CITY OF EDMONDS
CIVIL PLAN REVIEW COMMENTS
ENGINEERING DIVISION
(425) 771-0220
City Website: www.edmondswa.gov
DATE:
March 28, 2017—Revised April 11, 2017
TO:
Jacob Strobl – Strobl Design LLC
Jacob@strobldesign.com
FROM:
JoAnne Zulauf
Joanne.zulauf@edmondswa.gov
RE:
Application #: bld20170212
Project: Vrablik Residence Addition
Project Address: 17709 Talbot Road
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Reviews by other divisions, such as Planning, Building, or
Fire may result in additional comments. Please redline plans or submit three (3) sets of revised
plans/documents with a written response to each of the items below to a permit coordinator.
nd
Resubmittals can be made at the Development Services Department on the 2 floor of City Hall.
Permit Center hours are M, T, Th & F from 8am-4:30pm and on Wednesdays from 8:30am-noon.
City of Edmonds handouts, standard details and development code can be referenced on the City
website.
SITE PLAN
1.For proposed footing drain line, indicate if connecting to existing house footing system or if the
drain will be directed to another area. Geotech report indicates that the outfall shall be directed
away from the slope area.
2.Provide TESC standard details (can be found on the City Website) that will be used on the site.
May include silt fence, CB inserts, covered stockpiles, etc. Show location of erosion control
measures on the site plan. Waddles may be chosen instead of a silt fence to reduce the amount
of disturbance near the slope.
3.Splash blocks cannot be used for the stormwater discharge per the Geotech report. It states that
runoff be directed away from the slope. Please show how that will be accomplished on the
plans.
4.Add note: Install and maintain all TESC measures according to approved plans, City of
Edmonds standard details, and all other measures that may be required during construction.
5.Add note: “Disturbed areas to be compost amended per DOE standard detail BMP T5.13.”