Id3 Q3Wf1SSH ''.;: 1 (I 1 I I I r Ln LLLI
W 2 N �
CS ,6I Q3133f O cl) .: 41
=i::
i-Hg
cd °
'•.:ti:an,; }:�;;' . I (I (III
w
,y N
o
0
0
S
0
In 3
g
s
v �
i
iN3W3hdd 30 MG
N �
w
3�
~zu
0 0 0 0 0 0 0
00 Ih �0 M N
° z o
(133d) NOIldn333 oy z o °
'no H
i
i
Zl H9 G o 0
w M
0Lli
�. g
.J
t I I[
DRILLING COMPANY: Gregory Drilling Inc. LOCATION: See Site & Exploration Plan, Figure 2
DRILLING METHOD: Hollow -stem Auger; CME 45 C track rig DATE STARTED: 9/13/2002
SAMPLING METHOD: SPTw/Autohammer DATE COMPLETED: 9/13/2002
SURFACE ELEVATION: 70 t feet LOGGED BY: B. Thurber
w m LU z N w Standard Penetration Test
v EL j � L Co
~Q (140 lb. weight, 30" drop)
J U uJ
0 w w w co 0 A Blows per foot
H m N d a w w _.
dw
o N DESCRIPTION << a 8 O X LU
0 10 20 30 40 50
0 0
�. SM Loose, brown, silty, fine to medium SAND, dry. Some coarse
sand, trace fine gravel and organics.
.:....:....
' [ROAD FILL] S-1 2-2-2
5— 5
ML Very loose, brown and gray with heavy rust -mottling, very
S-3 2-2-2 GS ........ ....:....:.... :
SM sandy SILT to very silty fine SAND, wet. Interbedded. Some .....
partly decomposed wood fragments. :....:....:....:....:....:....:....:....:....
i _ ......:................... 10
[EXISTING LANDSLIDE DEBRIS] S4 1-1-1 %F
Grades to gray, silty SAND and sandy SILT with organics, . • .
' wet.-------------------- , �.
ML S-5 1-1-2
Soft, blue -gray with brown streaks, clayey SILT with partly
decomposed wood fragments, moist. Mixed/swirled
15 SP appearance.-----------------� ...�.... �.. 15
Loosera sli htI si fine to medium SAND wet. S-sa 1-2-3
' CH :.
Medium stiff, gray, green gray, and brown -gray, CLAY, with S 6b
micaceous fine SAND laminae, with partly decomposed "" "' " : '
woody debris, moist. Sand laminae at high angles, and clay S-7 2-3-6 �
laminations in sample tip are planar and at 60-degree angle.
' (OLD SLIDE DEBRIS)
20 :.
@17.5 feet: Gray and dark gray, CLAY, moist. Laminae � S-8 3-6-8 AL ' ' 20
disturbed by fine angular offsets. Some dark gray
slickensides at approx. 30 degrees. , . , , ; , ...: • „ ; , , ,
CH eo 20 feet: Grades to stiff. No bedding apparent; fine blocky
:.. .:
texture. Long wood fibers caught in tip.
Very stiff, gray to dark gray, fat CLAY, moist Finely
25 laminated, bedding approximately horizontal.
S-9 4-6-9 AL ........._—�.........:. 25
....:....:....:....:....:....:.........:....:....
[WHIDBEY FORMATION]
' 30 �. ..:...:.: 30
:....:.
Includes occasional light gray laminae of coarse silt /very fine N S-10 6-8-11
sand.
.................................................
Borehole terminated at 31.5 feet.
Inclinometer casing (3-inch diameter) installed to 30 feet, and
... .:.. ...
backfilled with bentonite grout to 2 feet.
...................:....:....:....:....:..
35 Bentonite chips backfilled from l to 2 feet; 10-inch diameter • . • . • • • • . • • • . • 35
flush monument set in 1 foot of concrete to surface.
....:....:....:....:....:....:....:....:....
40 40
For a proper understanding of the nature of subsurface conditions, this 0 20 40 60 80 100
exploration log should be read in conjunction with the text of the Water Content (%)
geotechnical report. Plastic Limit 1-0-1 Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
MWA NGUYEN RESIDENCE BORING:
HWA-3
16108 75TH PLACE WEST
IMGEOSCIENCE$IP1C, EDMONDS, WASHINGTON PAGE: 1 of 1
PROJECT NO.: 2002-099-21 FIGURE: 8
BORING 2002099.GPJ 11/15/07
C:
c.i
d
O
N
O O O
r M
N O
d CL = w
LO
>+ ~ O N
tm m =
Z co
cc
L
a
a
E
c
C
c:
C
O m 111 O
Co 0 0 O
N O O N
O
m LO N 0
i
Cl to OLO
N N
(U) Hld3a
O
N
O
Fri
m
O
N
N
C5. C O
_. a
d
�a
O
CD z
0
I
0
0
O
m
ci
Z
U)
W �Z
w aw
2Q
x W
Z ti O Uj
J o2S d �
z i �o
M j Q Q
Q W
_ (0 J
Z
UP
Ma
O
CD
co
�
O
O
O
O
N
O
O
N
O
N
N
M
CO
\
N
CO
Hld34
d
z
d
U CO
z
O
w
w O
D
0 N
_
a
H
O O
� J
a U)
w z
w aw
o Z F-o�
z_ 0
M wr2
Q Q w
0
2 J
ZCl w
Nt m
O
C)
N
z
0
O F
O q
o �
W
0
0
N
O
O
O
V
Cl z
Co
V
z
w
O V
C9 cn
o 0
0
OPP
Q
(s843ul) uoijelAOP size-d
�U NONLq~
LO O O O O O O O
ti
O
O
U
o
=
o
y
LO
N
�
o
O
_m
c
> E
O
(L =
>
O
o
V
O
w
X
lf)
N
ao
O
O
u7
O
u7
ti
0
y
a�
m �
N >
E �
A o
cc cob ao
v,a)>'m
x L 0 5
o•
Q cc n o rn�
a c `m
(oa)E
a��_2
0.� Q U
* d.a c
0
0
O
N
N
N
0
0
to N
N N
O i
V
C
O =
O O
L O
N
O d
0
O
to
O to O to 0 to O uy O Oi
N N m (M V
(;aa;) y;dap
LO
0
0
O N
LO d
N t
O V
C
� O C
R O O
Q N O 'fy0
0
d
to
O O
O �
O In O O LO O LOO 9
N N (+1 Cl)
(;aa;) yldap
U)
F-
0
a
Z
O F-
aELW
i =wQ
W LD
ae C0
H ��O
W >Qo
O =Yw
z (oQ
J ti
Z
I m I
M
04
Ca
M
N
N
O N
LL
� N
O
C
0
o�
U inoZ
N O � 4i N
O U
O
L G 'C
F O) C Q =
oN C O
�
o
U M m
�i
f6�o QOZ
U bi bia
N
m,2
row'mocU - -
•cm��o�
n�aLL
s
� t>
u
v }�`rcfbt.r�r`r 1 t
N
�
m
e
F
p.
�
N
O.
O
�
N
0
E 8 @
O p�
m
O�NOO
aj�0 N
LLh O)CQ
O
w N O (n
N G
�U)UUt.t.�
�
E
o N
m o �
UUM �
m o O
o
=AGO nNZ
+'o vi
�'OOOO
ohoN u�o�n ono NorooNo�no
�(q�ULL �s
-I ti'i
T
a
.i N N NNmM ..........
e
O L
ObL O L O L OSr00,.._,—,
Ob
OZ
�
rn
_m
o
N �
UJ
O
t1
�
O
� N
O N
UM m
a
OO
oh
(n c I—OICQO
1G-. N o (n
t0 C
O C O
�lnUS�"
Uu.L@
s-
N
0
ii
c
i S W
Eil
A}
No
N
{ to-
��.'.3 f
,I
O N
\\ c
� N G
O p N O o
2O yMZ
y
O
IL
O o
2.
O •_ L U �.
QUA DULL �S'
o
m o
`c N c
0
2 o
S � O ON N Z
TLO CaC
O
O Q O
co
o
}
o
oo NN o ho .00 N O N60 i. . in oNO�n ooNoen
b �nr
w
N._.c O
2i 0 LL
O
W O O O O ... . N N N N M M t+f rl a c c c N .. N .O
otq O L O L 08
09
Ob
m
1
1
1
'1
'1
1
1
1
1
1
1
III
i
Appendix A
Soil Boring Logs
F
1
0
L�
F
L
[I
F
C
RELATIVE DENSITY OR CONSISTENCY VERSUS SPT N-VALUE
COHESIONLESS SOILS
COHESIVE SOILS
Approximate
Density
N (blows/ft)
Approximate
Consistency
N (blowslft)
Undrained Shear
Relative Density(%)
Strength (pst)
Very Loose
0 to 4
0 - 15
Very Soft
0 to 2
<250
Loose
4 to 10
15 - 35
Soft
2 to 4
250 - 500
Medium Dense
10 to 30
35 - 65
Medium Stiff
4 to 8
500 - 1000
Dense
30 to 50
65 - 85
Stiff
8 to 15
1000 - 2000
Very Dense
over50
85 - 100
Very Stiff
15 to 30
2000 - 4000
Hard
I over 30
>4000
USCS SOIL CLASSIFICATION SYSTEM
MAJOR DIVISIONS
GROUP DESCRIPTIONS
Coarse
Grained
Soils
Gravel and
Gravelly Soils
Clean Gravel
(little or no fines)
IV
IS
GW
Well -graded GRAVEL
o Q
GP
Poody-graded GRAVEL
More than
50% of Coarse
Gravel with
a
GM
Silty GRAVEL
Fraction Retained
Fines (appreciable
on No. 4 Sieve
amount of fines)
GC
Clayey GRAVEL
Sand and
Clean Sand
,•
SW
Well -graded SAND
More than
Sandy Soils
(little or no fines)
SP
Poody-graded SAND
50% Retained
on No.
200 Sieve
Size
50% or More
of Coarse
Fraction Passing
No. 4 Sieve
Sand with
Fines (appreciable
amount of fines)
SM
Silty SAND
SC
Clayey SAND
ML
SILT
Fine
Silt
ZPA
CL
Lean CLAY
Grained
Sails
and Liquid Limit
Less than 50 %
Clay
_
—
OL
Organic SILT/Organic CLAY
MH
Elastic SILT
50% or More
Passing
No. 200 Sieve
silt Liquid Limn
and
50 % or More
Clay
CH
Fat CLAY
Size
OH
Organic SILT/Organic CLAY
Highly Organic Soils
PT
PEAT
COMPONENT DEFINITIONS
COMPONENT
SIZE RANGE
Boulders
Larger than 12 in
Cobbles
3 in to 12 in
Gravel
3 in to No 4 (4.5mm)
Coarse gravel
3 in to 314 in
Fine gravel
3/4 in to No 4 (4.5mm)
Sand
No. 4 (4.5 mm) to No. 200 (0.074 mm)
Coarse sand
No. 4 (4.5 mm) to No. 10 (2.0 mm)
Medium sand
No. 10 (2.0 mm) to No. 40 (0,42 mm)
Fine sand
No. 40 (0.42 mm) to No. 200 (0.074 mm)
Silt and Clay
Smaller than No. 200 (0.074mm)
TEST SYMBOLS
%F
Percent Fines
AL
Atterberg Limits: PL = Plastic Limit
LL = Liquid Limit
CBR
California Bearing Ratio
CN
Consolidation
DD
Dry Density (pcf)
DS
Direct Shear
GS
Grain Size Distribution
K
Permeability
MD
Moisture/Density Relationship (Proctor)
MR
Resilient Modulus
PID
Photoionization Device Reading
PP
Pocket Penetrometer
Approx Compressive Strength (tsf)
SG
Specific Gravity
TC
Triaxial Compression
TV
Torvane
Approx. Shear Strength (tsf)
UC Unconfined Compression
SAMPLE TYPE SYMBOLS
®2.0" OD Split Spoon (SPT)
(140 lb. hammer with 30 in. drop)
IShelby Tube
3-1/4" OD Split Spoon with Brass Rings
OSmall Bag Sample
® Large Bag (Bulk) Sample
nCore Run
Nonstandard Penetration Test
(3.0" OD split spoon)
GROUNDWATER SYMBOLS
Z7 Groundwater Level (measured at
time of drilling)
T Groundwater Level (measured in well or
open hole after water level stabilized)
COMPONENT PROPORTIONS
PROPORTION RANGE
DESCRIPTIVE TERMS
< 5%
Clean
5- 12%
Slightly (Clayey, Silty, Sandy)
12 - 30%
Clayey, Silty, Sandy, Gravelly
30-50%
Very (Clayey, Silty, Sandy, Gravelly)
Components are arranged in order of increasing quantities.
