Mike,
I am reviewing the resubmittal for the Engineering Division. I just have one question. The impervious surface amounts differ between the civils and the drainage
report.
On sheet C1 under Project Data:
Impervious 5424 sf
Eff Impervious 4468 sf
Pervious 957 sf
Off site Asphalt 533 sf
CSP Drainage Report:
Impervious 5513 sf
Eff Impervious 4557 sf
Pervious 956 sf
Off site Asphalt 622 sf
Site Plan matches the Drainage Report
Please make changes so all the numbers are consistent between the report and the two plans
Resubmit corrected sheets.
Thank you.