DATE:
July 22, 2010
TO:
Steve Waite
waitearch@comcast.net
FROM:
Jeanie McConnell, Engineering Program Manager
RE:
Plan Check #: BLD20090279
Project: El Sharawy - Pool
Project Address: 9231 Olympic View Drive
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please redline plans or submit three (3) sets of revised
plans/documents with a written response to each of the items below to Theresa Umbaugh.
City of Edmonds handouts and standard details can be referenced on the City website under
Development Services Department, Engineering Division.
June 10, 2009 Comments 1
October 23, 2009 Comments 2
July 22, 2010 Comments 3
1.ok
2.ok
3.ok
4.ok
5.ok
6.ok
7.ok
8.ok
9.ok
10.ok
11.ok
7/22/10 The retaining wall located on the neighboring property has been omitted from
12.
the recent resubmittal. Please provide proof of easement or agreement that allows for the
proposed drainage outfall from the detention system to the existing concrete lined ditch
located on this neighboring parcel.
10/23/09 comment A separate parcel number has been provided for the property in which the
retaining wall is located. Snohomish County records indicate this parcel is not owned by
Page 1 of 2
Sharawy bld20090279
Sharawy. Please provide verficiation that the property is in fact owned by Sharawy or relocated
improvements to private property.
6/10/09 comment - Show proposed retaining wall at the property line. Dimension wall setback
from property line and driveway surface. As noted on the plans, a surcharge shall not be placed
on the wall.
ok
13.
7/22/10 Note E14 has been revised to show omission of the wall drainage connection to
14.
the detention system. However, a section of tightline is still shown on the plans from the
area of the retaining walls to the detention system. In addition, the RIM and invert
elevations provided for the detention system are incomplete and/or are inconsistent with
regards to direction provided and north arrow shown. Please verify/provide RIM and
invert elevations at each CB of the detention system.
10/23/09 comment Please clarify Revision E14 note. Does the detention system daylight into
the existing conc. lined ditch? What about the retaining wall footing? Are they connected
together somehow? Please provide additional information on the existing flume and drop
where is the water directed from this point?
6/10/09 comment - Show point of connection of retaining wall drainage to an approved storm
system.
Please contact me at 425-771-0220 or by e-mail at mcconnell@ci.edmonds.wa.us if you have
specific questions regarding these plan corrections.