CRA20160039 Erosion Hazard.pdfCI'T"Y OF EMON:S
121 5"' Avenue North, Edmonds WA 98020
Phone: 425.771.0220 • Fax: 425.771.0221 • Web: www.edmondswa. o_v_
DEVELOPMENT SERVICES DEPARTMENT • PLANNING DIVISION
Critical Areas Reconnaissance Report
Critical Areas File Number
Determination
Site Location
Tax Account Number
Property Owner
Applicant
Critical Areas Present
Site Description
CRA20160039
Study Required
612-9 th Ave. S, Edmonds
00738700000600
Aaron Hansen
Garin Schenk
Q Geologically Hazardous Areas
Q Erosion Hazard Areas
During review and inspection of the subject site, it was found that the site may contain (or be adjacent to) critical
areas, including a Geologically Hazardous Area (Erosion Hazard Area), pursuant to Chapters 23.40 and 23.80 of
the Edmonds Community Development Code (ECDC). Cited sections of the Edmonds Community Development
Code (ECDC) can be found on the City of Edmonds website at www.edmondswago '.
The adjacent property to the north (addressed 608 — 9th Ave. S) contains a manmade pond and waterfall, which
does not qualify as a critical area. According to the Soil Survey of Snohomish County Area, Washington, soils on
the subject site consist of "Alderwood Urban land complex, 8 to 15% slopes." The western approximate two-thirds
of the site is relatively level. The eastern approximate third of the site slopes downwards from the 9th Ave. S right-
of-way, a portion of which is supported by a rockery. According to City LiDAR data, the overall slope on/adjacent
to the eastern approximate third of the subject site is approximately 30%, which qualifies as an Erosion Hazard
Area. Therefore, the site contains and/or is adjacent to a slope that is steep enough to be considered an Erosion
Hazard Area. No other critical areas were observed on or adjacent to the site.
Allowed Activities & Exempt Proposals
Certain activities are allowed in or near critical area buffers as specified in ECDC 23.40.220. Similarly, certain
development proposals may be exempt from Critical Areas requirements (ECDC 23.40.230). if you have any
questions about whether your proposed development qualifies as an allowed or exempt activity, please contact
a Planner for more information.
General Report Requirements
Critical Areas Reports identify, classify and delineate any areas on or adjacent to the subject property that may
qualify as critical areas. They also assess these areas and identify any potential impacts resulting from your specific
development proposal. If a specific development proposal results in an alteration to a critical area, the critical
areas report will also contain a mitigation plan. You have the option of completing the portion of the study that
classifies and delineates the critical areas and waiting until you have a specific development proposal to complete
the study. You may also choose submit the entire study with your specific development application. Please review
the minimum report requirements for all types of Critical Areas which are listed in ECDC 23.40.090.D. There are
additional report requirements for different types of critical areas (see below). Note that it is important for the
report to be prepared by a qualified professional as defined in the ordinance. There are options on how to
complete a critical areas study and an approved list of consultants that you may choose from. You may contact the
Planning Division for more information. General Mitigation Requirements for all Critical Areas are discussed in
ECDC 23.40.110 through 23.40.140.
Erosion Hazard Areas
It appears that this property contains or is adjacent to an Erosion Hazard Area. Geologically hazardous areas
include areas susceptible to erosion, land sliding, earthquake, or other geological events. They pose a threat to the
health and safety of citizens when incompatible development is sited in areas of significant hazard. Such
incompatible development may not only place itself at risk, but also may increase the hazard to surrounding
development and use.
Erosion Hazard areas include Alderwood and Everett series soils on slopes of 15 percent or greater, among others.
Landslide Hazard Areas are further defined in ECDC 23.80.020.A. In addition to the general requirements for
Critical Areas reports referenced above, specific Critical Area report requirements for Erosion Hazard Areas (which
are one of the Geologically Hazardous Areas) are provided in ECDC 23.80.050.
Note that Stable Erosion Hazard Areas may have limited report requirements at the director's discretion. At a
minimum, an erosion and sediment control plan prepared in compliance with the requirements in ECDC Chapter
18.30 shall be required.
Development is restricted within an Erosion Hazard Area and must meet additional criteria. For erosion hazard
areas with suitable slope stability, an erosion and sediment control plan prepared in compliance ECDC 18.30 will be
considered to meet the Critical Areas "Study Required" determination. The determination of "suitable slope
stability" will be made by both the Planning and Engineering divisions of the City of Edmonds. In areas where the
slope stability is not suitable, projects within Erosion Hazard Areas will require a report by a licensed Geotechnical
Engineer or other qualified professional. Note that it is important for the report to be prepared by a qualified
professional as defined in the ordinance. Report requirements are given in ECDC 23.80.050, and more generally in
ECDC 23.40.090.D. Development standards are given in ECDC 23.80.060 and 23.80.070.
Determination: Study Required
This review applies to the entire subject parcel. Depending on the location and project proposed relative to the
identified critical areas, certain studies and reports may be required. Please contact the Planning Division at
425.771.0220 if and when you have a specific development proposal for this site in order to discuss the various
permits that will be required. Please note that tree removal on sites containing critical areas may first require a
tree cutting permit, and the illegal removal of trees may result in penalties and steep fines (ECDC 18.45.070,
ordinance #3828).
Jen Machuga, Associate Planner
Name, Title
Signatu
April 22, 2016
Date
Page 12