NOTES: Soil classifications presented on exploration logs are based on visual and laboratory observation.
Soil descriptions are presented in the following general order:
Density/consistency, color, modifier (1f any) GROUP NAME, additions to group name (6any), moisture
content. Proportion, gradation, and angularity of constituents, additional comments.
(GEOLOGIC INTERPRETATION)
Please refer to the discussion in the report text as well as the exploration logs for a more
complete description of subsurface conditions.
MOISTURE CONTENT
DRY Absence of moisture, dusty,
dry to the touch.
MOIST Damp but no visible water.
WET Visible free water, usually
soil is below water table.
� 75th-76th Walkway Improvements LEGEND OF TERMS ANDSYMBOLS USED ON
Meadowdale
HMGEOSCIENCESINC Edmonds, WA EXPLORATION LOGS
PROJECT NO.: 2006-171-21 FIGURE: A-1
LEGEND 2006-171-21.GPJ 11/15/07
DRILLING COMPANY: Davies Drilling SURFACE ELEVATION: t feet DATE STARTED: 10/10/2007
DRILLING METHOD: Hollow stem Auger DATE COMPLETED: 10/10/2007
SAMPLING METHOD: Cat Head SPT LOGGED BY: P. Pearson
LOCATION: See Figure 2
y
W
w
U
g
U
w
¢ V)
U)
m
J
} 7)
F Z
rj L
c
W U
J
O
O
U
W W
J_j
rA
W rp
o
FF-
Q
2
EL
�.
U
a
Z 30
2
W S
o
U)
D
DESCRIPTION
(1) U)
a
O
a in
0
0
SM
Loose, Brown, slightly silty, fine to Medium SAND, moist with
®
S-1
1-1 4
roots and rootlets.
[FILL]
Soil becomes siltier then sandy again.
5
®
S-2
3-2-3
Loose, yellowish gray, sandy SILT, moist, trace organics.
CL
ML
`--------jVI COLLUUM-j-------
Soft, bluish gray, silty CLAY, moist. Older, black trace
organics.
10
Soft, bluish gray to brownish grey, ,silty CLAY, wet. Some
� S-3
2
1-1-2
dense chunks of clay also.
15V
Medium stiff to stiff, gray, silty CLAY, moist. Trace ® S-3 4 4 6
laminations observed.
2 inch sandy layer.
I 20 1 r — — — — — — — — — — — — — — — — — — — -CH Stiff to vry stiff, gray, CLAY, moist. S�es
[ RE -GLACIAL T RREST IIAL DEPOSITS]erved. 1 ®S-5 3-8-15
25
Hard, gray, CLAY with fine sand, slightly moist. ® S-6 10-21-35
30
Subvertical cracks with fine sands. Horizontal laminations ®S-7 9-18-32
observed.
35
Hard, massive, gray, fine sandy, CLAY, moist to wet. ® S-8 13-27-50/5
Boring terminated at 36.5 feet below surface.
Inclinometer casing was installed with grout from 2.5 feet
above ground surface to 35 feet below ground surface.
40 Ground water observed at 10 feet and 35 feet at time of
exploration.
1 45
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
Standard Penetration Test
(140 lb. weight, 30" drop)
♦ Blows per foot
2
a�
20 30 40 50 0 E
5
....:...............................II--10 I
:... ...:�.;....!....!....:....:....
: ..:.A .....................� �-20
25
.�. :»I-30 I
—45
0 20 40 60 80 100
Water Content (%)
Plastic Limit 1--0 Liquid Limit
Natural Water Content
BORING:
75th-76th Walkway Improvements BH-1
goo Meadowdale
FMGEOSC 14CH INC. Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE: A-2
PZO 2006-171-21.GPJ 11/16/07
DRILLING COMPANY: Environmental Drilling Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/25/2007
DRILLING METHOD: Hollow Stem Auger DATE COMPLETED: 10/25/2007
SAMPLING METHOD: SPT Auto Hammer LOGGED BY: V. Atkins
LOCATION: See Figure 2
w
mZ Standard Penetration Test
Ua 2 �_ F- w G (140 lb. weight, 30" drop)
J O w w e H w Q ♦ Blows per foot
LU mofg
a U EL CL Z p 2 S a
W d >- G Q Q W— H W G Wd
o N > DESCRIPTION co o7 a s O a Co 0 10 20 30 40 50 0 w
0 SP 1-2 inches of Asphalt over sand and gravel base course over 0
brown, poorly graded SAND with gravel fill.
MIL Stiff, brown silt with clay, moist.
[COLLUVIUM] S-1 2-4-5
----------------------
Loose brown fine SAND with silt, slight oxidized moist_—
CL Medium stiff, brown, SILT with sand, with trace dark orange
5 5
wet oxidized silty sand seams, moist. S-2 2-2-5
— — S-3 3-7-8 r
ML Stiff, gray, SILT to clayey silt with seams of fine sand and
clay, moist.
10 Sand seams are wet. S-4 4-4-8 • • . • :....: .�...:....:... • ; .... 10
"Wood fragments in sample------------- S-5 5-8-13
ML Stiff to very stiff, brown to olive brown organic SILT, moist.
ML Very stiff, gray to olive gray, sandy SILT, wet. S-6 3-8-11
[COLLUVIAL BLOCKS]
.... — — — — — — — — — — — — — — — — — — — — — —
SM Medium dense, gray, fine sandy SILT, wet.
20 .�.... ........ 20
CL Very stiff, gray, CLAY, moist.
High plasticity.
25 S-8 4-7-12 ,.:....;.... r ....:........ 25
30 :....:.... 30
S-9 6-9-15
Boring was terminated at 31.5 feet below ground surface.
Ground water seepage was encountered at 15 feet below
ground surface. A ground water monitoring well was installed
35 with screen from15-25 feet, and sand from 12 to 30 feet. :... ................:.... 35
40 40
0 20 40 60 80 100
Water Content (%)
Plastic Limit 1— 0 Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
BORING:
75th-76th Walkway Improvements BH-2
Meadowdale
HMGEOSCIENCES INC. Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171 -21 FIGURE: A-3
PZO 2006-171-21.GPJ 11/15/07
it
DRILLING COMPANY: Environmental Drilling Inc.
LOCATION: See Figure 2
DRILLING METHOD: Hollow Stem Auger
DATE STARTED: 10/25/2007
SAMPLING METHOD: SPTAuto Hammer
DATE COMPLETED: 10125/2007
SURFACE ELEVATION: t feet
LOGGED BY: D. Coltrane
w
z
W Standard Penetration Test
U
J
w
o-
t
F
Q (140 lb. weight, 30" drop)
w
I-
O Blows per foot
-' 0
W
w
w
_
CL Co COZ
o
2
O
a m
o- cn Z) DESCRIPTION
ai
in
a
O
o
0 10 20 30 40
50
0
7 inches of as halt at surface.
0
SM
Medium dense, olive brown to light brown, silty fine SAND
:....:....:....:....
with gravel, moist.
• •
:.:..
:..
[FILL]
S-1
4-9-9
5-
1 10 -
1 15-
1 25 -
1 30-
1 35 -
N
S-2
5-6-10
ML
— — — — — — — — — — — — — — — — — — — — — —
Medium dense to dense, olive brown, silty SAND to sandy
SM
SILT, with fine SAND seams, moist. Oxide mottling in seams
S-3
5-8-15
of fine SAND.
[COLLUVIUM]
S-4
11-15-16
CL
Gravellvdrilling,from 11 to 11.5feet BGS.-------
ML
Very stiff, gray to olive gray, silty CLAY with seams of gray
S-5
7-9-13
silty fine SAND, moist. SILT has organic smell.
[COLLUVIAL BLOCKS]
S-6
4-6-10
�. SP-----------------------
Loose, gray, poorly graded, fine to medium SAND with silt and
trace fine gravel, moist to wet.
S-7 2-3-7
Drilling became hard at 25-26 feet BGS. — S-8 6-12-23
ffFTML Hard, olive gray to olive brown, laminated SILT, moist. S-8a
SM Medium dense, gray, silty fine SAND, wet. S-9 7-12-12
Boring was terminated at 31.5 feet below ground surface.
Minor ground water seepage was encountered during the
exploration, but there was no standing ground water in the
hole after the auger was removed.
40—`
For a proper understanding of the nature of subsurface conditions, this
exploration log should be read in conjunction with the text of the
geotechnical report.
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
1— 10 1
I-15 1
1---20 1
0 20 40 60 80 100
Water Content (%)
Plastic Limit 1— -0 Liquid Limit
Natural Water Content
=i'Iii}:� 75th-76th Walkway Improvements BORING:
A I Meadowdale BH-3
HMGEOSCIENCH INC. Edmonds, WA PAGE: 1 of 1
PROJECTNO.: 2006-171-21 FIGURE: A-4
BORING 2006-171-21.GPJ 11/15/D7
SM
Medium dense, brown, sandy SILT with gravel, roots and
rootlets, moist.
[FILLIOLD TOPSOIL]
----------------------
Medium dense, brown silty SAND with gravel, roots and
SM
woodchips. Less moist than above.
--
- - - - - - - - - - - - - - - - - - - - - -
Loose, yellowish brown Silty SAND with gravel, organics and
-
SM
pieces of wood. No ground water.
HAND HOLE:
75th-76th Walkway Improvements HH-1
Meadowdale
HMIGEOSCIENCES INC Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE: A-5
HANDHOL 2006-171-21.r.PJ 11/15107
DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/8/2007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10/8/2007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
' LOCATION: See Figure 2
co N Lu m Z W
a._ U L In Q .-.
0 W W W'o FW- Z w
N =
a 2 v zo = 0 a
0 U) DESCRIPTION c4 v¢s a- a 0 (�0 0
0 0
SM Loose, dark brown, silty SAND with Gravel and organics.
Moist
-------- (TOPSOIL] ---------
SM Loose, light olive brown, silty SAND with rootlets and chunks
of grayish Gay below 1.5'.
1 [COLLUVIUM] : 1
S-1
0
2 2
ML Soft, olive brown, SILT with sand, chunks of gray clay, small S-2
woodchips and bits of charcoal. O
3 3
4 4
5.... :....:....:....:....:....:....:....:....:.... 5
6 6
Hand hole was terminated 5.5 feet below ground surface.
Ground water seepage was encountered at 5.0 feet below
ground level and stabilized at 4.7 feet below ground level after
exploration.
