bld20140415_jacobsen-1.docx City of Edmonds TH 121 5 AVENUE NORTH • EDMONDS, WA 98020 • (425) 771-0220 FAX(425) 771-0221 Website: www.ci.edmonds.wa.us PUBLIC WORKS DEPARTMENT Engineering Division Plan Review Corrections Plan Check : Date: # BLD20140415 June 6, 2014 Project Name/Address: Jacobsen New Single Family Residence 741 Hanna Park Ln Contact Person/Address/Fax: Bryan Krannitz bryan@krannitzgehl.com Reviewer: JoAnne ZulaufDivision:Engineering During review of the subject submittal, it was found that the following information, corrections, or clarifications would need to be addressed. All Handouts and Standard Details referred to in these comments can be accessed at our website: www.edmondswa.gov by choosing the Government tab and Public Works| Engineering under Departments: Please Note: Building Handouts do not include updated Engineering Division Requirements. Refer to Engineering Handouts for all Engineering Requirements. Plot Plan: 1. Please remove all existing conditions that will not remain after construction from this plan. 2. The plot plan shall show the location of all the utilities (water, sewer, electric, etc.) and stormwater system but does not need to include the details (length, size, etc.). 3. Add note to plan “All utilities will be installed underground.” 4. Please note the location of the nearest fire hydrant on plan and note the distance between the property line and the hydrant. Stormwater 5. Please revise impervious surface information. See comment # 1 under . Utilities: Please provide water, sewer and dry utility information and construction information in the civil plans. Stormwater Plan: 1. Please revise the site classification and the impervious surface map as follows; a. All impervious surface on this project is “new”. There is no impervious surface that meets the definition for “replaced”. Please see handout E72. b. The geo report mentions a possible small structure to be constructed in the east area of the property. Please add to the impervious surface calculations and the plans if this to be constructed. c. Unless specifically approved by the geotech in the form of an addendum, dispersion shall not be approved as a mitigation measure for runoff. The Geospectrum DATE FAXED/E-MAILED 7/2/2017 PAGE ___ OF __ 12 Consultant, Inc. report dated December 4, 2013 states on page 11; “no uncontrolled water flow should be allowed on the site”. All impervious surface runoff shall be mitigated using conventional stormwater management techniques. 2. Please replace or revise current control manhole for detention to be consistent with City Standard Detail E5.3 and add control structure Detail E5.4. 3. Remove sheer gate detail. (see E5.3 for more information) 4. Remove all references to Galvanized Steel piping. This is not an approved pipe material for construction of detention systems. See E72A for more information. 5. Please change footing drain line type to “fd”. Please change clean out labels to reflect footing drains. 6. Please address Geospectrum requirement for existing storm drain. See page 11 of report. 7. Note size, length and material of all tightline connections from house to detention system. All pipe located under driving surfaces shall be sdr 35 or better, or if under 1 ½’ of cover then shall be ductile iron. 8. Please replace or revise “Construction Sequence” to include the information on the Sample Construction Sequence attached. Please replace all instances of “town” with “city”. 9. Please provide a de-watering plan. 10. SWPPP # 11 not adequately addressed. Please add information regarding timing of inspections, storm event response and wet weather inspections and responsibilities for tesc. Sheet C2: Erosion Control: 1. Please show temporary construction entrance and location of stockpile(s) on plan. 2. Please review and revise Site Grading and T.E.S.C. notes. Many are not consistent with the geotechnical report recommendations. Attached are some sample grading and tesc notes that can be edited to work for this site. 3. “Cover Methods” and “Temporary Cover” are the same and can be combined into one. 4. Number 6 SWPPP is shown next to “Cover Methods”. There is no reference to cut and fill slopes. That information is under “Maintenance of Siltration Barriers”. 5. The heading “Maintenance of Siltration Barriers” does not describe all the information following it. 6. Add note to plans: “All disturbed areas on and off site shall be compost amended to meet requirements of BMP T5.13 in the Stormwater Manual, Vol V, Chapter 5. 7. Top Soil Preservation Notes: How does this work with the above (#6) requirement? Please clarify. 8. The clearing limits are shown along the entire property line. Please review the geotechnical report and adjust those lines according to the recommendations in the report. Also, Low Impact development encourages preservation of as much existing pervious area as possible. 9. Please provide detail showing how driveway will be constructed to meet the geotechnical report requirements on page # 10 Pavement and Slab Subgrade Preparation. DATE FAXED/E-MAILED 7/2/2017 PAGE ___ OF __ 22