Loading...
bld20140074-Post Office-E2-revised shoring.pdf CITY OF EDMONDS PLAN REVIEW COMMENTS ENGINEERING DIVISION (425) 771-0220 City Website: www.edmondswa.gov DATE:May16, 2014 TO:Scott Boyer scottb@mithun.com FROM:Jeanie McConnell, Engineering Program Manager Jerry Shuster, Stormwater Engineer Program Manager RE:Application#:bld20140074 Project:Post Office nd Project Address: 130 2Ave N During review of the above noted application, it was found that the following information, corrections, or clarifications are needed. Please redline plans or submit three (3) sets of revised plans/documents with a written response to each of the items below to a permit coordinator. City of Edmonds handouts, standard details and development code can be referenced on the City website. Comments 1 –March 11, 2014 Comments 1 REVISED –March 12, 2014 Revised to include striping and signage comments from traffic engineer. An additional comment about driveway slope has also been included. Refer to C3.01 – Paving and Utilities section below. Comments 2 –May 7, 2014–REVISED Comments 2 -May 16, 2014–revised to include additional shoring comments GENERAL 5/7/2014 –Thank you for providing a cost estimate. A general review of the estimate has 1. been completed and a more refined review will take place with the final plan submittal. The following revisions have been noted at this time: ADD: Filter socks a. REVISE: sidewalk depth shall be 5 ½” in general and 6” at driveway locations. b. ADD: Crosswalk striping c. ADD: Water utility system improvements d. ADD: Sewer utility system improvements e. ADD: Tree grates f. ADD: Temporary shoring g. ADD: Signage within the ROW h. bld20140074-Post Office-E2-plus shoring.docx Page 1of 8 ADD: Curb ramps with truncated domes i. 3/11/2014 comment -Please provide an itemized engineers cost estimate, including units and unit prices, for both on-site and off-site (right-of-way) improvements, including traffic control. Please use the King County Site Improvement Bond Quantity Worksheet. A bond is required to be placed for all right-of-wayand stormwater improvements as well as o erosion control. The amount of the bond will be based on 120% of theCity approved estimate of the improvement cost. The City will inform you of the appropriate bond amount after review of the cost estimate. Bond forms can be obtained fromPermit Coordinators Linda Thornquist or Kristin Johns at 425-771-0220 or by email at linda.thornquist@edmondswa.govor Kristin.johns@edmondswa.gov Inspection fees for this project will be calculated at 3.3% of the 120% City approved o estimate for all improvements. 5/7/2014 –Thank you for submitting a haul route plan. Please incorporate this plan into 2. the civil plan set. Please submit a traffic control plan. 3/11/2014 comment -Please submit a traffic control and haul route plan for review and approval. Individual plans shall be provided for all elements of work to be completed both in nd 2Ave and Bell Street. 5/7/2014 –Response comments state there were no further changes to the traffic analysis. 3. The traffic analysis, however, states “the existing 8,632sf US Post Office will be retained with the proposed development. No new trips are forecast to be generated by the existing post office land use.” There is an existing Post Office on the parcel, but the Post Office will be relocating to the new building and the square footage of the new Post Office space will be reduced. I had discussions with Bertrand Hauss, City Traffic Engineer, about how to calculate traffic impact fees for the Post Office space given the use will be relocating on the same property and therefore will not be a “new use” on the property. If the traffic analysis discussed the relocation of the Post Office use upon construction completion, as well as the reduction in the square footage of the space, this would clearly identify a no net increase with regards to impact and traffic impact fees would not be required for the new Post Office space. If this is not outlined though, then it would look as though the parcel had two commercial Post Office uses and fees would need to be paid for the new space. Please revise and resubmit the analysis. 3/11/2014 comment -Please submit 3 copies of an updated traffic impact analysis that includes both office space and apartments consistent with the building permit submittal. 5/7/2014 –Revision clouds can be removed from the plan set for the final print. 4. A1.01 –SITE PLAN 5/7/2014 –Thank you for submitting an encroachment permit. Please revise or note the 1. following: Revise application and agreement to include landscape irrigation within the ROW, a. flag pole, and any other features proposed for encroachment into the ROW. Please note that the permit details for the temporary shoring proposed within the b. City ROW are still being discussed within our office. The encroachment permit may need to include the shoring and the City of Seattle sample indemnification may be included as an addendum to the encroachment agreement. I will follow-up with you as soon as some of these details are ironed out. Page 2of 8 Please also note that any documents to be provided to the County for recording c. should be completed in black ink. Please revise Wall Section A-A detail to include a measurement from the steel d. canopy to the finished grade of the sidewalk. 