bld20120952_behar-1.doc
City of Edmonds
TH
121 5 AVENUE NORTH • EDMONDS, WA 98020 • (425) 771-0220 FAX(425) 771-0221
Website: www.ci.edmonds.wa.us
PUBLIC WORKS DEPARTMENT
Engineering Division
Plan Review Corrections
Plan Check : Date:
# BLD20120952 November 1, 2012
Project Name/Address:
Behar Co Plumbing 22001 Highway 99
Contact Person/Address/Fax:
Kitty Singh 206-783-0334 kitty@sismech.com
Reviewer: JoAnne ZulaufDivision:Engineering
During review of the subject submittal, it was found that the following information, corrections, or
clarifications would need to be addressed. All Handouts and Standard Details referred to in these
comments can be accessed at our website: www.edmondswa.gov by choosing the Government tab and
Public Works| Engineering under Departments:
Please Note: Building Handouts do not include updated Engineering Division Requirements. Refer to
Engineering Handouts for all Engineering Requirements.
1. Please provide a site plan showing the new utilities to be installed (water, sewer, storm)
from the building to the connections at the property line or to city utilities in the right of way
if a new connection will be made. Show all existing utility locations.
all
2. Call out on plan length, size and material of pipe to be installed.
3. Show the rpba location.
4. Provide a traffic control plan for closing sidewalks or road if necessary for this work.
5. Where will the proposed downspouts be directed? Show and label where they will be
added. Show and label all tightline runs. Show all new connection to catch basins or
other structures. All connections shall include invert elevations.
6. Sanitary sewer line for commercial use is required to use 6” conveyance pipe. It will be
necessary to replace existing 4” pipe.
7. Call out size and location of sewer clean outs. Clean outs are required at the building,
every 100 ft, and at the property line. All clean outs in drivable areas and at property line
shall have a 12” cast iron lamphole cover with ½” hexbolts. Note on plans.
8. Add and label on plan where the hose bibs will be installed. Show connecting pipe if
exterior connection.
9. Pipe for grease interceptor conveyance shall be 6”.
DATE FAXED/E-MAILED 7/2/2017 PAGE ___ OF __
12
Please resubmit 3 copies of the revised plans/documents to a Development Services Coordinator. Please
contact me at 425-771-0220 if you have specific questions regarding these plan corrections.
DATE FAXED/E-MAILED 7/2/2017 PAGE ___ OF __
22