bld20100339-Gold_ENG1.pdf City of Edmonds TH 121 5 AVENUE NORTH • EDMONDS, WA 98020 • (425) 771-0220 FAX(425) 771-0221 Website: www.ci.edmonds.wa.us PUBLIC WORKS DEPARTMENT Engineering Division Plan Review Corrections Plan Check :Date: #BLD20100339 June 8, 2010 th Project Name/Address: Gold – 16200 -75 Pl W Contact Person/Address/Fax: Robert Hughes – larslandy@hotmail.com Jennifer LambertDivision:Engineering Reviewer: During review of the subject submittal, it was found that the following information, corrections, or clarifications would need to be addressed. Our handouts can be found online at the City of Edmonds web site www.ci.edmonds.wa.us under City Government/Development Services/Engineering Division. Please resubmit 3 copies of the revised plans/documents to a Development Services Coordinator. Please contact me at 425-771-0220 if you have specific questions regarding these plan corrections. General: 1.Please revise the city approval block to say city engineering division instead of city engineer on all plans. 2.Prior to issuance of the permit a $50,000.00 performance bond will be required. 3.Please note that a special inspection will be required for the cut in exsting slope and placement of structural fill for the driveway construction. Site Plan: 1.Please show the existing house as TBR. Grading, TESC & Profiles Plan: 1.Please remove the vacated street from plans (name, dimensions, etc.). 2.Please revise grading quantities of cut/fill to be consistent with the grading calculations. DATE MAILED/FAXED 6/9/2010 PAGE ____ OF ___ 13 3.Please remove directional flows from the ‘Grading, TESC & Profiles Plan’ and add to the drainage plan. Please verify that all surface water runoff will be collected and drained to the storm system. 4.Add a general notes section (example provided). th 5.Please note why clearing is occurring within the right of way along 75. We are concerned with slope stability on the downhill side. Please provide a landscape plan. 6.Please add a haul route plan. Road, Drainage, & TESC Details Plan: General: 1.Please remove the vacated street from plans (name, dimensions, etc.). 2.Please revise the sheet title to include ‘Utilities’. 3.Please provide a driveway slope waiver request per ECDC 18.80.060 D justifing why you must exceed 14%. 4.Please note on plans what surface material will be used for the driveway. 5.Please revise ‘Gravel Construction Entrance’ detail to be consistent with Standard Detail E1.2 ‘Stabilized Construction Entrance’. 6.Please show a driveway apron to allow for the turn radius of cars entering the driveway without causing erosion to the landscape area abutting the driveway entrance. Utilities: 1.Please show location of all existing and proposed utilities (water, sewer, storm, gas, power, phone, cable) a.Please note that all new utilities must go underground. 2.Please show the 10’ sewer easement (see attached) located on the west side of the property. 3.Please show the location of the sewer line. You may add a note to the plans to contact engineer of record if actual location differs from what’s shown. 