Bld20161520 Email to applicant.pdfKevin Zweber
From: Kevin Zweber
Sent: Thursday, January 19, 2017 11:55 AM
To: 'HLIU@WAREMALCOMB.COM'
Subject: BId20161520, 22019 Hwy 99, Edmonds -Pad Building
In reference to the above project, the requirement for an automatic fire sprinkler system is not reflected on the
submission. The occupant load for tenant space 1 (A2) is indicated to be 148, which requires an automatic fire sprinkler
in accordance with IFC 903.2.1.2. Under the current submission showing a non -separated use, a automatic fire sprinkler
would be required for the building (IBC 508.3).
I would encourage the addition of automatic fire sprinklers to the building for future tenant opportunities.
Below are the notes provided on 11/15/16.
"PLANNING PERMIT REVIEW NOTES FOR 22019 Hwy 99, PLN20160049
1. An automatic fire sprinkler may be required in the assembly portion of the building depending
upon the occupant load of that area.
2. If an automatic fire sprinkler is required, provide under deferred submittal:
Fire connection permit
Fire Sprinkler Permit
Fire Alarm Permit
3. Provide fire access to all sides of building, minimum 20' wide, with required signs and
markings."
Please contact me if you have further questions.
Kevin Zweber
Deputy Chief - Fire Marshal
City of Edmonds,
Department of Fire Prevention
Snohomish County Fire District 1
425-771-0213 Office