Engineering Plan Review Comments
PermitApplication:Date:
#ENG2011 0259November 10, 2011
th
Project Name/Address:
2411–104Ave W –WO#109063925
Contact Person/Address, Fax or E-mail:
Kelli Martin
Reviewer: JENNIFER LAMBERTDivision:
ENGINEERING
During review of the subject submittal, it was found that the following information, corrections, or
clarifications would need to be addressed. All Handouts referred to in these comments can be accessed at
our website: www.ci.edmonds.wa.usunder City Government / Development Services Department /
Engineering Division then scroll down to Handouts:
General
1.Please provide approval from Olympic View Water Sewer District (OVWSD) for the proposed work.
2.Please add a note to the plans that if the cuts extend beyond the centerline of the road a fullwidth grind
and overlay will be required.
Sheet 3 of 8
th
1.The city storm main extends north of 104than what is shown (approximately to the middle of 23615
th
104Ave W). Please revise plans accordingly.
th
2.It appears that a portion of the proposed gas main along 104Ave W will be replaced within the
sidewalk.
a.Please show all cuts within the sidewalk and/or asphalt.
b.Please note what material will be replaced (i.e. sidewalk panel,asphalt roadway, etc).
c.Please show that 5’ separation will be maintained between the proposed gas and the City Storm
Main.
Sheet 5 of 8
1.The city has a future Stormwater project that is proposed to run conveyance and infiltration lines along
th
the north side (within the shoulder) of 238St SW.
DATE E-MAILED11/10/2011PAGE(1)
City of EdmondsENG20110259
TH
121 5AVENUE NORTHEDMONDS, WA 98020 • (425) 771-0220 FAX(425) 771-0221
Website: www.ci.edmonds.wa.us
PUBLIC WORK DEPARTMENT
Planning • Building • Engineering
Engineering Plan Review Comments
a.Please show the new line as close tothe aphalt edge or within the roadway; such that the
proposed line meets OVWSD requirements as well as maintain 5’ separation from the City
Stormwater Main.
b.Please show any asphalt cuts on the plans. If there are significant cuts within the roadway, please
note that ‘A ½ width grind and overlay may be required’.
st
2.Please note on the plans that a ‘A ½ width grind and overlay will be required on 101Ave W’.
Sheet 6 of 8
1.Please note on the plans that a ‘A ½ width grind and overlay will be required on Firdale Ave W’.
th
2.If the cuts on 238St SW are within the asphalt walkway, please note on the plans that, ‘The walkway
th
will be replaced from Firdale Ave W to the limits of construction on 238St SW’.
th
3.If the cuts on 238St SW are not within the asphalt walkway, please note as such on the plans.
Sheet 7 of 8
1.Please note on the plans that a ‘A ½ width grind and overlay will be required on Firdale Ave W’.
Sheet 8 of 8
1.Please note on the plans that a ‘A ½ width grind and overlay will be required on Firdale Ave W and
rd
243Pl SW’.
***Please make sure that any changes made above are also reflected on the appropriate Traffic Control
Plans. ***
Please resubmit 3 copies of the revised traffic control plansand associated documents with a written
response to each item to an Engineering Technician. Please contact me at 425-771-0220ext 1321or by e-
mail at jennifer.lambert@ci.edmonds.wa.usif you have specific questions regarding these plan
corrections.