CITY OF EDMONDS
PLAN REVIEW COMMENTS
ENGINEERING DIVISION
(425) 771-0220
City Website: www.ci.edmonds.wa.us
DATE: September 25, 2008
TO: File
FROM: Jerry Shuster, P.E., Stormwater Engineering Program Manager
RE: Application #: bld20080635
Project: Andersen Office Building
Project Address: 665 Edmonds Way
Item reviewed:
Drainage report dated June 10, 2008
Plan sheets C1-C3
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed.
The major items regarding site drainage that require revising include: the predevelopment site
assumptions used in the model, the precipitation values used in the model, and the piping plan for
roof water. In the erosion and sediment control plan, several steps in the construction sequence
need to be added as well as relocation of the silt fence (or the limits of clearing).
These items and minor revisions are detailed in the enclosed checklists.
Please contact me at 425-771-0220 or by e-mail at mcconnell@ci.edmonds.wa.us if you have
specific questions regarding these plan corrections.