Correction Notice 4.24.15.pdfRivera, Chris
To: winlessley@frontier.com
Subject: City of Edmonds - Final Inspection Corrections for Campbell Nelson
Win,
Below are the Corrections required prior to signoff.
1. Sidewalk ramp will need to meet ADA compliance.
2. Control Structure overflow with 2nd and 3rd Orifice need to be installed, see attached image from plans.
3. All CB's will need to be cleaned out.
4. Need to remove board from existing CB within the right of way.
5. Reduce the amount of rock over the top of drain for bio swale.
6. Need to remove socks out of CB's (2) in the right of way, south west corner of project and furthest CB from project
site.
7. Need to submit as-builts.
8. Beyond these corrections, we need to have our operations guys take a look at the storm filtration system once cover
is easily moved.
If there are any questions, please feel free to contact us.
Thank you,
Chris B. Rivera
Engineering Technkian
City of Edmonds
1215 1h Ave. N.
Edmonds, WA 98020
425.771.0220 ext. 1339
Chris.Rivera@edmondswa.gov