bld20080296 - Pt Edwards_Amenities #2_Plumbing.pdf
DATE: April 30, 2008
TO: Leonetti Plumbing, Inc.
mike@leonettiplumbing.com
FROM: Jeanie McConnell, Engineering Program Manager
RE: Application #: bld20080296
Project: Pt Edwards Amenities 2, Plumbing
Project Address: 21 Pine Street
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please submit three (3) sets of revised plans/documents
with a written response to each of the items below to Marie Harrison.
1.The sanitary sewer and storm connections shown on Sheet P1.0 do not appear to be consistent
with the civil construction drawings.
a.According to the approved civils, the sewer stub provided is located along the NW side
of the building and not perpendicular to Loop Rd. Without the property line/Loop Rd
being shown on this plan it is difficult to be sure of where the connection is shown, but
according to the North arrow, it is not consistent with the civils.
b.Also in accordance with the approved civils, the storm stub provided to Amenities 2, is
from Cleanout #18B and does not tie directly into the storm main.
Please revise the plan accordingly to show the utility connections consistent with the civils.
Please contact me at 425-771-0220 or by e-mail at
mcconnell@ci.edmonds.wa.us if you have
specific questions regarding these plan corrections.
bld20080296 - Pt Edwards_Amenities #2_Plumbing Page 1 of 1