Edmonds Way-665_bld20080635_Anderson Office_4.pdf
DATE: January 19, 2009
TO: Tony Shapiro
tony@adshapiro.com
FROM: Jeanie McConnell, Engineering Program Manager
RE: Application #: bld20080635
Project: Anderson Office Building
Project Address: 665 Edmonds Way
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please redline plans or submit three (3) sets of revised
plans/documents with a written response to each of the items below to Marie Harrison.
City of Edmonds handouts and standard details can be referenced on the City website under
Development Services Department, Engineering Division.
Review 1 September 22, 2008
Review 2 November 3, 2008
Review 3 December 19, 2008
Review 4 January 19, 2009
GENERAL
1/19/09 Please revise and resubmit cost estimate so inspection fees and bond amount can
1.
be determined.
12/19/08 Response letter state the cost estimate needs to be revised by the contractor. A
revised cost estimate was not submitted. Please submit so inspection fees and bond amount can
be determined.
11/3/08 Thank you for providing a cost estimate.
Please revise the cost estimate for on-site improvements as follows:
a.Add cost estimate for trash enclosure
b.Add cost estimate for parking lot striping
c.Revise quantity of Type II CBs to two (2).
d.Add 54 Type II MH
e.Revise detention system cost estimate to include a breakdown of pipe size, material and
lineal footage. The plans indicate a detention vault will not be installed at this site.
f.Add cost estimate for storm tightline. Specify pipe size, material and lineal footage.
g.Add cost estimate for footing drains. Specify pipe size, material and lineal footage.
Edmonds Way-665_bld20080635_Anderson Office_4
Comments e-mailed: December 19, 2008 Page 1 of 2
h.Revise water pipe (domestic & fire) and sewer pipe estimates to include pipe size,
material and lineal footage.
Please revise the cost estimate for off-site (right-of-way) improvements as follows:
a.Revise concrete curb callout to specify concrete curb and gutter.
b.Add cost estimate for the storm connection required at the existing manhole in the City
right-of-way.
c.Revise fire sprinkler service connection to include pipe size, material, lineal footage and
gate valve (if required by OVWSD).
ok
2.
ok
3.
Please contact me at 425-771-0220 or by e-mail at mcconnell@ci.edmonds.wa.us if you have
specific questions regarding these plan corrections.
Edmonds Way-665_bld20080635_Anderson Office_4 Page 2 of 2