7 7
8 1 8
0 20 40 60 80 100
Water Content (%)
Plastic Limit Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
75th-76th Walkway Improvements HAND HOLE:
I, Meadowdale H H-2
HMGEOSCIENCES INC. Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE7 A-6
HANDHOL 2006-171-21.GPJ 11/15/07
I
DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/812007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10/8/2007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
LOCATION: See Figure 2
Lu
U EL F m ~ w _
J _ U] ULu
co ¢ N
J 0 W W W� F— O
m cn a � NCr
Z ii =
w D
' Lu o
o DESCRIPTION v¢i < a z O rf Lu
>-
0 0
SM Loose, light brown, silty SAND with gravel and roots, moist.
[TOPSOIL)
S-1
SM Loose, light yellowish brown, silty SAND with gravel and wood
chips. gravels are fine to medium. Soil is moist but less so
than above. O S-2
2 [RECESSIONAL OUTWASH] 2
' Hand hole was terminated at 2.25 feet below surface level.
3 No ground water seepage was encountered during 3
exploration.
4 4
' 6 6
7 7
r
8 1 8
' 0 20 40 60 80 100
Water Content (%)
Plastic Limit 1 0 Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
75th-76th Walkway Improvements HAND HOLE:
gon HH-3
Meadowdale
HMGEOSCIENGS INC. Edmonds, WA PAGE: 1 of 1
PROJECTNO.: 2006-171-21 FIGURE: A-7
HANDHOL 2006-171-21.GPJ 11/15/07
DRILLING COMPANY: HWAGeosciences Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/8/2007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10/8/2007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
LOCATION: See Figure 2
W
' U d m Fa- N ~ W
}} j /) r U Q
y J F Z C W w
J O W W W �p F- Z
N
EL m N d d 3 W 0 H
0
o v}i D DESCRIPTION v¢i vai a$ IS 5, 0
0 0 SM Medium dense, brown, silty SAND with gravel, roots and
rootlets, moist.
1 [TOPSOILIWEATHERED OUTWASH]
1 S-1 1
r
0
2 `. SM Loose, light yellowish brown silty, ravel SAND, moist. -2 2
9 Y tY gravely OS
[RECESSIONAL OUTWASH]
3 3
Hand hole was terminated at 2.5 feet below surface level. No
ground water seepage was encountered during exploration.
4 4
5:....:....:....:....:....:....:....:....:.... 5
6 6
7 7
8 8
0 20 40 60 80 100
Water Content (%)
Plastic Limit 1--0 Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
HAND HOLE:
75th-76th Walkway Improvements HH-4
Meadowdale
HWAGEOSCIENCH INC Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE: A-8
HANDHOL 2006-171-21.GPJ 11/15/07
1
1
1
1
1
1
1
1
1
1
1
1
1
SM
Loose, very dark brown, silty SAND with organic material,
moist.
[TOPSOIL]
Loose, light yellowish brown, gravely SAND with silt
SM
andcobbles. Moist
C.
[RECESSIONAL OUTWASH]
Loose, very light yellowish brown, silty, gravely SAND. Sand
SM
is fine, gravel is coarse. Soil becomes less gravely below 3.0
feet, moist.
HAND HOLE:
MWA 75th-76th Walkway Improvements HH-5
Meadowdale
I IGEOSCIENCH INC. Edmonds, WA PAGE: 1 of ,
' PROJECT NO.: 2006-171-21 FIGURE: A-9
HANDHOL 2005-171-21.GPJ 11/15/07
or DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/8/2007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10/812007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
LOCATION: See Figure 2
3
U
J O
LU co
v
U) D
0 --1 rrrrr-
2-
3-
4-
5-
6-
7-
8-
DESCRIPTION
Loose -medium dense, light olive gray, sandy SILT with
organics. Soil was clumpy with some debris, moist.
[COLLUVIUM]
ML Soft, light olive gray, silty CLAY. Chunks of silty sand, pieces
of wood, and roots, moist.
______________________
ML Loose, light gray to yellowish brown, silty CLAY, moist.
aT 1
Hand hole terminated at 5.5 feet below surface level. No
ground water seepage was encountered during exploration.
w
U
m
Z --
H
W
0.
Q
F Z
� C
LLJ
I—
w
Z
x
W
Z o
S
O
F
0
vai
a 8
0
(.9
o
0S2
0 S-3
0
NOTE: This log of subsurface conditions applies only at the specked location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
r0
1-1
F-5
I-6
�-7
L-8
20 40 60 80 100
Water Content (%)
Plastic Limit 1 -0 Liquid Limit
Natural Water Content
HAND HOLE:
75th-76th Walkway Improvements HH-6
Meadowdale
HMGEOSCIENM INC. Edmonds, WA PAGE: 1 of
PROJECT NO.: 2006-171-21 FIGURE: A-1 0
HANDHOL 2005-171-21.GPJ 11/15/07
DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/19/2007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10/1912007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
LOCATION: See Figure 2
3 uJ a (a � w r J o- j F L Q Non -Standard Penetration Resistance
.�°'.. p Z F C o (17.6 lb. weight, 22.6" drop) w
w w WWco 3:3 w D F
g o o-
o y 7) DESCRIPTION vdi U) 0.W
0.. :aO 0 p
0
�. SM Loose, olive brown silty SAND with gravel, roots and rootlets 0
present, moist.
1 [FILL]
O S-1 1
2—
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ 2
Piece of old asphalt at 2.25 feet below ground surface.
_ _ S-2
SP Medium dense, gray gravelly fine to medium SAND with silt, ; 33
3 Oroots and rootlets, moist. 3
OLD TOPSOIL
Hand hole was terminated at 3.0 feet below ground surface.
4 No ground water seepage was encountered during the 4
exploration.
5 5 6—AL 6
7 7
8 6
1
9 9
A
10 :....:....:....:.........:... .. 10
;....;
O:
11 � 11
12 12
13 13
14 14
15 115
0 20 40 60 so 100
Water Content
Plastic Limit 1 --♦ Liquid Limit
Natural Water Content
1 NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
75th-76th Walkway Improvements HAND HOLE:
HH-7
Meadowdale
HMGEosaENCES INC. Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE: A-11
HANDHOL 2006-171-21.GPJ 11/15/07
DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/19/2007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10/19/2007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
LOCATION: See Figure 2
m Z W r U CL Fa- L Imo- Q Non -Standard Penetration Resistance
F = N
O Z C F o (17.6 lb. weight, 22.6" drop)
w w w� Z
try x
F- m co a of 3 w F
o
o ai � DESCRIPTION ran ran a � O � o
0 0
SM Loose, light brown, silty SAND with gravel, roots and rootlets,
moist.
[FILL]
1 1
OS1
SM Loose, brown, silty SAND with gravel, bumf wo�TitZroo�s,
3 and rootlets, moist. O S-2A 3
OLD TOPSOIL
4 Hand hole was terminated at 3.2 feet below ground surface. 4
No groundwater seepage was encountered during the
exploration.
I 5 :33 s
6
6
7 7
8-
9— —9
10 10
11 11
12 12
13 13
14 14
15 15
0 20 40 60 80 100
Water Content (%)
Plastic Limit Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
HAND HOLE:
75th-76th Walkway Improvements HH-8
Meadowdale
HMGEOSCIENCESINC: Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE: A-12
HANDHOL 2006-171-21.GPJ 11/15/07
SM
1.5 inches of Beauty Bark on surface.
Loose to medium dense, olive brown, silty SAND with gravel,
roots and rootlets, moist.
pieces of plastic and cemented soils present.
[COLLUVIUM/FILL]
MIL
Soft, to loose, layers of olive brown, sandy SILT with trace
SM
gravel, mottled olive brown fine silty SAND with rootlets, and
grayish brown sandy SILT with trace gravel, roots, rootlets,
and pieces of burnt wood present, moist.
[COLLUVIUM]
75th-76th Walkway Improvements HAND HOLE:
HH-9
Meadowdale
HWAGEOR IENCES INC. Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE: A-1 3
HANDHOL 2006-171-21.GPJ 11/15/07
� Appendix B
� Geotechnical Laboratory
Testing
L
1
-----------
2
Emmons
MEN
----------
----------
monsoons
EMMEMMEM..
ff
-
FAMOMMOMMOM
ce
M
�
ui
o
��
0
o
co
o
0
0
c�
a
J
d
J
J
U
O
m
CD
O
0
co
■
U
J
J_
U
0
� �
0
O
N
CJ
G
�
J
0
'ITch
o
0 0
N
0
CO LO
0 o0
N
N
C_
LL
co
o
d
d
N
N
N
J
Lf7
I,-
N
co
r
c
N
co
CO
z
O
U
N
i
Q Z(f) m
~off j
��ti LL
VOo
V!Ui� N
gzQ
F-: F-o 0
J. N
0 Cn 2 z
gU
W
J acu
1
11
it
jTA HWA GEOSCIENCES INC.
Geotechnical & Pavement Engineering • Hydrogeology • Geoenvironmental • Inspection & Testing
November 16, 2007
HWA Project No. 2006-171-21
Gray & Osborne, Inc.
701 Dexter Avenue North, Suite 200
Seattle, Washington 98109
Attn: Ms. Tani Stafford, P.E.
Project Manager
r JED
APR 20�8
BUILDING D��pg
CITY OF
GEOTECHNICAL REPORT
76TH AVENUE WEST AND 75TH PLACE WEST WALKWAY IMPROVEMENTS
EDMONDS, WASHINGTON
Dear Tani:
As requested, HWA GeoSciences Inc. completed geotechnical engineering studies for the
proposed walkway and park improvements along 76th Avenue West and 75th Place West
in Edmonds, Washington. The results of our investigations and geotechnical
recommendations for the proposed facilities are presented in this report.
We appreciate the opportunity to provide geotechnical services on this project.
Sincerely,
HWA GEOSCIENCES INC.
7Ralph oirum, P.E.
Geotechnical Engineer
Principal
Enclosure: Geotechnical Report
19730 - 64th Avenue W.
Suite 200
Lynnwood, WA 98036.5957
Tel: 425.774.0106
Fax: 425.774.2714
www.hwageosciences.com
r
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
:NO
E IV
007ENEERING ~ VISION
RE FFPVE
APR 2 2 2008
BUILDING
CIDEPARTMENT
TY OF EDMONDS
GEOTECHNICAL REPORT
761h Avenue West & 75th Place West
Walkway Improvements
Edmonds, Washington
HWA Project No. 2006-171-21
Prepared for
Gray & Osborne, Inc.
November 16, 2007
Y 1'L'f�-
HWAGEOSCIENCES INC.
