Loading...
BLD20161347_ENG2.pdf CITY OF EDMONDS PLAN REVIEW COMMENTS ENGINEERING DIVISION (425) 771-0220 City Website: www.edmondswa.gov June 5, 2017 DATE: December 30, 2016 TO:Jeff Geers JEFFGEERS@OUTLOOK.COM Mitch Boyd, Stantec Consulting Services FROM: Mitch.Boyd@edmondswa.gov Jennifer Lambert Jennifer.lambert@edmondswa.gov RE:Application #: BLD20161347 Project: Geers-Single Family Residence nd Project Address: 9340-232St SW(Lot 3) During review of the above noted application, it was found that the following information, corrections,or clarifications are needed. Reviews by other divisions, such as Planning, Building, or Fire may result in additional comments. Please redline plans or submit three (3) sets of revised plans/documents with a written response to each of the items below to a permit coordinator. nd Resubmittals can be made at the Development Services Department on the 2floor of City Hall. Permit Center hours are M, T, Th & F from 8am-4:30pmand on Wednesdays from 8:30am-noon. City of Edmonds handouts, standard details and development code can be referenced on the City website. All comments in bold were created on June 5, 2017. STORM, SEWER, WATER, ELECTRIC & GASEXHIBIT OK–Please add “For Reference Only” underneath “Combined Utility Schematic”. The 1) combined utility schematic is not being approved under this permit as it was approved under the short plat permit. What is the purpose of this sheet? a.If this sheet is intended to show the utilities that havebeen installed with the short plat, please provide an asbuilt drawing. A typical asbuilt, shows invert elevations for all pipes at each catch basin, pipe material, size, depth, invert elevations at cleanouts, clearly shows easements, etc. Please note that the City shows that no inspections have been completed for this short plat. b.If this sheet is intended to show the utilities approved with the short plat, please provide the approved plan sheet for theshortplat as a reference sheet. The Overall Site Plan detail provided on A0 could be used as the reference sheet for the utilities for the shortplat. If you use the Overall Site Plan, please bold out the utilities more and maybe lighten the properties lines, this might make this plan a little clearer as to what was or will be installed with the short plat. SITE PLAN (A0 OF A9) The comment below was not addressed, please address. Please coordinate within the project 1) team if required. Clearly distinguish between what utilities were or will be installed under the short plat and what utilities will be installed with the single family residence(i.e. bolder lines). The comment below was not addressed, please address. Please coordinate within the project 2) team if required. Please add a note that final construction approval must be obtained by Olympic View Water and Sewer District, prior to final construction approval for the single family residence. The comment below was not addressed, please address. Please coordinate within the project 3) team if required. Please add a note that the dry utilities (power, phone, cable, gas, etc.) final approved location will be reviewed and approved under a separate right-of-way permit obtained by the utility companies. A minimum of 3’ of horizontal separationand 1’ vertical separationbetween the storm, sewer, and waterand any of the dry utilities (i.e. power, phone, gas, cable, etc.)is required. The comment below was not addressed, please address. Please coordinate within the project 4) team if required. Please remove the rockery detail or the City of Edmonds title block from the plans. The City will only inspect the rockery to make sure that rockery is placed such that it meets Edmonds City Code and Community Development Code, 18.40.020. EROSION CONTROL OK 1) Show the filter fence and reference the Edmonds Standard Detail E1.1. OK 2) Add a note that the filter socks willbe added to catch basins per Edmonds Standard Detail E1.3 as needed, downstream from the site and areas where debris may enter the City stormwater system from the construction/vehicles leaving the site. OK 3) Show the construction entrance and reference the Edmonds Standard Detail E1.2. Please address the comment below. 4) Show protection fencing around the stormwater management system. There should not be any vehicles/construction equipment driven over this area, stockpilesshall not be placed over this area, etc. OK 5) Please add a note that all disturbed soils shall be compost amended. STORM Page 2of 5 OK 1) Please show the stormwater management system as approvedand shownunder the short plat (i.e. quarry spalls, overflow path, etc.). a. What are the rectangles shown over the stormwater management system location? Please note that any deviations from the approved system will need to be reviewed and approved under the short plat. OK 2) Label the material and size of all pipes. OK 3) Show the invert elevations at the home and for all new pipe connections to catch basins. This is to make sure that there is slope on the pipe and proper coverage (2’ of coverage under driveable areas, and 1’ of cover in landscape areas). a.Please show a minimum of 2’ of cover under driveable surfaces. If only 1’ of cover can be obtained, please show ductile iron or PVC 900. OK 4) Please show that there is a minimum of 3’of horizontal separation and 1’ vertical separation between the dry utilities (power, phone, cable, gas, etc.) and water. OK 5) Show how the surface water runoff from the driveway will be collected and discharged to the onsite stormwater management system (i.e. directional flow arrows,trench drain, curbing,etc.). The drywell is of an acceptable design to mitigate footing drains. However, the current drywell 6) location is at a higher grade than the proposed footing drains. Please provide the footing drain IE and the drywell intake IE and, if necessary, relocate the drywell downgrade (south). Show where the footing drains will discharge to (i.e. drywell). Typically the footing drains cannot discharge to the onsite stormwater management system unless the system was designed for the allowance of the footing drains. Add a callout to the plans to connect roof drains to the existing stormwater stub. 7) Have the plans show all SD lines that are existing and/or under the short plat permit 8) (PLN20140045) as shaded back. Have all SD lines that are proposed under the SFR permit shown as bold. This will help clarify which SD lines are being installed under the SFR permit. A Stormwater Covenant is required to be recorded against the property based on the 9) proposed stormwater facilities for the project. Please complete the covenant, including notarization and any required exhibits and submit to the city. The document must be complete, but will not be recorded prior to permit issuance. Prior to construction final location of facilities are to be verified (by field inspection and asbuilt) and then the covenant will be recorded. WATER Please distinguish between what is proposed to be installed under the SFR permit and what is 1) or will be installed with the short plat. The SFR water service line and the Short Plat water system have the same linetype. Please distinguish the service lines, if applicable. Page 3of 5 Please include the pipe material, size, and note tracer wire to be installed on the water service line. Although this site is within Olympic View Water Sewer district, the City is required to ensure compliance with the plumbing code. a.Please clearly distinguish between what is proposed to be installed with the single family residence and what is or will be installed with the short plat. b.Please label the pipe material, size, and note tracer wire to be installed on the water service line. OK 2) Pleasekeep in mindthat a minimum of 10’ of horizontal separation between the water and the sewer linesis required.If the water crosses the side sewer, the water shall be placed above the sewer at a minimum of 18” of vertical separation. OK 3) Please show that there is a minimum of 3’ of horizontal separation and 1’ vertical separation between the dry utilities (power, phone, cable, gas, etc.) and water. SEWER Per the plans it appears that the entire sewer line will be installed under the SFR permit. Per 1) the short plat permit, the sewer appears to beasewerinstalled under the short plat permit. Please show the connection point between the sewer service to be installed underthe SFR permit and the sewer thatwas installedperthe short plat permit. Ensure the SFR and short platsewers are of a different linetype to clearly differentiate the two systems.Add a callout indicating the transition point between SFR sewer and short platsewer. Please show a cleanout within 2’ of the structure. Please label the pipe material and size on the plans. Although this site is within Olympic View Water Sewer district, the City requests the following information to ensure the plans are consistent and feasible with the requirements set forth by Olympic View Water Sewer District and theCity Standards. a.Please clearly distinguish between what is proposed to be installed with the single family residence and what is or will be installed with the subdivision. b.Show a cleanout at the edge of easement and within 2’ of the structure. c.Please show the invert elevations at the stub and the house so that slope (minimum of 2%) and coverage (minimum 2’) can be verified. d.Label the pipe material and size. Add a note to the plans that a minimum of 1.0’ of vertical separation is required between the 2) crown of the existing sewer and theIE of theproposed SD. Page 4of 5 Please show that there is a minimum of 3’ of horizontal separation and 1’ vertical separation between the dry utilities (power, phone, cable, gas, etc.) and sewer. DRY UTILITIES OK 1) Please adda note that all utilities shall go underground. OK 2) Please show the dry utilities to the house. OK 3) Please show that the dry utilities (power, phone, cable, gas, etc.) have a minimum of 3’ of horizontal separation and 1’ vertical separation between the storm, sewer, and water. Page 5of 5