3/11/2014 comment -Plans indicate a steel canopy will encroach into the City right-of-way. A separate encroachment permit will be required for any encroachments. Please refer to City Handout E26. ok 2. ok 3. L1.01 –(LANDSCAPE) MATERIALS & LAYOUT PLAN 5/7/2014 –Thank you for providing a detail on sheet L3.02. The detail does not include a 1. stamp by a structural engineer. As the flag pole will be located in the City ROW, please move the detail to the civil plan set and include design/approval for the concrete base by a structural engineer. Please consider installing a flag pole arm on the building instead of placing the pole within the sidewalk. 3/11/2014 comment -Plans state “Flag Pole -see specifications”. Specifications have not been provided in the plan set. Please provide. ok 2. ok 3. L2.01 –(LANDSCAPE) PLANTING PLAN ok 1. ok 2. 5/7/2014 –Response comments state that street tree has been revised to avoid conflict with 3. power facilities. In comparing the civilplans and the landscape plan there still appears to be a conflict. Please add a general planting note regarding utility separation and tree placement. 3/11/2014 comment -Power facilities are shown on the civil construction plans at the northeast corner of the property. Please confirm the proposed Street Tree location is not in conflict with these facilities. ok 4. ok 5. ok 6. SHORING 1.5/16/2014 –In addition to the comments provided below, please respond to thefollowing: a.On Sheet SH3.0, SH3.1, and SH3.3 please note the proposed elevation of the soil nail or ground anchor at the location in which it crosses any utility. b.On Sheet SH4.0Add a general note to this sheet that statesa minimum 3’clearance between nail/anchor and utility shall be provided. c.Please provide a cost estimate for bonding purposes using the attachedbond form. This form is similar to that used by the City of Seattle.The sidewalk repair calculation shall be for that portion of thesidewalk not currently shown under the bond quantity worksheet previously submittedto the City. Page 3of 8 d.City staff is currently workingwith our City attorneyto finalize the encroachment/indemnificationforms. e.Add notes to the civil plans requiring the sewer main to be TV’d before and after installation of thetemporary shoring.In addition, the plans shall callout the requirement for flows within the sewer manholes to bemonitored during construction of the temp shoringwall to verify there is no introduction of debris or grout,which would indicate a nail or anchor has punctured the sewer main ora lateral. 5/7/2014 –The City has reviewed the materials submitted. Please refer to note 1 under A1.01 site plan aboveand respond to the following: Add notes to civil plan set and structural details on SH4.0 requiring utilities to be a. potholed prior to constructionof temp shoring walls. Add notes to civil plan set noting the requirement for asbuilts of the shoring system. b. Add notes to civil plan set noting the requirement for structural special inspections c. during construction of the walls. Add details and notes to civil plan set similarto City of Seattle shoring example, d. which indicates soldier pile wallremoval to 4-feet below grade. Revise shoring plan sheets to include wall profiles that show the elevation of nails e. and anchors at utility crossings. Plans currently indicate elevations at the wall. FYI –City staff is currently working through the indemnification process. f. Additional information or notes on plans may be required. 3/11/2014 comment -A conceptual shoring design was discussed with the City in October 2013. nd It was conveyed that the shoring systems had the potential to encroach into the alley and 2 Ave, but not on Bell Street. A soldier pile wall with tie backs was proposed for the alley and a nd cantilever wall was proposed on 2Ave. The City asked about the possible elimination of tie nd backs, potential utility conflicts and construction of a soldier pile wall on 2instead of the cantilever wall. It was stated that the City would be looking for a proposal that provided as minimal impact as possible. The current proposal is for a soldier pile wall with tie backs that nd extend half way into 2Ave, a portion of the way into Bell Street, and across the entire alley. g.Please provide written comments as to why the proposed design was selected. h.Provide any information you may have regarding City of Seattle procedures for similar proposals. i.Provide a summary of construction impacts to the surrounding area during construction of the walls. j.Show temporary impacts, including street and sidewalk closures, in the civil plan set. k.Provide information regarding the final state of the wall once the temporary use is no longer needed. How will the wall be left? Does the proposal include cutting the wall down to a certain height at completion of basement and ground floor construction? 2.Refer to separate structural review comments provided by Beck & Associates and dated February 9, 2014. STORMWATER REPORT The following comments are provided from Jerry Shuster, Stormwater Engineer. Please contact Jerry directly at 425-771-0220 or by email at jerry.shuster@edmondswa.govwith any specific questions you may have regarding these comments. Page 4of 8 5/7/2014 –All comments related to the Stormwater report have been adequately addressed. With regards to Site Classification/Minimum requirements –the project is still shown to be categorized as a Large Site project, however, the logic used with phasing and the decision to not submit an NOI changes this project to a Category 2 Small Site. Inaddition, page 10 includes a Construction Site Sediment Transport Potential Worksheet that is no longer needed if the project is categorized as a Cat 2 Small Site. Please revise the report appropriately. SHEET C1.01 –DEMOLTION TESC 1.ok 2.ok 5/7/2014 –Doug Spee has now indicated that the electrical lines will remain overhead. 