• Geotechnical Engineering
• Hydrogeology
• Geoenvironinental Services
• Inspection & Testing
'
TABLE OF CONTENTS
Page
1. INTRODUCTION...........................................................................................................1
1.1 SITE AND PROJECT DESCRIPTION.................................................................1
2. EXPLORATIONS AND GEOLOGIC CONDITIONS............................................................2
'
2.1 SUBSURFACE EXPLORATIONS.......................................................................3
2.2 GENERAL GEOLOGIC CONDITIONS..............................................................3
2.3 LANDSLIDE HISTORY....................................................................................3
2.4 SUBSURFACE CONDITIONS............................................................................4
2.5 GROUNDWATER CONDITIONS.....................................................................5
2.6 LABORATORY TESTING................................................................................5
3. RECOMMENDATIONS..................................................................................................6
3.1 GENERAL.......................................................................................................6
3.2 EARTH RETAINING STRUCTURES.................................................................6
'
3.3 PILE SUPPORTED WALKWAYS.....................................................................7
3.4 PAVEMENTS...................................................................................................7
3.5 PARK DESIGN................................................................................................8
3.5.1 Stability ................................................ :......................................... 8
3.5.2 Park Drainage..............................................................................8
3.5.3 Foundation Design.......................................................................9
3.5.4 Park Pavement.............................................................................9
'
4.0 CONDITIONS AND LIMITATIONS................................................................................9
LIST OF FIGURES (FOLLOWING TEXT)
Figure 1 Vicinity Map
Figures 2-4 Site and Exploration Plan
Figure 5 Park Property Exploration Plan
'
Figure 6 Proposed Park Plan
Figure 7 Cross Section A -A'
Figure 8 Log of Previous Test Boring HWA-1
Figure 9A & 913 Boring HWA-3 Inclinometer Plot
Appendices
Appendix A: Field Exploration
Figure A-1. Legend of Terms and Symbols Used on Exploration Logs
Figures A-2 - A-13 Logs of Test Borings BH-1 through BH-3 and Hand
Borings HH-1 through HH-9
'
Appendix B: Laboratory Testing
Figure B-1 Particle Size Distribution Test Results
Figure B-2 Liquid Limit, Plastic Limit, and Plasticity Index of Soils
(Atterberg Limits)
1
1
LI
11
GEOTECHNICAL REPORT
WALKWAY IMPROVEMENTS
76TH AVENUE WEST AND 75TH PLACE WEST
EDMONDS, WASHINGTON
1. INTRODUCTION
This report presents geotechnical recommendations for design and construction of the
proposed walkway improvements to 76d' Avenue West and 75`" Place West in Edmonds,
Washington. The purpose of this work was to assess geotechnical conditions along the
project alignment and provide recommendations for design and construction of the
proposed improvements.
1.1 Site and Project Description
The project is located in the Meadowdale area of Edmonds, which is located along the
shoreline of Puget Sound north of the city. The area is indicated on the Vicinity Map,
Figure 1.
The project will include construction of a walkway along 70 Avenue West and 751h
Place West extending from Meadowdale Beach Road north to North Meadowdale Road,
with some additional improvements north to the King County Park. The project will
include development of a park at the north-west comer of 75 h Place West and 162nd
Street SW.
Three conceptual designs for the proposed improvements were developed during
I preliminary studies. We understand Concept 1 was selected for fmal design and
construction. Under the selected concept, the new sidewalk will be located along the east
(upslope) side of the roadway from Meadowdale Beach Road north to 162nd Street SW.
Cuts into the hillside will be required for the new sidewalk in much of this area. The cuts
will be typically 3 to 4 feet in height but will be up to 12 feet high in some areas.
From 162nd Street SW north to North Meadowdale Road the new walkway will be
located on the western side of the road. Since placing fill along the top of the slope could
reduce the stability of the slope and is to be avoided, the new sidewalk will be supported
' on small diameter pipe piles where there is insufficient existing flat area. North of North
Meadowdale Road two pull-outs will be constructed on the east side of the road for
vehicle parking, and one 130-foot-long section of pile -supported walkway is planned on
the west side of the road.
Development of the proposed park will include regrading the site and construction of a
driveway, walkways, lawn and play areas. We understand an interpretive overlook is
planned adjacent to 75d' Place West. A plan of the proposed park is presented on
Figure 6.
1
I�
I
F
1
November16, 2007
HWA Project No. 2006-171-21
2. EXPLORATIONS AND GEOLOGIC CONDITIONS
2.1 Subsurface Explorations
Subsurface information for the project was obtained by advancing three hollow stem
auger borings designated BH-1 through BH-3; nine hand borings designated HH-1
through HH-9; and three DCP soundings performed in concert with hand borings HH-7
HH-8 and HH-9. Boring 1311-1 was conducted by Davies Drilling Inc. using a track
mounted CME-75 drill rig with a 3.25 inch OD hollow stem auger. Borings BH-2 and
BH-3 were drilled by Environmental Drilling using a truck mounted B-61 drill rig with
an 8 inch OD hollow stem auger.
Boring BH-1 is located in the northeast section of the proposed new park. Borings BH-2
and BH-3 are located along the proposed sidewalk alignment where a new solider pile
wall will be installed on the east side of 76"' Avenue West and 75d' Place West. Hand
holes HH-1 through HH-6 are located along the east side of 76th Avenue West and 75 h
Place West along the alignment of the proposed sidewalk. Hand holes HH-7 through
HH-9 along with their associated DCP soundings are located along the west side of 75t'
Place west between 162nd Street West and North Meadowdale beach road. Borings were
advanced either at the edge the City`right of way, or in the middle of the right travel lane,
as shown in Figures 2-4.
A 2-inch diameter ground water monitoring well was installed in BH-2 with screen from
a depth of 15 to 25 feet and a silica sand filter from a depth of 12 to 30 feet. A slope
inclinometer casing was installed in BH-1 after the completion of the boring. The casing
was installed to a depth of 35 feet below the ground surface and was incased in cement
grout. A baseline reading for future measurements was taken on October 24a' 2007.
Borings were located using a site map provided by Gray & Osborne inc. by measuring
' from existing structures shown on the base map provided. A legend of the terms and
symbols used on the boring logs is presented in Figure A-1. Summary boring logs are
presented in Figures A-2 through A-13.
Standard Penetration tests were performed at 2.5-foot or 5-foot intervals in all three
borings. The Standard Penetration test consists of driving a 2-inch O.D. split -spoon
sampler a distance of 18 inches into the bottom of the borehole with a 140-pound
hammer falling 30 inches. The number of blows required to drive the sampler each of
three 6-inch increments was recorded, and number of blows required to cause the last 12
inches of penetration was termed the Standard Penetration Desistance (N-value). This
value is an indicator of the relative density or consistency of the soils. Whenever 50 or
more blows were required to cause 6 inches of penetration, driving was stopped and the
number of blows and corresponding penetration were recorded. Samples recovered from
the split spoon sampler were disturbed but were representative of the soils encountered.
' Final Geotechnical Report 2 HWA GeoSciences Inc.
�I
I
I
Novemberl6, 2007
HWA Project No. 2006-171-21
An HWA geologist monitored the drilling and logged the borings. Soil samples were
obtained from the borings at intervals of 2.5 to 5.0 feet, classified in the field, and
representative portions were placed in plastic bags. These soil samples were taken to our
Lynnwood, Washington, laboratory for further examination and testing. Pertinent
information including soil sample depths, stratigraphy, soil engineering characteristics,
and ground water occurrence were recorded on the exploration logs. The stratigraphic
contacts shown on the individual boring logs represent the approximate boundaries
between soil types; actual transitions may be more gradual. The soil and ground water
conditions depicted are only for the specific date and locations reported and, therefore,
are not necessarily representative of other locations and times.
2.2 General Geologic Conditions
Geologic information for the project site was obtained from the published geologic map
for the area; Booth, D. B., Cox, B. F., Troost, K. G., and Shimel, S. A., 2004, Composite
geologic map of the Sno-King area: University of Washington, Seattle Area Geologic
Mapping Project, scale 1:24,000. This map indicates that the surficial geology of the
area consists of Pre -Fraser terrestrial deposits, overlain by Vashon-stade advance
outwash, a unit of mostly clean sand with some gravel, overlain by Vashon-stade glacial
till a non -stratified and non -sorted mixture of clay, silt, sand, and gravel. The terrestrial
deposits reside mainly in the northern portion of the sidewalk alignment while the till and
advance deposits are seen in the southern portion of the alignment. The area is also
overlain by landslide colluvium deposited by the ancient Meadowdale slide. The
landslide deposits occur throughout most of the site and are surficial above the glacial
and pre -glacial terrestrial deposits.
2.3 Landslide History
The majority of the project alignment lies within the North Edmonds Earth Subsidence
and Landslide Hazard Area, which is described in detail in a report titled "Landslide
Hazards Investigation, Meadowdale Area, Edmonds, Washington" prepared by Roger
Lowe Associates in 1979.
According to the Roger Lowe Associates report, this area of Meadowdale experienced
large-scale ground movement between two and three thousand years ago. This slide was
approximately 3,200 feet long and up to 650 feet wide. The head scarp is easily
distinguishable above 751h Place West. The cause of this large-scale earth movement is
inferred to be progressive shoreline erosion by wave action; the waves eroded the toe of
the slope, which over -steepened it and eventually led to land sliding. Construction of the
Great Northern Railroad, which is currently owned by Burlington Northern Santa Fe,
along the beach, has halted the shoreline erosion process since it armors the toe of the
slope from wave erosion.
11
Final Geotechnical Report 3 HWA GeoSciences Inc.
Novemberl6 2007
HWA Project No. 2006-171-21
1
No large-scale earth movements have been recorded for this area in modern times.
However, subsequent to the ancient slide, the mass of soil within the body of the slide has
experienced numerous small-scale adjustments. This type of post -slide adjustment is
common and typically occurs in the form of shallow earth slumps.
More recently, sliding occurred in the area in January 1997, after heavy snowfall was
followed immediately by several inches of rain. Sliding occurred at several locations on
the eastern side of 75`t' Place West and debris from one slide flowed across the street and
came to rest on the western side the road. Landslides occurred throughout the Puget
'
Sound Region at that time and are described in more detail in the paper by Gerstel et al.
titled "Puget Sound Bluffs: The Where, Why, and When of Landslides Following the
'
Holiday 1996/97 Storms" (in Washington Geology, vol. 25, no. 1, March 1997).
The study YRogerb Ro Lowe Associates also indicates that the stabilityof the Meadowdale
area is highly sensitive to groundwater levels. Improvements to local site drainage,
including the installation of sewers and storm drains, have had a positive impact on the
stability of the area.
2.4 Subsurface Conditions
Based on the results of our exploration program, the soils underlying the project area
were observed to consist of Pre -Fraser terrestrial deposits overlain by colluvial depoits
and small localized quantities of fill. This observation is consistent with the soils unit
'
mapped in the area by Booth ET. Al., by Roger Lowe Associates, and as encountered
during previous drilling undertaken by HWA to evaluate the subsurface conditions for
other projects in this area in the past. (HWA, 2003).
Following are descriptions of the soil deposits encountered in our explorations in the
order of stratigraphic (depth) sequence by which they were deposited or placed, with the
youngest unit described first. Detailed descriptions of the soils are presented in the
exploration logs in Appendix A. A legend of the terms and symbols used on the boring
logs is presented in Figure A-1. Summary boring logs are presented in Figures A-2
'
through A-13.
Fill — Fill, consisting of loose to medium dense silty sand to sandy silt was identified in
the locations of BH-1, BH-3, HH-1 and HH-7 through HH-9, and ranged from 1.25 to 7
'
feet thick. The fill was usually identified adjacent to the road, most likely from the
grading of the roadway during the initial construction.
1
Topsoil — Topsoil consisting of light brown to dark brow, silty sand with gravel was
identified in HH-1 through HH-5. In all of the hand holes the topsoil consisted of loose
to medium dense surficial material with abundant roots and rootlets being present.
'
Depths ranged from 0.5 to 2.0 feet in depth.
' Final Geotechnical Report 4 HWA GeoSciences Inc.
t
Novemberl6, 2007
HWA Project No. 2006-171-21
Colluvium — Colluvium was encountered in all of the borings and in hand holes HH-2,
HH-6 and HH-9. It generally consisted of very soft to medium stiff clays and silts with
interspersed pieces of colluvial clays and silts, with seams of sand. The majority of the
colluvium has experienced some oxidation mottling, and the seams of sand tended to be
wetter than the surrounding fine grained material.
