Plan Review Corrections
Application : Date:
# bld20090339 June 29, 2009
Project Name/Address:
South County Senior Center / 220 Railroad Ave
Contact Person/Address, Fax or E-mail:
J Stevens / e-mail: jstevens@ci.edmonds.wa.us
Reviewer: JoAnne ZulaufDivision:Engineering
During review of the above noted application, it was found that the following information, corrections, or
clarifications are needed. Please redline plans or submit three (3) sets of revised plans/documents with a
written response to each of the items below to Theresa Umbaugh.
1.Site plan should show all intended changes and additions. Please provide a complete site plan showing the
proposed changes, parking, direction of traffic, catch basins, sidewalks etc.
2.Specify dimensions of drive aisle and sidewalk/walkway area. Clarify that existing striping and signage for
one way traffic to be shown on plan.
3.The plan provided shows the catch basin in the wrong location. It is actually approximately 7 ft or so from
the west wall which would place it at the landing for the new door. This catch basin takes in the runoff from
the travel lane and the parking lot area to the north. Please show where the catch basin will be relocated to
continue to be able to function as intended. Include grading and intended flow lines to show direction of
runoff.
4.Please clarify the replacement of asphalt with concrete. Will you be replacing the entire asphalt patched area
with concrete? The plan provided shows that the asphalt will be demo’d but does not show replacement.
Will this be used as sidewalk? Please show area on site plan with label and measurements. Will there be a
curb along the concrete area? How will drainage of this area be handled?
5.What type of drainage system does the tightline connect to? Clarify location of the tightline and will it be re-
routed to the exterior of the building? Show on the site plan where it connects to drainage system.
6.Please add to site plan temporary erosion and sedimentation control measures to be in place during
demolition and construction.
DATE E-MAILED 8/15/07 PAGE
1 of 2
Please contact me at 425-771-0220 or by e-mail at mcconnell@ci.edmonds.wa.us if you have specific
questions regarding these plan corrections.
DATE E-MAILED 8/15/07 PAGE
2 of 2