bld20080257_Sound Trans-Ed Station_REVISED SCOPE_7.pdf
DATE: February 18, 2010
TO: Andrea Clinkscales
Sound Transit
andrea.clinkscales@soundtransit.org
FROM: Jeanie McConnell, Engineering Program Manager
RE: Application #: bld20080257
Project: Sound Transit Edmonds Station REVISED SCOPE
Project Address: 209 West Dayton Street
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please redline plans or submit three (3) sets of revised
plans/documents with a written response to each of the items below to Marie Harrison.
City of Edmonds handouts and standard details can be referenced on the City website under
Development Services Department, Engineering Division.
Review 7 February 18, 2010
Review 6 January 14, 2010
Review 5 December 1, 2009 - REVISED SCOPE, new comments
Previous reviews:
Review 4 November 17, 2008
Review 3 July 22, 2008
Review 2 June 12, 2008
Review 1 - April 22, 2008
EDM-PV3 Sheet 19 Paving and Horizontal Control Plan
2/18/10 In addressing this comment other sheets will need to be updated as well,
1.
specifically sheet 26.
The curb ramps that have been provided on the south side of the drive are acceptable.
·
However, only one curb ramp has been identified on the north side of the drive and the
·
ramp is conflict with the existing 84 SSMH. I have discussed with City staff the
reasoning behind the flush pedestrian walk adjacent to the drive (protected by
bollards) and it has been determined that the City would accept two curb ramps
similar to those shown on the south side of the driveway. It appears as though the curb
ramp at the NW corner could begin just south of the sewer manhole access. The
landscape planter between the two ramps in question could be extended to the south
and terminate at a curb adjacent to the drive.
Please also include the requirement for truncated domes at each ramp.
·
Move right turn only arrow to the east a short distance and add in a stop bar as well as
·
crosswalks.
1/14/10 Consistent with our discussions on 1/13/10, please revise plans to show sidewalk curb
ramps that are necessary to transition the full height sidewalk to be flush with the stained
concrete driveway approach. Please see attached plan markup of what this could look like.
12/1/09 - While it is not clear from this plan sheet if the stained concrete area is flush with the
driveable surface, it appears from Sheet 32-EDM-PS3 that it is.
a.A break in the curb is noted on the west side of the stained concrete, but curb ramps have
been provided to indicate a grade change from sidewalk to driveable surface. Please
revise accordingly.
b.It appears as though the curbing should wrap around the sidewalk areas. Please revise
accordingly.
ok
c.
ok
2.
ok
3.
ok
4.
ok
5.
ok
6.
ok
7.
ok
8.
EDM-GD1 Sheet 24 Grading, Drainage and Utility Plan
ok
1.
ok
2.
ok
3.
ok
4.
ok
5.
ok
6.
ok
7.
ok
8.
ok
9.
2/18/10 If this CB no longer serves the subject property then it should be abandoned, as
10.
well as the stub to the existing CB in West Dayton. Are there existing connections into this
CB that need to be maintained? If not, please abandon.
1/14/10 It appears as though an existing storm catch basin has not been accounted for in the
vicinity of the new water service line, RPBA and storm CB #2 near West Dayton. Please revise
plans accordingly.
11.2/18/10 The light pole shown in the planter area north of the lift station and driveway
appears to be in conflict with the existing 84 SSMH. Please revise.
Bld20080257 Sound Transit Edmonds Station Page 2 of 3
12.2/18/10 - The following comments could be redlined on the plans:
a.An RPBA in a hotbox shall be installed on the existing water service line.
b.Contractor shall pothole location of water main prior to installation of light poles to
ensure 5 separate between water main and light pole.
Sheet 26 Grading, Drainage and Utility Plan
. 2/18/10 -The following comment could be redlined on the plans:
1
a.An RPBA in a hotbox shall be installed on the existing water service line.
Sheet 28 Storm Drain and Utility Details
1.2/18/10 Due to settlement issues found within wet environments, the catch basin
foundation should also include a rat slab to be poured prior to setting the structure.
Please contact me at 425-771-0220 or by e-mail at mcconnell@ci.edmonds.wa.us if you have
specific questions regarding these plan corrections.
Bld20080257 Sound Transit Edmonds Station Page 3 of 3