' Colluvial Blocks — Colluvial blocks were encountered in Borings BH-2 and 13H-3 under
the softer colluvial material that overlies it. In the case of these explorations colluvial
blocks refers to disturbed native soils that are denser then the overlying material, but still
' exhibit some variability in density and an irregularity in the soil that does not correspond
with native undisturbed glacial and pre -glacial terrestrial deposits. For example in BH-3
loose poorly graded sand was encountered from 18 to 26 feet between very stiff clay and
' a hard laminated silt. It is not known when or how these materials were mobilized in the
past, but they do exhibit some signs of disturbance.
Recessional Outwash — Loose to medium dense glacial outwash consisting of light
brown silty sand with gravel to gravelly sand with silt was identified in HH-3 through
HH-5. The recessional outwash was encountered on the uphill (east) side of the sidewalk
alignment in the area where a slope cut will occur for the new sidewalk. At the locations
' of TP-1 and TP-16, thin layers of silty sand were encountered from 0.5 to 1.0 foot thick,
which appeared to consist of recessional outwash. These soils were loose to medium
' dense and directly overlie the glacial till.
2.5 Ground Water Conditions
' Ground water seepage was encountered in borings BH-1 and 13H-2 and HH-2. We
expect, however, that actual ground water depths will vary depending on the season,
' variation in local subsurface conditions, and other factors.
The project alignment is near the toe of the hillside, which is a ground water discharge
area. Consequently, springs and seeps occur at numerous locations along the alignment
where groundwater emerges from the ground.
' 2.6 Laboratory Testing
Representative soil samples obtained from the subsurface explorations were returned to
the HWA laboratory for further examination and testing. Laboratory tests, as described
below, were conducted on selected soil samples to characterize relevant engineering
properties of the on -site soils.
' Moisture Content of Soil: The natural moisture content of all soil samples (percent by
dry mass) was determined in general accordance with ASTM D 2216. The results are
shown at the sampled intervals on the test pit logs in Appendix A.
I I
,' Final Geotechnical Report 5 HWA GeoSciences Inc.
' Novemberl6, 2007
HWA Project No. 2006-171-21
' Particle Size Analysis of Soils: Selected samples were tested to determine the particle
size distribution of material in general accordance with ASTM D 422. The results are
summarized on Figure B-1, Appendix B, which also provides information regarding the
classification of the samples and the moisture content at the time of testing.
Liquid Limit, Plastic Limit, and Plasticity Index of Soils (Atterberg Limits): Selected
samples were tested using method ASTM D 4318, multi -point method. The results are
reported on the attached Liquid Limit, Plastic Limit, and Plasticity Index reports, Figure
B-2.
3. RECOMMENDATIONS
' 3.1 GENERAL
Construction of a walkway along 76t' Avenue West and 75t' Place West will require
' excavation into the toe of the slope on the up -slope (eastern) side of the roadway in some
areas, and placement of fill or a pile supported partially -elevated walkway on the
downslope side of the road. Because placement of fill on the downslope side of the road
would add to the weight of a potential landslide, reducing the stability of the slope, we
recommend that filling be avoided to the extent possible. As a result, we recommend that
walkways and walkway approach structures on the downslope side of the road be pile -
supported wherever there is insufficient existing flat terrain.
Development of the propose park will include regrading the site and construction of a
driveway, walkways, lawn and play areas. We understand an interpretive overlook is
planned adjacent to 75a' Place West. Because of the relatively high ground water level
' and the presence of an existing landslide on the property, we recommend the installation
of a deep trench subdrain across the park. More detailed recommendations for park
design are presented in Section 3.5.
3.2 EARTH RETAINING STRUCTURES
Cuts along much of the eastern side of the alignment will be 3 to 4 feet tall. In our
opinion, the most cost-effective way of retaining these shallow cuts would be with
modular block walls such as Keystone blocks, or with rockeries. Block walls up to about
4 feet high (twice the depth of the block) may be made by stacking blocks without need
for geogrid reinforcing. Block walls higher than twice the block depth should include
geogrid reinforcing which extends back from the, face of the wall a horizontal distance
' equal to at least 0.7 times the free-standing wall height. Geogrid reinforcing should be
placed between every second layer of blocks. We recommend the use of Tensar BX1200
geogrid, or equivalent, wherever geogrid reinforcing is needed.
1 Final Geotechnical Report 6 HWA GeoSciences Inc.
' Novemberl6, 2007
HWA Project No. 2006-171-21
' Because of the horizontal space required for block walls, it may be desirable to use
soldier pile and lagging walls where the retained height of the cut exceeds about 4 feet.
Soldier pile and lagging walls would consist of 4-inch or larger H piles set in concrete in
pre -drilled holes. Lagging consisting of treated timber or precast concrete panels would
be placed between the soldier piles. The size of the H-pile section would depend on the
height of the wall and the horizontal spacing of the piles. Soldier piles should be
designed to resist an equivalent fluid pressure equal to 55 pounds per cubic foot (pcf)
■ plus one pcf for each degree of upward inclination of the backslope. We recommend the
soldier pile walls be tall enough that the backslope inclination does not exceed 2H to 1 V.
Fill could be placed behind the soldier pile walls as necessary to flatten the slope.
Soldier piles which are set into concrete in predrilled holes should penetrate below
finished grade at least 1.5 times the wall's free-standing height. We do not recommend
driving soldier piles because: 1) driving and maintaining pile alignment may be difficult
in dense gravelly soils, 2) vibrations from pile driving can cause landslides, and 3) a
concrete -filled hole provides better lateral resistance than a driven pile. Piles which are
driven in place would need to extend to a depth equal to twice their free-standing height.
' Backfill behind the lagging should consist of 11/4-inch minus crushed rock. Soldier pile
and lagging walls constructed as recommended above are typically permeable and will
' allow the passage of moderate amounts of seepage. Where significant volumes of water
are expected, such as at existing springs, a slotted drain pipe and crushed rock backfill
should be placed to intercept the flow and convey it through the wall to the storm drain
system.
3.3 PILE SUPPORTED WALKWAYS
Where pile support of walkways and approach structures is required, we recommend the
use of 2-inch diameter extra -strong steel pipe. When driven to less than 1 inch of
' penetration in 1 minute of driving with a 90 psi jackhammer, each pile should be capable
of supporting 2 tons of vertical load (allowable capacity) with an adequate factor of
safety. Pile installation can actually be accomplished with a backhoe-mounted compactor
' (hoepac), but testing to verify capacity should be done with a jackhammer. Piles will
develop their bearing in native soils below any fill, and pile lengths will vary
considerably. Pile lengths could average 20 to 25 feet.
' 3.4 PAVEMENTS
Where new street pavement is required, the pavement subgrade should be proof -rolled to
verify that it is dense and unyielding. Any soft or spongy material should be replaced
with 11/4-inch-minus crushed rock. The pavement section should consist of at least 6
' inches of crushed rock (CSBC) and 3 inches of asphalt.
1
Final Geotechnical Report 7 HWA GeoSciences Inc.
Novemberl6, 2007
HWA Project No. 2006-171-21
3.5 PARK DESIGN
A plan showing the park property with existing ground surface contours and the location
' of boring BH-1 is presented on Figure 5. A cross section through the park property
showing BH-1, the previous boring HWA-3, and the assumed failure plane of the existing
landslide is shown in Figure 7. The proposed layout of park facilities is shown on
Figure 6.
3.5.1 Stability
As indicated on Figure 5, the park property slopes downward from 75 h Place West about
2H to 1 V for approximately 20 vertical feet. The site then slopes gradually to 75th
Avenue West. Our previous studies indicate that a landslide exists on the north end of
the park property and the adjacent property to the north. The slide is still moving as
evidenced by renewed cracking in the pavement of 75a' Place West. Readings from an
'
inclinometer casing installed in the street right-of-way in front of the adjacent property to
the north, shown in figure 9A and 9B indicate that the slide is about 18 feet deep at the
western side of 75fl' Place West. As part of the current study, HWA installed an
inclinometer casing in BH-1 so that any earth movements at that location can be detected.
Based on our previous studies and the existing site geometry, it appears likely that the
existing slide terminates at the toe of the slope on the east side of the park and does not
involve most of the park site. The results of future measurements in the two inclinometer
casings will confirm or deny that assumption.
Assuming that the existing landslide is confined to the north end of the slope on the
eastern side of the park, the proposed park development can proceed without stabilizing
the slide, providing the City is willing to accept that portions of the park as well as the
roadway and the utilities within its right-of-way will continue to be affected by the
sliding.
Current plans for park development include placing fill along the toe of the slope below
the roadway, which will tend to increase the stability of the slide but may not be
sufficient to prevent future movement. A definitive stabilization design will require
additional measurements in the two slope indicator casings over the course of the coming
winter to determine the location of the slide plane and performing stability analyses to
develop stabilization measures. That additional analysis is not within the present scope
of work; however, we recommend that this additional analysis be performed and the
results incorporated into the park design.
3.5.2 Park Drainage
We believe the installation of a trench subdrain across the park property is necessary to
remove excessive moisture for park development and maintain stability of the lower
portion of the park; however, it may or may not be effective in stabilizing the existing
landslide.
Final Geotechnical Report 8 HWA GeoSciences Inc.
' Novemberl6, 2007
HWA Project No. 2006-171-21
1
' We recommend the construction of a trench subdrain across the park. The subdrain
would consist of an 8 to 10-foot-deep trench extending roughly north -south along the toe
of the eastern slope and then turning westward near the north property line to daylight at
' the western edge of the park. The approximate location of the proposed trench drain is
shown on Figure 6. A 6-inch diameter slotted plastic pipe would be placed in the bottom
of the trench and the trench would be backfilled with 1'/4-inch-minus crushed rock. The
trench subdrain would intercept and remove ground water seepage from the site and
would serve as a shear key to reduce the potential for future sliding.
' 3.5.3 Foundation Design
Structures in the park may be supported on spread footings providing they can tolerate
' some settlement. The soils are capable of supporting structures at allowable bearing
pressures up to 1,500 psf; however, some settlement is likely due to the loose, soft and
' variable nature of the soils. Structures that can not tolerate 2 inches of total and 1 inch of
differential settlement should be supported on small diameter pipe piles as described in
Section 3.3.
Column footings should have a minimum width of 24 inches and wall footings should
have a minimum width of 18 inches. Footings should bear at least 18 inches below the
lowest adjacent finished grade.
' 3.5.4 Park Pavement
Any pavements within the park that will carry vehicular traffic should be constructed as
accordance with the recommendations in Section 3.4. We recommend that pavements for
walkways and trails consist of 6 inches of 1'/4-inch minus crushed rock overlain by 1'/2
inches of asphalt.
4.0 CONDITIONS AND LIMITATIONS
We have prepared this report for Gray & Osborne and the City of Edmonds for use on
this project. This data and report should be provided to prospective contractors for their
bidding or estimating purposes, but the conclusions and interpretations presented should
not be construed as a warranty of the subsurface conditions. Experience has shown soil
' and ground water conditions can vary significantly over small distances. Inconsistent
conditions can occur between explorations and may not be detected by a geotechnical
study. If, during future site operations, subsurface conditions are encountered which vary
appreciably from those described herein, HWA should be notified for review of the
recommendations of this report, and revision of such if necessary.
IFinal Geotechnical Report 9 HWA GeoSciences Inc.
Novemberl6 2007
HWA Project No. 2006-171-21
' We recommend that HWA GeoSciences be retained to provide monitoring of .
construction sufficient to verify that the construction of retaining walls and the driving of
foundation piles is accomplished in accordance with our recommendations and with the
approved plans and specifications.
The scope of work did not include environmental assessments or evaluations regarding
the presence or absence of hazardous substances in the soil, surface water, or ground
water at this site.