4.Please show a cleanout located at the sewer easement. a.Please note on the plans that the cleanout shall be 6” with 12” cast iron locking lamphole cover (with ½” hexbolts) on right of way side of property line. 5.Please show on the plans a cleanout approximately 2’ from the house. 6.Please provide elevations at sewer cleanouts. 7.Please note on plans if you are intending to use existing side sewer lateral, from main to edge of easement. If you are, it will need to be TV’s by Public Works to determine if it is in acceptable condition to re-use. Contact Public Works at 425-771-0235. If condition is not acceptable to reuse, owner/contractor shall be responsible to replace sewer lateral. 8.Please note on plans that the water service line will be a minimum of 1” diameter pipe at 160 PSI. DATE MAILED/FAXED 6/9/2010 PAGE ____ OF ___ 23 Drainage: 1.The yard drains must be a minimum of Type I catch basins due to the high velocity of flow. Please revise accordingly. 2.Please show the rim and invert elevations for all the catch basins. 3.A different line type was used for the connection of the drainage from one of the retaining walls. Is this accurate? If this was intended please note on plans what the dashed line indicates? If this was not intended to be a different line type please revise plans accordingly. 4.Please add a general note on plans: if rim to invert exceeds 5’ a Type II manhole must be installed. 5.Please show the impervious surface calculations. 6.Please remove directional flows from the ‘Grading, TESC & Profiles Plan’ and add to the drainage plan. Please verify that all surface water runoff will be collected and drained to the storm system. 7.Please show a raised edge from CB#2 around the driveway radius to prevent runoff from cascading down the slope. 8.Based on the information provided, the project is exempt from ECDC 18.30.060 A1 (stormwater detention/streambank erosion control). a.However, since the project creates 5,000 sq ft or more of new impervious surface, requirements 2-10 described in ECDC 18.30.060 B must be evaluated for this project. A description of compliance with each minimum requirement or a rationale for why a requirement doesn’t apply to this site must be presented. Traffic Impact Analysis: Traffic Impact fees are not required for the subject development (demo 1 SFR, build 1 SFR). DATE MAILED/FAXED 6/9/2010 PAGE ____ OF ___ 33 GENERAL NOTES 1. ALL MATERIALS AND WORK SHOWN ON THESE PLANS SHALL CONFORM TO THE CITY OF EDMONDS STANDARD PLANS AND DETAILS, THE FOLLOWING SPECIFICATIONS AND CODES, AND ALL OTHER APPLICABLE LOCAL MUNICIPAL, STATE, AND FEDERAL CODES, RULES AND REGULATIONS: - CURRENT INTERNATIONAL BUILDING CODE (IBC) - 2010 WSDOT/APWA STANDARD SPECIFICATIONS FOR ROAD, BRIDGE AND MUNICIPAL CONSTRUCTION - WASHINGTON STATE DEPARTMENT OF ECOLOGY STORMWATER MANAGEMENT MANUAL FOR THE PUGET SOUND BASIN (CURRENT EDITION) 2. STANDARD PLAN AND TYPE NUMBERS INDICATED ON THESE DRAWINGS REFER TO CITY OF EDMONDS STANDARD DETAILS, UNLESS NOTED OTHERWISE 3. A COPY OF THESE APPROVED PLANS MUST BE ON THE JOBSITE WHENEVER CONSTRUCTION IS IN PROGRESS. 