Building Comments 1.pdfCity of Edmonds
PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: October 4, 2017
TO: Elyssa Boyd
_rg avitybar2017 a,gmail.com
FROM: Chuck Miller, Plans Examiner
RE: Plan Check: BLD2017-1193 - I" review
Project Address: 610 51h Avenue S, Suite B
Project: The Gravity Bar plumbing
Scope: Plumbing for commercial kitchen including grease trap— A-2 occupancy
group (proposed as `B') — 58 occupants (38 proposed) — VB construction — no
sprinkler system required — tenant improvement, mechanical, fire alarm, etc. under
separate permits
Please be advised that the building plans for the above referenced project have been disapproved
for the purposes of obtaining a building permit. During a review of the plans by the Building
Division for compliance with the applicable building codes, it was found that the following
information, clarifications, or changes are needed. Reviews by other divisions, such as Planning,
Engineering, or Fire, may result in additional comments that require attention beyond the scope of
this letter.
A complete review cannot be performed until the revised plans/documents, including a
written response in itemized letter format indicating where the `clouded' or otherwise
highlighted changes can be found on the revised plans, have been submitted to a Permit
Coordinator.
Resubmittals must be made at the Development Services Department on the 2nd Floor of City Hall.
Permit Center hours are M, T, Th, & F from 8am-4:30pm and from 8:30am-12pm on Wednesdays.
On a copy of sheet 4 of the plans submitted for permit BLD2017-1135:
Plumbing Plans — While the plans generally appear to represent a compliant plumbing
supply, drain, waste, and vent system, there are other interested parties (the City of Edmonds
Pretreatment Technician and the Environmental Health Division of the Snohomish Health
District) that may have unresolved concerns regarding the proposed project. Those may
include a determination of which fixtures are to be connected to the `grease trap' and the
requirement that the `3 compartment sink' be indirectly connected to the sanitary drainage
system (and possibly another floor sink installation). A complete Building Division review
cannot be performed until those reviews have been completed and any required revisions in
response to them have been made to the plans.