3. Please revise notes on plans accordingly. A general statement could be made that any improvements to existing electrical will be done under separate permit. 3/11/2014 comment -It is understood that the electrical lines through the alley will be placed underground. Please add notes to this effect on the plans and indicate work will be done under a separate permit. ok 4. ok 5. 5/7/2014 –Thank you for adding this callout. I did not include in my last comments the 6. need to cut and cap the existing water service line at the main once this service is no longer needed and prior to final site restoration. Please add these notes to the plans. 3/11/2014 comment -Please show the location of the existing water meter to be used for temporary water supply during construction. 5/7/2014 –Thank you for the clarification. Will there be any conflicts between the utility 7. poles and the proposed shoring system in the alley? Please confirm and add notes for PUD coordination as appropriate. 3/11/2014 comment -Plans indicate “relocate UP” and “Protect Ex. UP”. Please clarify what UP refers to. ok 8. ok 9. ok 10. ok 11. SHEET C2.01 –GRADING & DRAINAGE ok 1. ok 2. ok 3. ok 4. 5/7/2014 –Plans indicate floor drains are to connect to internal plumbing. Please confirm 5. what is meant by internal plumbing. Will these areas flow to sanitary sewer or the storm system? If these areas will receive stormwater flows then they should be connected to the storm system. In addition, please clarify the note that states “connect FD to storm drain pump basins system per plumbing designer”. Will footing/foundation drains be connected to the outfall of the storm system? Page 5of 8 SHEET C3.01 –PAVING & UTILITIES ok 1. ok 2. ok 3. ok 4. ok 5. ok 6. ok 7. ok 8. ok 9. 5/7/2014 –Thank you for providing a detail in the landscape plans. Please refer to note 1 10. under L1.01. 3/11/2014 comment -Installation of a flag polehas been shown on this plan and reference made to the LA dwgs. The Landscape drawings, however, do not provide details for the flag pole. Please include details in the plan set, including distance from curb and distance from building, so it can be determined if the proposed location is acceptable to the City. ok 11. ok 12. ok 13. 5/7/2014 –Thank you for adding a note to this effect. Please add an additional leader so 14. this note points to the domestic and fire line connections as well. 3/11/2014 comment -At the proposed point of connection to the City water main it appears as though gas main may be in conflict. Please add notes to the plans requiring potholing in this area to confirm gas main location and provide opportunity to deal with any potential conflicts ahead of actual main line tap. ok 15. ok 16. ok 17. 5/7/2014 –My typo … please revise to say EZ 2 valve. Please provide additional notes 18. requiring the gas main to be potholed prior to EZ valve installation to ensure sufficient space exists for equipment setup, etc. 3/11/2014 comment -Instead of installing a valve cluster and the fire line connection to the City main, an EZ-valve 2 inline valve insertion will be required. Staff is currently making a determination as to where this should be located, but it will likely be just north of Main Street. ok 19. ok 20. ok 21. ok 22. ok 23. ok 24. 25.ok –thank you for the clarification 26.5/7/2014 –Please add a note that the loading zone parking signs on Main Street, in front of the existing Post Office, shall be replaced with the 3-hr parking signage once the Post Officerelocates to their new space. Page 6of 8 nd 27.5/7/2014 –Near the NW corner of the building, on 2Ave, a 3-hr parking sign is shown to the north of a flower basket post. Please swap these two features so the hanging basket does not block the parking sign. nd 28.5/7/2014 –Please add notes that the existing crosswalks and stopbars on 2at Main Street and Bell Streets shall be re-established consistent with City standard detail E3.2. nd 29.5/7/2014 –Please confirm the proposed street trees on 2Ave are not in conflict with the building canopy. 30.5/7/2014 –At proposed curb ramp/landscape bulb out -add reference to detail 8 on Sheet C4.04. nd 31.5/7/2014 –Note sidewalk width on 2Ave. 32.5/7/2014 –Please show the inline valve that will be installed at the fire hydrant line. SHEET C4.01 –SITE NOTES & DETAILS ok 1. ok 2. ok 3. ok 4. SHEET C4.02 –SITE NOTES & DETAILS ok 1. SHEET C4.03–SITE NOTES & DETAILS ok 1. SHEET C4.04–SITE NOTES & DETAILS ok 1. ok 2. ok 3. ok 4. ok 5. SHEET C4.05–DETENTION DETAILS & STORM DRAIN MAIN EXTENSION ok 1. 5/7/2014 –Thank you for removing the shear gate from the detail. Please also remove the 2. reference in the plan view of this structure. 3/11/2014 comment -Detail 6 -The City no longer accepts shear gates as our standard.Use Standard DetailE5.4 from http://edmondswa.gov/services/permits-development/handouts- forms/services-permits-std-details-main-page-menu/services-std-details-storm-drainage-section- 5-menu.html. The screen is OK to use in the detail. ok 3. 5/7/2014 –Detail 7 –Please revise 10’ max from property line to detention pipe to say 10’ 4. minimum. Page 7of 8 Please contact me at 425-771-0220 or by e-mail at jeanie.mcconnell@edmondswa.govif you have specific questions regarding these plan corrections. Page 8of 8