4. DEVIATIONS FROM THESE PLANS MUST BE APPROVED BY THE ENGINEER OF RECORD AND THE LOCAL GOVERNING AUTHORITY. 5. CONTRACTOR SHALL RECORD ALL APPROVED DEVIATIONS FROM THESE PLANS ON A SET OF "AS-BUILT" DRAWINGS AND SHALL SUMMARIZE ALL AS- BUILT CONDITIONS ON ONE SET OF REPRODUCIBLE DRAWINGS FOR SUBMITTAL TO THE OWNER PRIOR PROJECT COMPLETION AND ACCEPTANCE. A SET OF AS- BUILT DRAWINGS SHALL BE SUBMITTED TO THE CITY OF EDMONDS PRIOR TO FINAL APPROVAL OF THE BUILDING OCCUPANCY/FINAL PROJECT APPROVAL. 6. ELEVATIONS SHOWN ARE IN FEET. SEE SURVEY FOR BENCHMARK INFORMATION. 7. THE LOCATIONS OF EXISTING UTILITIES AND SITE FEATURES SHOWN HEREON HAVE BEEN FURNISHED BY OTHERS BY FIELD SURVEY OR OBTAINED FROM AVAILABLE RECORDS AND SHOULD THEREFORE BE CONSIDERED APPROXIMATE ONLY AND NOT NECESSARILY COMPLETE. IT IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR TO INDEPENDENTLY VERIFY THE ACCURACY OF ALL UTILITY LOCATIONS SHOWN AND TO FURTHER DISCOVER AND PROTECT ANY OTHER UTILITIES NOT SHOWN HEREON WHICH MAY BE AFFECTED BY THE IMPLEMENTATION OF THIS PLAN. CONTRACTOR SHALL VERIFY LOCATION, DEPTH, SIZE, TYPE AND CONDITION OF EXISTING UTILITY LINES AT CONNECTION OR CROSSING POINTS BEFORE TRENCHING FOR NEW UTILITIES. ENGINEER ASSUMES NO RESPONSIBILITY FOR THE COMPLETENESS OR ACCURACY OF THE EXISTING UTILITIES AND SITE FEATURES PRESENTED ON THESE DRAWINGS. ENGINEER SHALL BE NOTIFIED IMMEDIATELY OF CONFLICTS THAT ARISE. 8. CONTRACTOR SHALL LOCATE AND PROTECT ALL UTILITIES DURING CONSTRUCTION AND SHALL CONTACT THE UNDERGROUND UTILITIES LOCATION SERVICE (1-800-424-5555) AT LEAST 48 HOURS PRIOR TO CONSTRUCTION. 9. CONTRACTOR SHALL VERIFY ALL CONDITIONS AND DIMENSIONS AT THE PROJECT SITE BEFORE STARTING WORK AND SHALL NOTIFY OWNER'S REPRESENTATIVE OF ANY DISCREPANCIES. 10. PIPE LENGTHS WHERE SHOWN ARE APPROXIMATE AND MAY CHANGE DUE TO FIELD CONDITIONS. 11. CONTRACTOR SHALL OBTAIN A COPY OF THE GEOTECHNICAL REPORT (WHERE APPLICABLE) AND SHALL THOROUGHLY FAMILIARIZE HIMSELF WITH THE CONTENTS THEREOF. ALL SITE WORK SHALL BE PERFORMED IN STRICT COMPLIANCE WITH THE RECOMMENDATIONS OF THIS REPORT. 12. STRUCTURAL FILL MATERIAL AND PLACEMENT SHALL CONFORM TO THE RECOMMENDATIONS OF THE PROJECT GEOTECHNICAL REPORT. 13. MANHOLES, CATCH BASINS, UTILITIES AND PAVEMENT SHALL BEAR ON MEDIUM DENSE TO VERY DENSE NATIVE SOIL OR COMPACTED STRUCTURAL FILL. IF SOIL IS DISTURBED, SOFT, LOOSE, WET OR IF ORGANIC MATERIAL IS PRESENT AT SUBGRADE ELEVATION, REMOVE AND REPLACE WITH COMPACTED STRUCTURAL FILL PER GEOTECHNICAL REPORT. 14. SEE SURVEY AND ARCHITECTURAL DRAWINGS FOR DIMENSIONS AND LOCATIONS OF BUILDINGS, LANDSCAPED AREAS AND OTHER PROPOSED OR EXISTING SITE FEATURES. 15. SEE ARCHITECTURAL DRAWINGS FOR PERIMETER FOUNDATION DRAINS. FOUNDATION DRAINS SHALL BE INDEPENDENT OF OTHER SITE DRAIN LINES AND SHALL BE TIGHTLINED TO THE STORM DRAIN SYSTEM WHERE INDICATED ON THE PLANS. 