Hello,
Please find attached a memo with a few remaining comments to be addressed. I have also
attached a ROW permit application for your contractor to complete. Please submit a signed copy
of this application so I can complete the ROW permit application.
Once the cost estimate is updated I will be able to calculate engineering inspection fees as well as
a bond amount for the project.
I also need one more full set of plans, less the Olympic View Water Sewer District plans for which
you already provided 4 sets.
Thank you!
Jeanie McConnell
Engineering Program Manager
ΓΑΔȁΖΖΐȁΏΑΑΏ ·ΐΒΒΗ
www.edmondswa.gov
From: McConnell, Jeanie
Sent: Wednesday, May 01, 2013 8:42 AM
To: Bill Ruecker (billr@baysingerpartners.com); 'Craig Harris' (craigh@aaieng.com); Norm Scheg
(norms@aaieng.com)
Subject: Walgreens - Edmonds
Good morning,
Thank you for your patience as I work my way through my projects. I wanted you to know that I
have a precon meeting out in the field this morning for another project and after that I will be
working to complete civil plan review approval for this project. I will follow up with you later today
to let you know if there is anything else we need or what the status is.
Regards,
Jeanie McConnell Engineering Program Manager
#¨³¸ ®¥ %£¬®£² Ȟ 0´¡«¨¢ 7®±ª² $¤¯ ±³¬¤³
th
ΐΑΐ Δ !µ¤´¤ .®±³§Ǿ %£¬®£² 7! ΘΗΏΑΏ
ΓΑΔȁΖΖΐȁΏΑΑΏ ·ΐΒΒΗ Ȟ www.edmondswa.gov
CITY OF EDMONDS
PLAN REVIEW COMMENTS
ENGINEERING DIVISION
(425) 771-0220
City Website: www.edmondswa.gov
DATE:March 25, 2013
TO:Norm Scheg –norms@aaieng.com
Craig Harris –craigh@aaieng.com
FROM:Jeanie McConnell, Engineering Program Manager
RE:Application#:bld20120455
Project:Chase Bank –New Bank
Project Address: 9801 Edmonds Way
Application #: bld20120925
Project: Walgreens
Project Address: 9797 Edmonds Way
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please redline plans or submit three (3) sets of revised
plans/documents with a written response to each of the items below to Marie Harrison.
City of Edmonds handouts, standard details and development code can be referenced on the City
website.
st
1Review –August 13, 2012
nd
2Review –December 6, 2012
rd
3Review –February 12, 2013
th
4
Review –March 25, 2013
th
5Review –May 1, 2013: All but the following items have been addressed. Please submit
revised plans as needed.
GENERAL
May 1, 2013 –Please revise the cost estimate as follows:
1.
a.Add rock construction entrance
b.Revise sawcut quantity to include sawcut of entire frontage.
c.Revise sidewalk demo quantity to include demo of entire sidewalk along frontage
d.Add asphalt patch within right-of-way
e.Add Type 1 CB’s to be installed within City storm easement
f.Revise number of on-site CB’s to reflect what’s shown on the plans.
bld20120455-Chase_Bank and bld20120925-Walgreens-E5.docx
Page 1of 3
g.Revise storm pipe within ROW to reflect PVC.
h.Add ductile iron storm pipe and pipe anchors.
i.Under Write-In Items, please shown drainage infrastructure in the appropriate
column.
j.Add traffic control
k.Add pavement striping
March 25, 2013 –The cost estimate is currently being reviewed and any comments will follow
these plan corrections.
February 12, 2013 –Response comments state the values have been updated, but I am not able
to find a copy of the estimate within the submittal packet. Please submit for review.
12/6/2012 -Thank you for providing a cost estimate. The estimate will be reviewed inmore
detail once the civils plans are closer to their final form. In an initial review of the document
the following corrections/information was noted:
l.Sidewalk thickness shall be 5 ½” thick (currently shown as 4” in estimate)
m.Sawcut for work within CityROW shall be included in estimate
8/13/2012 comment -Please provide an itemized engineers cost estimate, including units and
unit prices, for both on-site and off-site (right-of-way) improvements, including traffic control.
The City recommends use of the King County Site Improvement Bond Quantity Worksheet.
A bond is required to be placed for all right-of-way improvements. The amount of the bond
o
will be based on 120% of the City approved estimate for all right-of-way improvements.
The City will inform you of the appropriate bond amount after review of the cost estimate.
Bond forms can be obtained from Marie Harrison, Permit Coordinator –425-771-0220 or
Harrison@ci.edmonds.wa.us
Inspection fees for thisproject will be calculated at 2.2% of the 120% City approved
o
estimate for all improvements.
May 1, 2013 –Please submit a traffic control planalong with the attached ROW permit
2.
application.
March 25, 2013 –Response comments state a contractor will be chosen soon and TCP and Haul
Route will be provided at that time.
February 12, 2013 –Plan not yet submitted.
12/6/2012–Response letter states TCP and haul route plan will be provided by contractor once
selected for project.
8/13/2012 comment -Please submit a traffic control and haul route plan for review and
approval.
Sheet C-000–GENERAL NOTES
1.May 1, 2013 -On 4/15/2013 I received an email showing a revision to this sheet to include a
site map and haul route. While the changes were found to be acceptable, I still need hard
copies of the plans. Please submit 4 copies of this plan sheet.
Sheet C-101–FRONTAGE IMPROVEMENTPLAN
May 1, 2013 –WSDOT is requiring a WSDOT Construction Permit. Has this been obtained
yet? Plans can be redlined to include a note that no work shall begin within the ROW until
this has been secured.
Page 2of 3
March 25, 2013 –response comment states “Plans have been submitted to WSDOT, no plan review
response from them yet.
February 12, 2013 –Copy of plans approved by WSDOT notyet received.
12/6/2012 comment -The City was recently informed by WSDOT that they would like to see
improvement plans that involved removal and replacement of curb sections. Please submit the
frontage improvement plan to WSDOT for review and approval or deferral back to the City.
Sheet C-110–UTILITY PLAN
May 1, 2013 –While reviewing the cost estimate I realized the plans do not specify the
1.
size/type of storm CB’s and Manholes to be installed with the project. Please revise the
Utility Info section to include this additional information.
Please note on plans that DCDV vault shall be located entirely on private property. Please
2.
also note that vault lid shall be non-slip for pedestrian use.
Please contact me at 425-771-0220 or by e-mail at jeanie.mcconnell@edmondswa.govif you
have specific questions regarding these plan corrections.