HWA does not practice or consult in the field of safety engineering. We do not direct the
' contractor's operations, and we cannot be responsible for the safety of personnel other
than our own on the site; the safety of others is the responsibility of the contractor. The
contractor should notify the owner if he considers any of the recommended actions
presented herein unsafe.
We appreciate the opportunity to be of service.
Sincerely,
HWA GEOSCIENCES INC.
Ralph N. Boirum, P.E.
Geotechnical Engineer
Principal
' Final Geotechnical Report 10
HWA GeoSciences Inc.
Novemberl6, 2007
HWA Project No. 2006-171-21
References
Roger Lowe Associates Inc., 1979, Final Report, Landslide Hazards Investigation,
Meadowdale Area, Edmonds, Washington, for the City of Edmonds, consultant report
dated October 16, 1979.
Gerstel et al. "Puget Sound Bluffs: The Where, Why, and When of Landslides Following
the Holiday 1996/97 Storms" (in Washington Geology, vol. 25, no. 1, March 1997).
HWA Geosciences Inc., 2002-099-21, Geotechnical Report, Nguyen Property Slope
Stabalization 16018 75th Place West Edmonds, Washington, consultant report dated
November 8, 2002.
Booth, D. B., Cox, B. F., Troost, K. G., and Shimel, S. A., 2004, Composite geologic
map of the Sno-King area. University of Washington, Seattle Area Geologic Mapping
Project, scale 1:24,000
Final Geotechnical Report
11
HWA GeoSciences Inc.
L
1�
k
1
N
g � o a
N �
d r
� O
B N
it
0
W
E 3NnOI3 3NI-IHOIVW
5
00
`j ¢ Q Z
_ - c
0
E
0 0
TRACT 93 - CL c1
MEADOWDALE BEACH c:
TRACT 13
r COMMON A
PARCEL B
PARCEL A
r
5P S 49-76 O
i E
Ln O �w
r c
�j
TRACT 95 -Wam
-{-� MEADOWDAIE BEACH
Li
O d
nuo
''''
7(�}
0 - ,..-;
tA ne ,
1r
F o
T
ECOR
TRACT 13 R 1 J4,
gygtl3'�8'E �"�
.�a EA�
?�( RD
l o
REACy �ALE
,
�Q e� CAD
s, z
168TH PL. 0 55
o
z
52 2 o
baF a a z
U
z O w
z o
0 x
z
� � m
w
J 0 0
ox
0
z ?
W O, Q
J S m =
a
a
=:-
N
� � w
b 321f1JI3 3NI-lHO1dW o M o
- ---'( di N
ct 1/ 6 }
1/2 OF 8 a o
1/2 OF 8 0 N
=- t m 9 G4 SURV 5�
I z
LU O
g T s D 16 2�
SW Ln
JCL cn
m
i V
fu�a
c
cp LOT 4 O
a-r
U a U
Ln
r, h W
O m LOT 5
m
4 LO Q
LOT 3
' �4 1
26 54
LOT 2
13-57
L�
LOT
S ST ERN ENGVNEERS '05
LOW NFS _
10-
5. 64TN S� S
20� (no open -
not � -',��
SEC NpNSEN
„m
SET CAP 94D 5
REBAR #
mEYER P
Z
G_-4 '94
43 247
a
oz d °
a
N
a < o
rC z0 Z w
o °
z
Z 3dngI3 3NIIH31VW N m
N �
0 O
z w
a
S m S m
z
M
W O �{. Q j
i.{,�.
_ m Y S a
m m = m m m m m m
N W 0 8
o >
N
t`
� O
N
II'
0
z
LOT 1LU
%fi'S9
SHORT PLAT v�
S-04-IOB
LOT 2
c
au
? E c
a�
020
cm
N E N
r �
u LU
'v
h
885
sag
a
SURVEY AS
5 z
O
I
°o NORTN P z
o �
Q U a
a
E 3Nnoi3 3NI3H01dW Z
a a
o
a
O N
zd z o
z w
O o O
z
QW
� en
o O_
O w
m O d
_ _
M
Z o
WLU
a
WT UZI 'z
mi [��
Uj
(1) z z
() IOU,) LU IL
OW0
uj
5
uj
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
0
(1)
�I
U
O
O
z
d
z
o
z
U (6
O C)
0 N
a
U)
Z �Z
Q �w
a
a
Y F-, >
Q ti0�
IL .6w
LU HMO
cn w >- 5;
IL Q¢w
0 =
a ti<
U33d) NOIldA333
00 U)
H
Q �
o
..
o
N O
O
cu
C U
Lij
W
N N N
Z
1N3W3AVd AO 30¢3_i'
I
O o o
'W
I I
'
>
R ;
I I I
CD
O
O
O O
1N3W3AVd JO 30¢ Y I I I W
CS ,9'L9 (3103! Md) Rr - sr
;��:: .f• i.
are
TtL c
I I I I
3
o X c
3Nd'kl 3an-IId3 ¢3WOSSH P •' �I I I I
CJ
i-Hfi:'` lug lu� I I
3
•Jf.•.m:Ll,
a
°I T
I- N
O
00
a
1N3W3Add .40 39aa---! "'
zr
O o 0 0 0 0 0 0 0
07 h w in V- M N
U33d) NOIldh3-13
z s
o=
w
o
FF
-
_
o
N
affiww
�N
°
o
Ow
a o
a = m
o
�w
a o
g� z
«z
w k
z
y
I
I
Z
w
I M
I
0
a.
Ii
�
J
' DRILLING COMPANY: Gregory Drilling Inc. LOCATION: See Site & Exploration Plan, Figure 2
DRILLING METHOD: Hollow -stem Auger; CME 45 C track rig DATE STARTED: 9/13/2002
SAMPLING METHOD: SPT w/ Autohammer DATE COMPLETED: 9/13/2002
' SURFACE ELEVATION: 70 t feet LOGGED BY: B. Thurber
Lu
mz w Standard Penetration Test
' U }a j t y Q (140 lb. weight, 30" drop)
p w W w Z Blows per foot
SPEL EL U) of x
iL 1 2 v 2 2 z o x O CL
0 w rrn D DESCRIPTION vai v¢i a s O Cro7 p
0 10 20 30 40 50
0 SM Loose, brown, silty, fine to medium SAND, dry. Some coarse p
:....:....
sand, trace fine gravel and organics.
' [ROAD FILL] S-1 2-2-2
5......................:............ 5
S-2 2-2-4 .. '
ML Very loose, brown and gray with heavy rust -mottling, very
SM sandy SILT to very silty fine SAND, wet. Interbedded. Some S-3 2-2-2 GS .
' partly decomposed wood fragments. ................ ................ ... .
10 � � SZ ......... .... ........................ 10
[EXISTING LANDSLIDE DEBRIS] S-4 1-1-1 %F
Grades to gray, silty SAND and sandy SILT with organics, .• • •
' wet.S-5 1-1-2 -------------------- -...,
ML Soft, blue -gray with brown streaks, Gayey SILT with partly
....:...:...:....:...:. ..:...:...:...:.. .
decomposed wood fragments, moist. Mixed /swirled
15 SP appearance.-----------------...�... ........................ 15
Loose ra sli hti sil fine to medium SAND wet. S-6a 1-2-3
CH S 6b:....:..............:....:....:....:....
' Medium stiff, gray, green -gray, and brown -gray, CLAY, with
micaceous fine SAND laminae, with partly decomposed
woody debris, moist. Sand laminae at high angles, and clay S-7 2-3-6 ...• •
laminations in sample tip are planar and at 60-degree angle. : . . ..:....:. . . . : . . . . : • , , • ; • • • • ; , • • • ; , , , , ; , , ,
' 20 (OLD SLIDE DEBRIS) .
:....:.
@17.5 feet: Gray and dark gray, CLAY, moist. Laminae S-8 3-6-8 AL 20
disturbed by fine angular offsets. Some dark gray • • • • . . . . . . . . • . • •
slickensides at approx. 30 degrees. ; • ...: • • , • ; , , ,
CH @ 20 feet: Grades to stiff. No bedding apparent; fine blocky
' texture. Lnq wood fibers caught in tip.
Very stiff, gray to dark gray, fat CLAY, moist Finely
25 laminated, bedding approximately horizontal.
25
S-9 4-6-9 ALA .:....:....:....:....
' [WHIDBEY FORMATION]
' 30 .:.�. ....:....:. 30
:.. .:.
Includes occasional light gray laminae of coarse silt /very fine � S-10 6-8-11
sand. :.. .:...:....:....:....... .:.. .:..
Borehole terminated at 31.5 feet
' Inclinometer casing (3-inch diameter) installed to 30 feet, and
backfilled with bentonite grout to 2 feet.
35 Bentonite chips backfilled from 1 to 2 feet; 10-inch diameter 35
flush monument set in 1 foot of concrete to surface.
40 40
' For a proper understanding of the nature of subsurface conditions, this 0 20 40 60 80 100
exploration log should be read in conjunction with the text of the Water Content(%)
geotechnical report. Plastic Limit 1-0--I Liquid Limit
Natural Water Content
' NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
NGUYEN RESIDENCE BORING:
HWA-3
16108 75TH PLACE WEST
IMGEOSCIENCESINC. EDMONDS, WASHINGTON PAGE: 1 of 1
PROJECT NO.: 2002-099-21 FIGURE: 8
BORING 2002099.GPJ 11/15/07
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
O
0
N
o
ch
m �P
0 0
O O
N N
w v
O
0
N
�-
I
O U')
LO
N N
(4) Hld3a
O
O
O
N
0
O
O
o
a
O
w
a
0
d
O Z
N
a°
O =
aQ
O
�r 0 3
O O
0
d
r
o �
CD Z
0
I
0
0
o
M
O
J
a U)
w �z
w Q_w
2 = wQ
_Z r O uj
�a0
z �20
C' >Q�
Q Q�w
x
z r-<
ci
C
Hld3a
Cl
O
I-
O
N
0
Z
O
o
O Q
O >
W
0
O
N
O
O
O
I
o
z
cfl
U �
w O
z N
a
CO
�SZ
J W
D.W<
LOj�
0 � �
O
Q<°W
= Sc
lapp
C2
i Appendix A
Soil Boring Logs
In
C'�
RELATIVE DENSITY OR CONSISTENCY VERSUS SPT N-VALUE
COHESIONLESS SOILS
COHESIVE SOILS
Approximate
Approximate
Density
N (blows/ft)
Consistency
N (biows/ft)
Undrained Shear
Relative Density(%)
Strength (psf)
Very Loose
0 to 4
0 - 15
Very Soft
0 to 2
<250
Loose
4 to 10
15 - 35
Soft
2 to 4
250 - 500
Medium Dense
10 to 30
35 - 65
Medium Stiff
4 to 8
500 - 1000
Dense
30 to 50
65 - 85
Stiff
8 to 15
1000 - 2000
Very Dense
over 50
85 - 100
Very Stiff
15 to 30
2000 - 4000
Hard
over 30
>4000
USCS SOIL CLASSIFICATION SYSTEM
MAJOR DIVISIONS
GROUP DESCRIPTIONS
Gravel and
C9w
Well -graded GRAVEL
Coarse
Clean Gravel
•'
Grained
Gravelly Soils
(little or no fines)
Soils
o
GP
Poorly -graded GRAVEL
More than
50% of Coarse
Gravel with
o
GM
Silty GRAVEL
Fraction Retained
Fines (appreciable
on No. 4 Sieve
amount of fines)
GC
Clayey GRAVEL
Sand and
Clean Sand
••
$w
Well -graded SAND
More than
Sandy Soils
(little or no fines)
$P
Pooriy-graded SAND
50% Retained
50% or More
on No.
