CITY OF EDMONDS
PLAN REVIEW COMMENTS
ENGINEERING DIVISION
(425) 771-0220
City Website: www.edmondswa.gov
DATE: May 28, 2015
TO: Jeff Yates
Jeff@RJDevelopmentservices.com
FROM: JoAnne Zulauf, Engineering Technician
RE: Application #: bld20150032 – Second Review
Project: Edmonds Memory Care
nd
Project Address: 21006 72 St SW
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please redline plans or submit three (3) sets of revised
plans/documents with a written response to each of the items below to a permit coordinator.
City of Edmonds handouts, standard details and development code can be referenced on the City
website.
GENERAL
1. Received Bond Worksheet. There are a few discrepancies between the plans and the
worksheet. Also water and sewer were not included. I have attached a copy of the worksheet
with the changes in red. Please review and correct as needed.
A1.01 – SITE PLAN -
Completed
STORMWATER REPORT
Technical Information Report (12/31/2014)
8. 5/28/15 The WWHM2012 modeling does not represent what is in the drawings – The bottom
orifice and riser pipes are larger in the drawings and vault dimensions are off. Remodel using the
Appendix D – The modeling uses an orifice size less than 0.5
information from the drawings.
inches. As stated in Section 4.7.4. of the ESCS, the minimum orifice size is 0.5 inches due to
clogging concerns. Always be sure and download the latest version of WWHM2012, the
program has MANY bugs. The Clear Creek Solution has the latest free downloads available
(http://www.clearcreeksolutions.com/SearchResults.asp?Cat=17 ). While this website says
the latest update is 8/18/2014, it is not. The latest they have on their website was actually
updated 01/28/2015 (see change log on the website).
bld20150032-Memory Care-2 Page 1 of 2
Plan Sheets
9. 5/28/15 It does not appear that there are risers 50 feet apart in each compartment of the
The vault needs access manholes every 50 ft. for
vault. This is required for maintenance access.
maintenance.
10. 5/28/15 Control Structure Detail – The riser is modeled as an 18 inch pipe, The detail shows 12
inch pipe, please reconcile. Also, this detail shows a shear gate which is in conflict with City of
Edmonds standard detail E5.4 on Sheet 8.0. Having two details is confusing to a contractor. Use
Detail E5.4. We do have this detail in AutoCAD format for addition of elevations on our website
(http://www.edmondswa.gov/engineering-standards/section-5-storm-drainage.html ).
The east inlet to the vault have a invert elevation of 397.0, only 1 foot above the bottom of the live
storage. The pipe also has a 10.71% slope. Making the inlet at a higher elevation would reduce
backup in the pipe.
The Flow Control Structure detail on Sheet C8.0 needs elevations for the office(s), top of the
riser and the notch match that the modeling so it can be constructed properly. Also, make
the notch a rectangular notch to match the modeling.
Please provide structural calculations for the concrete vault structure. Review
11. 5/28/15
will be sent out for third party review. Cost will be pass through. The structural design of
the vault has (not) been sent out for peer review. Comments will be forwarded when review
is complete.
SHEET C1.0 – SITE PLAN
- Completed
SHEET C3.0 – TESC
-Completed
SHEET C3.1 – TESC NOTES AND DETAILS
- Completed
SHEET C5.0 – GRADING, DRAINAGE PLANS & VAULT SECTIONS
29. 5/28/15 See #11 above. Please provide structural calculations for the stormwater vault.
A structural review of the vault shall be sent out for peer review. Consultant fee shall be
pass through.
SHEET C7.0 – SEWER & WATER PLAN
- Completed
Please contact me at 425-771-0220 or by e-mail at joanne.zulauf@edmondswa.gov if you have
specific questions regarding these plan corrections. Jerry Shuster, can be reached at
jerry.shuster@edmondswa.gov, for any stormwater questions.
Page 2 of 2