Engineering Plan Review Comments
PermitApplication:Date:
#BLD20131278 December 26, 2013
nd
Project Name/Address:
Ardsley –1026–2Ave S
Contact Person/Address, Fax or E-mail:
Reviewer: JENNIFERLAMBERTDivision:
ENGINEERING
During review of the subject submittal, it was found that the following information, corrections, or
clarifications would need to be addressed. All Handouts referred to in these comments can be accessed at
our website: www.ci.edmonds.wa.usunder City Government / Development Services Department /
Engineering Division then scroll down to Handouts:
GENERAL
1)Please label the plan sheets (i.e. Site Plan, Stormwater/UtilityPlan, TESC Plan, etc.) accordingly.
a.Please have the impervious surfacechart on the Stormwater/Utility Plan.
b.Please note that you may combine plan sheets (i.e. Stormwater/Utility/TESC…etc.) to one sheet
as long as the plan sheet remains readable.
2)Please reference the recording number for theretaining wall &private drainageeasements.
SEWER
3)Per the approved civils and topography it appears that the sewer will need to be pumped to the manhole
as shown on the civils.
a.Please show the pumpon the plans and refer to City Standard E6.9.
b.Please refer to the handout #E62 for engineering requirementsfor sewer pumps. Please note that
the City does allow E-One pumps. If the E-One pump is used a pre-design report is not required.
DATE E-MAILED12/27/2013PAGE (1)
City of EdmondsBLD20131278
TH
121 5AVENUE NORTHEDMONDS, WA 98020 • (425) 771-0220 FAX (425) 771-0221
Website: www.ci.edmonds.wa.us
PUBLIC WORK DEPARTMENT
Planning • Building • Engineering
Engineering Plan Review Comments
STORM
1)Please bold the stubs to theinfiltration system, since the connections will be madeduring the
construction of the single family.
2)Please bold and callout the permeable driveway since the driveway will be installed during the
construction of the single family.
3)Please show the permeable pavement detail and associated notes that was approved with the short plat
civils on the plans.
4)Please remove the driveway swale and CB. Since the driveway will be permeable this is not needed.
5)Please add a note that if the driveway subgrade slope exceeds 2%, check dams will be required.
6)Please note that the infiltration system is designed to allow for the collection of the flows from the
footing drains. You may show either a separate drywell or show the footing drains connected to the
infiltration system.
Please resubmit 3 copies of the revised plansand associated documents with a written response to each
item to a Permit Coordinator. Please contact me at 425-771-0220ext 1321or by e-mail at
jennifer.lambert@ci.edmonds.wa.usif you have specific questions regarding these plan corrections.
DATE E-MAILED12/27/2013PAGE (2)