of Coarse
Sand with:
$M
Silty SAND
200 Sieve
Fines (appreciable
Fraction Passing
Size
No. 4 Sieve
amount of fines )
$C
Clayey SAND
MIL
SILT
Fine
Silt
CL
Lean CLAY
Grained
and Liquid Limit
Soils
Less than 50%
Clay
—
OL
Organic SILT/Organic CLAY
MH
Elastic SILT
Silt
50% or More
Liquid Limit
Passing
and
or More
CH
Fat CLAY
Clay50%
No. 200 Sieve
Size
OH
Organic SILT/Organic CLAY
Highly Organic Soils
PT
PEAT
� tr
COMPONENT DEFINITIONS
COMPONENT
SIZE RANGE
Boulders
Larger than 12 in
Cobbles
3 in to 12 in
Gravel
3 in to No 4 (4.5mm)
Coarse gravel
3 in to 3/4 in
Fine gravel
3/4 in to No 4 (4.5mm)
Sand
No. 4 (4.5 mm) to No. 200 (0.074 mm)
Coarse sand
No. 4 (4.5 mm) to No. 10 (2.0 mm)
Medium sand
No. 10 (2.0 mm) to No. 40 (0.42 mm)
Fine sand
No. 40 (0.42 mm) to No. 200 (0.074 mm)
Silt and Clay
Smaller than No. 200 (0.074mm)
TEST SYMBOLS
%F
Percent Fines
AL
Afterberg Limits: PL = Plastic Limit
LL = Liquid Limit
CBR
California Bearing Ratio
CN
Consolidation
DID
Dry Density (pcf)
DS
Direct Shear
GS
Grain Size Distribution
K
Permeability
MD
Moisture/Density Relationship (Proctor)
MR
Resilient Modulus
PID
Photoionization Device Reading
PP
Pocket Penetrometer
Approx. Compressive Strength (tsf)
SG
Specific Gravity
TC
Triaxial Compression
TV
Torvane
Approx. Shear Strength (tsf)
UC
Unconfined Compression
SAMPLE TYPE SYMBOLS
®2.0" OD Split Spoon (SPT)
(140 lb. hammer with 30 in. drop)
IShelby Tube
3-1/4" OD Split Spoon with Brass Rings
OSmall Bag Sample
Large Bag (Bulk) Sample
Core Run
Non-standard Penetration Test
(3.0" OD split spoon)
GROUNDWATER SYMBOLS
Q Groundwater Level (measured at
time of drilling)
1 Groundwater Level (measured in well or
open hole after water level stabilized)
COMPONENT PROPORTIONS
PROPORTION RANGE
DESCRIPTIVE TERMS
< 5%
Clean
5 - 12%
Slightly (Clayey, Silty, Sandy)
12 - 30%
Clayey, Silty, Sandy, Gravelly
30-50%
Very (Clayey, Silty, Sandy, Gravelly)
Components are arranged in order of increasing quantities.
NOTES: Soil classifications presented on exploration logs are based on visual and laboratory observation.
Soil descriptions are presented in the following general order: MOISTURE CONTENT
Density/consistency, color, modifier (if any) GROUP NAME, addib'ons to group name (1f any), moisture DRY Absence of moisture, dusty,
content Proportion, gradation, and angularity of constituents, additional comments, dry to the touch.
(GEOLOGIC INTERPRETATION) MOIST Damp but no visible water.
Please refer to the discussion in the report text as well as the exploration logs for a more WET Visible free water, usually
complete description of subsurface conditions.
soil is below water table.
� Meadowdale 75th-76th Walkway Improvements LEGEND OF TERMS AND
SYMBOLS USED ON
� HMGEOSCIENCES INC. Edmonds, WA EXPLORATION LOGS
PROJECT No.: 2006-171-21 FIGURE: A-1
LEGEND 2006-171-21.GPJ 11/15/07
' DRILLING COMPANY: Davies Drilling SURFACE ELEVATION: t feet DATE STARTED: 10/1012007
DRILLING METHOD: Hollow stem Auger DATE COMPLETED: 10/10/2007
SAMPLING METHOD: Cat Head SPT LOGGED BY: P. Pearson
LOCATION: See Figure 2
m
g W W Z y co Standard Penetration Test
m
o- v~j D v~i w _U (140 lb. weight, 30" drop)
p Z U I.W.- w A Blows per foot
F- .� m y a o- y W O W
Q. v 2 2 z o = w= am
O �' Cn � DESCRIPTION in w a� O a ai p °'
0 10 20 3D 40 50
D SM Loose, Brown, sli 9 h tiY sil tY, fine to Medium SAND, moist with S-1 1-1-4 0
roots and rootlets.
' [FILL]
Soil becomes siltier then sandy again.
5...........*...........:....: 5
CL Loose, yellowish gray, sandy SILT, moist, trace organics. S-2 3-2-3
ML `--------jCOLLUVIUil--------�
Soft, bluish gray, silty CLAY, moist. Older, black trace
organics.
10...........�...:............ 10
Soft, bluish gray to brownish gray, silty CLAY, wet. Some S-3 1-1-2
dense chunks of day also.
15---------------------- ...�................... 15
' CL Medium stiff to stiff, gray, silty CLAY, moist. Trace S-3 4-4-6
laminations observed.
2 inch sandy layer.
CH Stiff to very stiff, gray, CLAY, moist. Slickenslides observed. S-5 3-8-15 —20
[PRE -GLACIAL TERRESTRIAL DEPOSITS]
25 :.... »
F--{ ...: 25
Hard, gray, CLAY with fine sand, slightly moist. S-6 10-21-35
30 ;....;....�.......... ;>> 30
Subvertical cracks with fine sands. Horizontal laminations S-7 9-18-32
observed.
35 .... .... .� ........:.... i>> 35
Hard, massive, gray, fine sandy, CLAY, moist to wet. S-8 13-27-5015
Boring terminated at 36.5 feet below surface.
' Inclinometer casing was installed with grout from 2.5 feet
above ground surface to 35 feet below ground surface.
40 Ground water observed at 10 feet and 35 feet at time of 0
..........:....:..
exploration. 4
45 45
0 20 40 60 80 100
Water Content (%)
Plastic Limit 1 0 Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
' 75th-76th Walkway Improvements BORING:
MT, I BH-1
Meadowdale
HMGEOSCIENCES INC. Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE A-2
PZO 2006-171-21.GPJ 11/15/07
DRILLING COMPANY: Environmental Drilling Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/25/2007
DRILLING METHOD: Hollow Stem Auger DATE COMPLETED: 10/25/2007
SAMPLING METHOD: SPT Auto Hammer LOGGED BY: V. Atkins
LOCATION: See Figure 2
w '
w CoCoStandard Penetration Test
v o D U) s (n w v (140 lb. weight, 30" drop)
O Z 0 � LU w ♦ Blows per foot
F- m a. a m y w O w x
0_ .
o "� x DESCRIPTION < can a F- a cq Wp a
0 10 20 30 40 50
0 0
. SP 1-2 inches of Asphalt over sand and gravel base course over
brownPoorly graded SAND with gravel fill.
ML Stiff, brown silt with Gay, moist.
[COLLUVIUM]
S-1 2 4 5
Loos1 browner ne SAND with silt slilht�oxidized, moist_ —
5 CL Medium stiff, brown, SILT with sand, with trace dark orange '
.A.:...�...:.......... 5
wet oxidized silty sand seams, moist. � S-2 2-2-5
— — S-3 3-7-8 r
ML Stiff, gray, SILT to clayey silt with seams of fine sand and
day, moist.
10 Sand seams are wet • • 10
' S-4 4-4-8
fragments in sample------------- S-5 5-8-8
r'
[iWood
Stiff to very stiff, brown to olive brown organic SILT, moist.
15 .;. _.. ....i....i 15
ML Very stiff, gray to olive gray, sandy SILT, wet. S-6 3-8-11 �' ~
' [COLLUVIAL BLOCKS]
— — — — — — — — — — — — — — — — — — — — — —
SM Medium dense, gray, fine sandy SILT, wet.
....... 20 20
:.
CL Very stiff, gray, CLAY, moist.
High plasticity.
25 25
30 30
S-9 6-9-15 •
Boring was terminated at 31.5 feet below ground surface.
Ground water seepage was encountered at 15 feet below
ground surface. A ground water monitoring well was installed
35 with screen from15-25 feet, and sand from 12 to 30 feet. :..
35
40 40
' 0 20 40 60 80 100
Water Content (%)
Plastic Limit 1Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
' 75th-76th Walkway Improvements BORING:
BH-2
Meadowdale
HWAGEOSCIENCES INC Edmonds, WA PAGE: 1 of 1
' PROJECT NO.: 2006-171-21 FIGURE: A-3
PZO 2006-171-21.GPJ 11/15/07
DRILLING COMPANY: Environmental Drilling Inc.
LOCATION: See Figure 2
DRILLING METHOD: Hollow Stem Auger
DATE STARTED: 10125/2007
SAMPLING METHOD: SPT Auto Hammer
DATE COMPLETED: 10/25/2007
SURFACE ELEVATION: t feet
LOGGED BY: D. Coltrane
gw
z
w Standard Penetration Test
U
EL
Co
N
D
¢ (140 lb. weight, 30" drop)
J
r
-' y
w
A Blows perfoot
w
w
o DESCRIPTION
ai
U)i
a 8
O
CC
w
� w
0 10 20 30 40
50
0
7 inches of as halt at surface.0
SM
Medium dense, olive brown to light brown, silty fine SAND
'
•''•
with gravel, moist.
••••••••••••• ••••••.........
[FILL]
S 1
4 9 9
A'
�-C
1 10-
1 15-
1 20-
1 25 -
1 30-
1 35 -
S-2
5-6-10
ML
Medium dense to dense, olive brown, silty SAND to sandy
SM
SILT, with fine SAND seams, moist. Oxide mottling in seams
S-3
5-8-15
of fine SAND.
[COLLUVIUM]
S-4
11-15-16
Gravellyrillina dfrom BG 11 to 11.5 feet S.
CL
ML
_ _ _ _ _ _ _
Very stiff, gray to olive gray, silty CLAY with seams of gray
S-5
7-9-13
silty fine SAND, moist. SILT has organic smell.
[COLLUVIAL BLOCKS]
S-6
4-6-10
SIP
--
Loose, gray, poorly graded, fine to medium SAND with silt and
trace fine gravel, moist to wet.
S-7
2-3-7
Drilling became hard at 25-26 feet BGS.
S
6-12-23
ML
_
Hard, olive gray to olive brown, laminated SILT, moist.
a
SM Medium dense, gray, silty fine SAND, wet. S-9 7-12-12
Boring was terminated at 31.5 feet below ground surface.
Minor ground water seepage was encountered during the
exploration, but there was no standing ground water in the
hole after the auger was removed.
40-
For a proper understanding of the nature of subsurface conditions, this
exploration log should be read in conjunction with the text of the
geotechnical report.
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
F--5
I-90 I
F-15
F-25 1
f— 30 1
1— 35 1
0 20 40 60 80 100
Water Content (%)
Plastic Limit i 0 Liquid Limit
Natural Water Content
75th-76th Walkway Improvements BORING:
MWI I BH-3
Meadowdale
EMGEOSCIENCES INC. Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171 -21 FIGURE: A-4
BORING 2006.171-21.GPJ 11/15/07
SM
Medium dense, brown, sandy SILT with gravel, roots and
rootlets, moist.
[FILUOLD TOPSOIL]
- - - - - - - - - - - - - - - - - - - - - -
Medium dense, brown silty SAND with gravel, roots and
SM
woodchips. Less moist than above.
