ENG Approval Memo - Design Review - Phase II.pdfDate:
ral
MEMORANDUM
July 31, 2019
Michael Clugston, Senior Planner
From: Jeanie McConnell, Engineering Technician
Zachary Richardson, Stormwater Engineer
Bertrand Hauss, Transportation Engineer
Subject: PLN20190009 —Design Review Graphite I and II
Graphite — 202 Main St
Engineering has reviewed the subject application and found the information provided is
consistent with Title 18 Edmonds Community Development Code & Engineering standards.
Compliance with Engineering codes and construction standards, including street tree placement
and quantity, trash enclosure dimensions, parking layout, etc., will be reviewed with the building
permit application for development of the site. Approval of the design review phase of the
project does not constitute approval of the improvements as shown on the submitted plans.