Loading...
bld20120895-Boregson-final-correction-notice-09.16.2015.pdf CITYOFEDMONDS CORRECTION NOTICE ENGINEERING DIVISION (425) 771-0220 City Website: www.edmondswa.gov DATE:September 16, 2015PERMIT NUMBER:BLD20120895 OWNER:Scott BorgesonSITE CONTACT:Scott Borgeson th ADDRESS:7822–240St SW TYPE OF INSPECTION:FINAL INSPECTION -SFR WORK DESCRIBED BELOW HAS BEEN INSPECTED AND APPROVED APPROVED PLANS AND PERMIT JOB CARD MUST BE AVAILABLE TO INSPECTOR ON SITE CORRECTIONS LISTED BELOW MUST BE MADE BEFORE WORK CAN BE APPROVED AND/OR THE NEXT PHASEOF WORK IS STARTED. RECALL FOR INSPECTION REINSPECTION FEE MUST BE PAID PRIOR TO NEXT INSPECTION REQUEST. STOP WORK UNTIL AUTHORIZED TO CONTINUE BY CITY INSPECTOR st 1Inspection –4/3/15 nd 2Inspection –6/2/15 rd 3Inspection –7/28/15 th 4Inspection –8/11/15 th 5Inspection –9/16/15 Theonlyincomplete inspection item at this pointpertains to #16 of the previous correctionnotice: 7/28/15 –A drainage swale with drain rock (from CB1 to CB2) was required as an overflow path per the approved plans. However, as shown in the photo below, this area was covered with crushed rock with fines. Please correct to be consistent with the approved plans. 08/11/2015 –Applicants response to the City is as follows: Rock wastemporarily placed over filter fabric over the top of the catch basin in order to facilitate better access to the rear yard for delivery of new landscaping plantsthat is underway.During this dry season, the additional overflow capacity of the second catch basin was not deemed necessary.Since this was re-inspected by the City during the last inspection and we were told it was approved, we expected that we could then place this temporary rock over the CB so that other work could be more easily accomplished.We never expected that the City inspectors would re-inspect every aspect of the property every time they come out.It was our understanding that the City had no further requests or inspection needs associated with the improvements adjacent to the house and that the inspector's focus would be on the frontage improvements. In order to address your concern, the catch basin has been re-exposed andthe rock that was temporarily placed over it has been removed. The stormwatermanagement system shall be maintained as originally approved and shall not be modified to be covered with rock as shown in the following photos.As noted, the basin was uncovered for the latest inspection. Please revise drainage swale to be consistent with the approved planswhich state “Swale to be 6” +/-with 3:1 maximum side slopes and 1% minimum flow path slope. Place 2”minus washed rock, 3’ wide, over mirafi 140-N fabric”. Please also note, additional impervious surface area shall not be added to the site. 9/16/2015 – As shown below, the washed rock does not surround the catch basin per the approved plans. The washed rock will prevent landscaping debris from entering/clogging the stormwater system and shall be installed as designed. For inspection scheduling call 425-771-0220 x1326. Page 2of 2