16. ALL REQUIRED STORMWATER FACILITIES MUST BE CONSTRUCTED AND IN OPERATION PRIOR TO INSTALLATION OF ANY PAVEMENT UNLESS OTHERWISE APPROVED BY THE ENGINEER. 17. ALL ROOF DRAINS, PERIMETER FOUNDATION DRAINS, CATCH BASINS AND OTHER EXTERNAL DRAINS SHALL BE CONNECTED TO THE STORM DRAINAGE SYSTEM, UNLESS NOTED OTHERWISE. 18. CONTRACTOR SHALL OBTAIN AND PAY FOR ALL PERMITS REQUIRED FOR INSTALLATION OF ALL SITE IMPROVEMENTS INDICATED ON THESE DRAWINGS. 19. AS A MINIMUM REQUIREMENT, ALL DISTURBED AREAS ON AND OFF SITE SHALL BE RETURNED TO THE EQUIVALENT OF THEIR PRECONSTRUCTION CONDITION IN ACCORDANCE WITH APPROPRIATE REQUIREMENTS AND STANDARDS. 20. ALL DISTURBED SOIL AREAS SHALL BE SEEDED OR STABILIZED BY OTHER ACCEPTABLE METHODS FOR THE PREVENTION OF ON-SITE EROSION AFTER THE COMPLETION OF CONSTRUCTION. SEE EROSION CONTROL PLANS FOR SPECIFIC GRADING AND EROSION CONTROL REQUIREMENTS. 21. THE CONTRACTOR SHALL KEEP OFF-SITE STREETS CLEAN AT ALL TIMES BY SWEEPING. WASHING OF THESE STREETS WILL NOT BE ALLOWED WITHOUT PRIOR APPROVAL. 22. THIS PROJECT IS NOT A BALANCED EARTHWORK PROJECT. BOTH EXPORT AND IMPORT OF SOIL AND ROCK MATERIALS ARE REQUIRED. 23. SLOPE OF FINISHED GRADE SHALL BE CONSTANT BETWEEN FINISHED CONTOURS OR SPOT ELEVATIONS SHOWN. 24. FINISHED GRADE SHALL SLOPE AWAY FROM BUILDING WALLS AT MINIMUM 5% SLOPE FOR A MINIMUM DISTANCE OF 10 FEET. 25. CONTRACTOR SHALL BE RESPONSIBLE FOR AND SHALL INSTALL AND MAINTAIN SHORING AND BRACING AS NECESSARY TO PROTECT WORKERS, EXISTING BUILDINGS, STREETS, WALKWAYS, UTILITIES AND OTHER EXISTING AND PROPOSED IMPROVEMENTS AND EXCAVATIONS AGAINST LOSS OF GROUND OR CAVING EMBANKMENTS. CONTRACTOR SHALL ALSO BE RESPONSIBLE FOR REMOVAL OF SHORING AND BRACING, AS REQUIRED. 26. CONTRACTOR SHALL OBTAIN APPROVAL FROM THE CITY AND FOLLOW CITY PROCEDURES FOR ALL WATER SERVICE INTERRUPTIONS, HYDRANT SHUTOFFS, STREET CLOSURES OR OTHER ACCESS RESTRICTIONS. CONTRACTOR SHALL NOT RELOCATE OR ELIMINATE ANY HYDRANTS WITHOUT FIRST OBTAINING WRITTEN APPROVAL FROM THE FIRE MARSHAL. 27. COORDINATE AND ARRANGE FOR ALL UTILITY CONNECTIONS, UTILITY RELOCATIONS AND/OR SERVICE INTERRUPTIONS WITH THE AFFECTED OWNERS AND APPROPRIATE UTILITY COMPANIES. CONNECTIONS TO EXISTING UTILITIES SHALL BE MADE ONLY WITH ADVANCE WRITTEN APPROVAL OF THE AUTHORITIES GOVERNING SAID UTILITIES. 28. EXISTING UTILITY LINES IN SERVICE WHICH ARE DAMAGED DUE TO CONSTRUCTION WORK SHALL BE REPAIRED AT CONTRACTOR'S EXPENSE AND INSPECTED AND ACCEPTED BY CITY OF EDMONDS AND OWNER'S REPRESENTATIVE PRIOR TO BACKFILLING. 29. NEW UTILITY LOCATIONS ARE GENERALLY SHOWN BY DIMENSION, WHERE NO DIMENSIONS ARE INDICATED, LOCATIONS MAY BE SCALED FROM DRAWINGS. FIELD ADJUSTMENTS SHALL BE APPROVED BY OWNER'S REPRESENTATIVE AND CITY. 30. WHERE NEW PIPE CLEARS AN EXISTING OR NEW UTILITY BY 6" OR LESS, PLACE POLYETHYLENE PLASTIC FOAM AS A CUSHION BETWEEN THE UTILITIES. 31. SEE MECHANICAL DRAWINGS (WHERE APPLICABLE) FOR CONTINUATION OF SITE UTILITIES WITHIN THE BUILDING. 32. SEE ELECTRICAL DRAWINGS (WHERE APPLICABLE) FOR EXTERIOR ELECTRICAL WORK. 33. SEE LANDSCAPE DRAWINGS (WHERE APPLICABLE) FOR SITE IRRIGATION SYSTEM.