- - - - - - - - - - - - - - - - - - - - - -
Loose, yellowish brown Silty SAND With gravel, organics and
- -
SM
pieces ofwood. No ground water.
75th-76th Walkway Improvements HAND HOLE:
HH-1
Meadowdale
EWGEOSaENCES INC Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE7 A-5
HANDHOL 2006-171-21.GPJ 11115/07
DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/8/2007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10/8/2007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
' LOCATION: See Figure 2
rn uj m Z w
o Ut U) ~¢
} U
N W W LU
I— m w o_ a N w Z
' o Cn D DESCRIPTION uai a 8 O 0 w
0
0 SM Loose, dark brown, silty SAND with Gravel and organics. 0
Moist
-------- [TOPSOIL] ---------
SM Loose, light olive brown, silty SAND with rootlets and chunks
of grayish clay blow 1.5'.
1 [COLLUVIUM[
S-1 1
0
' 2 2
ML Soft olive brown, SILT with sand, chunks of gray clay, small S-2
woodchips and bits of charcoal. 0
3 3
' 4 4
5....:....:....:....:....:....:....:....:....:.... 5
6—
6
Hand hole was terminated 5.5 feet below ground surface.
Ground water seepage was encountered at 5.0 feet below
ground level and stabilized at 4.7 feet below ground level after
exploration.
7 7
8 : 8
' 0 20 40 60 80 100
Water Content (%)
Plastic Limit 1---0— Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
' � 75th-76th Walkway Improvements HAND HOLE:
HH-2
Meadowdale
HMIGEOSCIENCES INC. Edmonds, WA PAGE: 1 of 1
' PROJECT NO.: 2006-171-21 FIGURE: A-6
HANDHOL 2005-171-21.GPJ 11/15/07
' DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/8/2007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10/8/2007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
' LOCATION: See Figure 2
to W W Co z .. W
^ U o ~L ~ F}- U
J y LLl lL W F-' 0 w
F- m U) a Q- y W 7 _
Lu ° w
o N � DESCRIPTION u¢i vai a s O c�a o
0
`. SM Loose, light brown, silty SAND with gravel and roots, moist. 0
[TOPSOIL]
' S1 .
SM Loose, light yellowish brown, silty SAND with gravel and wood
chips. gravels are fine to medium. Soil is moist but less so
than above. O S-2
2 [RECESSIONAL OUTWASH] 2
Hand hole was terminated at 2.25 feet below surface level.
3 No ground water seepage was encountered during 3
exploration.
' 4 4
5 :....:....:....:....:.... 5
6 6
7 7
8 8
t 0 20 40 80 80 100
Water Content (%)
Plastic Limit 1 0 Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
75th-76th Walkway Improvements HAND HOLE:
HH-3
Meadowdale
HMGEOSCIENCES INC Edmonds, WA PAGE: 1 of 1
' PROJECT NO.: 2006-171 -21 FIGURE: A-7
HANDHOL 2006-171-21.GPJ 11/15/07
' DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION: 3 feet DATE STARTED: 10/8/2007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10/8/2007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
' LOCATION: See Figure 2
m Z of
W
v (L F m H
N J } n !n U (n Q N
J 0 W W W �p I— p
2
m <n CL a o y w F
' o of d
DESCRIPTION ai ai a 8 O p
0 0
. SM Medium dense, brown, silty SAND with gravel, roots and
rootlets, moist.
' [TOPSOIIJWEATHERED OUTWASH]
1 1
' S-1
O
' 2 — — — — — — — — — — — — — — — 2
SM Loose, light yellowish brown silty, gravely SAND, moist. S-2
[RECESSIONAL OUTWASH] O
3—
3
Hand hole was terminated at 2.5 feet below surface level. No
ground water seepage was encountered during exploration.
4 4
5 5
6 6
' 7 7
8 B
' 0 20 40 60 80 100
Water Content (%)
Plastic Limit 1 0 Liquid Limit
Natural Water Content
' NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
75th-76th Walkway Improvements HAND HOLE:
MT1, I Meadowdale HH-4
EMGEOSCIENCEB INC Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE: A-6
HANDHOL 2006-171-21.GPJ 11/15/07
1
1
1
1
1
1
1
1
1
1
1
1
1
DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION:
DRILLING METHOD: Hand Bucket Auger
SAMPLING METHOD: GRAB
LOCATION: See Figure 2
t feet
DATE STARTED: 10/812007
DATE COMPLETED: 10/8/2007
LOGGED BY: D. Coltrane
rn
Lu
Z
w
U
M
(L
-
F aa)
F
'1
N
J
Y• Z
(n V
toj
J O
W W
W (G
F-
p
„1D
F-
m U)
a a
m
w
Z
2
o
N D DESCRIPTION
v¢i v¢i
o
Wa Z
O
Q
a
p
0
SM Loose, very dark brown, silty SAND with organic material,
0
1
andcobbles. Moist
HAND HOLE:
=I I 75th-76th Walkway Improvements HH-5
Meadowdale
HMGEO$CIENCE$ INC. Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE: A-9
HANDHOL 2006-171-21.GPJ 11/15/07
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Loose -medium dense, light olive gray, sandy SILT with
organics. Soil was dumpy with some debris, moist.
[COLLUVIUM]
----------------------
Soft, light olive gray, silty CLAY. Chunks of silty sand, pieces
ML
of wood, and roots, moist.
Loose, light gray to yellowish brown, silty CLAY, moist.
IML
75th-76th Walkway Improvements HAND HOLE:
BOA I HH-6
Meadowdale
EMGEOSCIENCES INC, Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE: A-1 0
HANDHOL 2006-171-21.GPJ 11/15/07
or
DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/1912007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10/19/2007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
LOCATION: See Figure 2
Ucn m Z _ w
�a} ? I t � Lu Q Non -Standard Penetration Resistance
a' rp W w w o (17.6 lb. weight, 22.6" drop)
I= m N a Ja X y Z =
Lu
' o
o r¢n DESCRIPTION vai a O �0 c0
0 `. 0 SM Loose, olive brown silty SAND with gravel, roots and rootlets
present, moist.
' [FILL]
1 * 1
O S-1
2 2
' Piece of old asphalt at 2_25 feet below ground surface._ _ _ S-2 Ajb:
SP �Mediurn dense, gray gravelly fine to medium SAND with silt,
3
ots and rootlets, moist. g
' OLD TOP--I,L �
Hand hole was terminated at 3.0 feet below ground surface.
4 No ground water seepage was encountered during the A4
exploration. i
5 5
7 7
6
8
9 9
10 10
11 A� 11
12
12
13
13
' 14
14
15
15
0 20 40 60 80 100
Water Content (%)
Plastic Limit Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
75th-76th Walkway Improvements HAND HOLE:
um, I HH-7
Meadowdale
HMGEOSCIENCES INC. Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FIGURE: A-1 1
HANDHOL 2006-171-21.GPJ 11/15/07
DRILLING COMPANY: HWA Geosciences Inc. SURFACE ELEVATION: t feet DATE STARTED: 10/19/2007
DRILLING METHOD: Hand Bucket Auger DATE COMPLETED: 10A9/2007
SAMPLING METHOD: GRAB LOGGED BY: D. Coltrane
' LOCATION: See Figure 2
of
U a Q Q Non -Standard Penetration Resistance
a) J _ U) U N
J O Z <n S H
W p (17.6 lb. weight, 22.6" drop) w
1:p CO W w m Z -
F co <A a. EL N a:x
-AJ
w WQ. i..,
O to Z) DESCRIPTION cQn c¢n - 7 O (3 p
0 0
`. SM Loose, light brown, silty SAND with gravel, roots and rootlets,
moist.
' [FILL] ♦
1 1
O S-1
2 ♦ 2
SM Loose, brown, silty SAND with gravel, burnt wood bits, roots,
3 and rootlets, moist. O S-2
OLD TOPSOIL3
' »
4 Hand hole was terminated at 3.2 feet below ground surface. a No groundwater seepage was encountered during the ::: 4
exploration. 1
♦:
' 5-
6— ♦`
' ♦ 6
7 7
' 8
8
9 9
10 :....:....:....:-10
...
11 11
12
12
' 13 13
' 14 14
15 15
' 0 20 40 60 80 100
Water Content (%)
Plastic Limit 1 --0 Liquid Limit
Natural Water Content
NOTE: This log of subsurface conditions applies only at the specified location and on the date indicated
and therefore may not necessarily be indicative of other times and/or locations.
HOLE:
H
'75th-76th Walkway Improvements HAND
��r� (UWA
Meadowdale F
HMGEOSWNCH INC. Edmonds, WA PAGE: 1 of 1
PROJECT NO.: 2006-171-21 FI Re A-12
HANDHDL 2006-171-21.GPJ 11/15/07
1.5 inches of Beauty Bark on surface.
`.
SM
Loose to medium dense, olive brown, silty SAND with gravel,
roots and rootlets, moist.
pieces of plastic and cemented soils present.
[COLLUVIUM/FILL]
ML
Soft, to loose, layers of olive brown, sandy SILT with trace
SM
gravel, mottled olive brown fine silty SAND with rootlets, and
grayish brown sandy SILT with trace gravel, roots, rootlets,
and pieces of burnt wood present, moist.
[COLLUVIUM]
' A HAND HOLE: 75th-76th Walkway Improvements HH-9
Meadowdale
HMGEOSCIENCES INC. Edmonds, WA PAGE: 1 of 1
PROJECTNO.: 2006-171-21 FIGURE A-13
HANDHOL 2006-171-21.GPJ 11/15/07
7
� Appendix B
� Geotechnical Laboratory
Testing
I
�' I
I�
T
m
di
CN
Q LL
Q
N0Q N
J5 f ) T
1 ��T
J00 o
V �-- N
O
Q z
IL U
W
0
LL'
a
N
C
N
N
O
Q O Q
O
M 'O
�o O
(d N E
W
CO
i
LO
ti
0
0
0
00
■
J
J_
H
U � �
0
U � �
CDN
J
J
U
O O O O O O 00
C4 � M N
Od) X34N1 ,,UIOIlS`d-ld
LL
di
N
N
0
d M n o
d N N N
�n n c`7�i r°'i
U
g n n rn coo N M M
e
z
O
H
U
LL
g
} } U I—
U
J U �
.N
T
O
T A O y
CM m (0 'O
y Y �
0 cc J �
2 2 J J
� u� in o u�
cD v co
= N M N
H
d o o �n o
w � O N 6
W fA fA fn N
a
� co
2 2 2
m m m m
J
O
00 • ■ t O
}
pCL
:
cr
w
0 N
Q J m
f=0ao
�
M LL
UO�
X�
JZQ �
I_-F=0 0
N
Q Q�
z
J ~
U
w
J a
m
C
O
O
m E
w
di
N
N
0
d M n o
d N N N
�n n c`7�i r°'i
U
g n n rn coo N M M
e
z
O
H
U
LL
g
} } U I—
U
J U �
.N
T
O
T A O y
CM m (0 'O
y Y �
0 cc J �
2 2 J J
� u� in o u�
cD v co
= N M N
H
d o o �n o
w � O N 6
W fA fA fn N
a
� co
2 2 2
m m m m
J
O
00 • ■ t O
}
pCL
:
cr
w
0 N
Q J m
f=0ao
�
M LL
UO�
X�
JZQ �
I_-F=0 0
N
Q Q�
z
J ~
U
w
J a
m
C
O
O
m E
w
0 N
Q J m
f=0ao
�
M LL
UO�
X�
JZQ �
I_-F=0 0
N
Q Q�
z
J ~
U
w
J a
m
C
O
O
m E
w