bld20110808 storm revision-E1 with attachment.pdf
From:McConnell, Jeanie
To:"Ronald Johnson"
Subject:RE: 9921 Water St. - bld20110808 revision
Date:Tuesday, September 04, 2012 10:43:28 AM
Attachments:ROW_Permit_Application.pdf
Hi Ron,
Please find attached a ROW permit application to be completed and signed by your contractor.
You can email the completed application to me if you’d like or you can drop it by our Permit
Counter anytime between 8am-4pm Monday-Friday. Once this is received I can finalize the ROW
permit and the revision will be ready for issuance. At that time a permit coordinator will contact
you to inform you of any fees due at the time of pick-up.
Regards,
Jeanie
From: Ronald Johnson \[mailto:ronmaile@comcast.net\]
Sent: Tuesday, September 04, 2012 8:52 AM
To: McConnell, Jeanie
Subject: Re: 9921 Water St.
Hi Jeanie....can I come in today to pick the permit up?
Ron
----- Original Message -----
From:McConnell, Jeanie
To:Ronald Johnson
Cc:Lambert, Jennifer
Sent: Wednesday, August 29, 2012 9:56 AM
Subject: RE: 9921 Water St.
Ron,
Once we get the drainage permit issued you can continue work on site again. We should have it
ready to go today or tomorrow.
Thanks,
Jeanie
From: Ronald Johnson \[mailto:ronmaile@comcast.net\]
Sent: Wednesday, August 29, 2012 7:49 AM
To: McConnell, Jeanie
Subject: Fw: 9921 Water St.
Jeanie....any thoughts as to my email below as to having Ben get the detention pipe
work done once the permit revision is done/ready?
Ron
----- Original Message -----
From:Ronald Johnson
To:McConnell, Jeanie
Sent: Monday, August 27, 2012 9:18 AM
Subject: Re: 9921 Water St.
Jeanie....as to continue working....could Ben start the detention pipe work that
would be on Barb's private property, but not in the ROW? Also, if PSE is having to
get permits, how long will that take to issue their permit?
Ron
----- Original Message -----
From:McConnell, Jeanie
To:Ronald Johnson
Cc:Lambert, Jennifer
Sent: Monday, August 27, 2012 9:12 AM
Subject: RE: 9921 Water St.
Hi Ron,
PSE is working to put this job together and submit permits to the City. You might be receiving
a call from Doug Usitalo or someone else from PSE to discuss the open trench work that will be
needed to relocate the gas main. We should be able to issue your permit revision in the next
couple of days, but the permit itself will not give you permission to continue work. The timing
of that will depend on when PSE can relocate the gas main.
Jeanie
From: Ronald Johnson \[mailto:ronmaile@comcast.net\]
Sent: Monday, August 27, 2012 6:27 AM
To: McConnell, Jeanie
Subject: 9921 Water St.
Jeanie....any morethoughts as to when I can get Ben back out on site to complete
the storm drain work? Is PSE getting ready to do their revision work?
Thanks
Ron Johnson
ROW PERMIT NO. : ENG___________
ISSUE DATE: ________________
RIGHT-OF-WAY CONSTRUCTION
PERMIT APPLICATION
PROJECT NAME: CONTACT:
CONTRACTOR:Phone #:
Mailing Address: Fax #:
State License #: Email #:
City Business License #: Liability Insurance Bonded
ADDRESS OR INTERSECTION OF CONSTRUCTION:
ROW WORK ASSOCIATED WITH THE FOLLOWING TYPE OF PROJECT:
Commercial Subdivision City Project Traffic Control (Only)
Multi-Family Single Family Other
EUC (PUD, VERIZON, PSE,
COMCAST, OVWSD):
Yes No
Is this permit part of a blanket permit?
ANY ASSOCIATED PERMITS?
BLD#____________ ENG#____________
DESCRIPTION OF PROPOSED WORK (Be Specific) :
_________________________________________________________________________
WAS STREET OVERLAYED WITHIN THE LAST FIVE (5) YEARS? YES NO Year:
PAVEMENT CUT: Yes NoIf yes, indicate size of cut: _________x_________
CONCRETE CUT: Yes NoIf yes, indicate size of cut: _________x_________
RIGHT-OF-WAYDURATION
AREATOTAL
CLOSURE (NUMBER OF MONTHS)
Sidewalk 48 Hrs + LF X LF SF
Alley 72 Hrs + LF X LF SF
Parking 72 Hrs + LF X LF SF
APPLICANT TO READ AND SIGN
*Traffic control and public safety shall be in accordance with City regulations as required by the City
Engineer. Every flagger must be trained as required by (WAC) 296-155-305 and must have certification
verifying completion of the required training in their possession.
*Restoration is to be in accordance with City codes and Standards. All street-cut trench work shall be
patched with asphalt or City approved material prior to the end of the workday – NO EXCEPTIONS.
Indemnity: The Applicant has signed an application which states he/she hold the City of
Edmonds harmless from injuries, damages or claims of anykind or description
whatsoever, foreseen or unforeseen, that may be made against the City of Edmonds or
any of its departments or employees,including defense costs and attorney fees by reason
of granting this permit.
I have read the above statements and understand the permit requirements and acknowledge that I must
follow all requirements in order for the permit to be valid.
SIGNATURE DATE
Contractor or Agent
NO WORK SHALL BEGIN PRIOR TO PERMIT ISSUANCE