Engineering Plan Review Comments
PermitApplication:Date:
#ENG201400491/31/14
th
Project Name/Address:
8325–212St SW –Job #109078605
Contact Person/Address, Fax or E-mail:
Todd Beckley –todd.beckley@pse.com
Reviewer: JENNIFER LAMBERTDivision:
ENGINEERING
During review of the subject submittal, it was found that the following information, corrections, or
clarifications would need to be addressed. All Handouts referred to in these comments can be accessed at
our website: www.ci.edmonds.wa.usunder City Government / Development Services Department /
Engineering Division then scroll down to Handouts:
General
1.Please note that theentire jobis to be open trench. Please note that finalrestoration will be coordinated
with the City of Edmonds.
2.There are portions where thegasmain will be placed at a different depthsthan the typical 3’depth.
When the utilities are located in the future, how will it be identified that the main is deeper than the
standard 3’depth?
3.Please verify and confirm that thetrench depth between all utilities hasbeen agreed uponand verified.
Sheet 1 of 5
1.Standard gas construction notes
a.Please revisenote 6 to include the City of Edmondsas a party that must approve in change in
route.
b.Add to note 13 that restoration must also meet ADA requirements.
Sheet 2 of 5
th
1.Plot Plan at the top left corner of the sheet (streets shown –84Pl W & Woodlake Dr).
a.Please obtain the revisedplans from David & Evans Associate.
b.Please make sure that all utility layers are shown on the plans. The watermainlayer is not
currently shown on the plans.
c.Field locates show the existing gas main on Woodlake Dr further west than what is shown.
Please verify and revise the plans accordingly.
DATE E-MAILED1/31/2014PAGE (1)
City of Edmonds
TH
121 5AVENUE NORTHEDMONDS, WA 98020 • (425) 771-0220FAX (425) 771-0221
Website: www.edmondswa.gov
PUBLIC WORK DEPARTMENT
Planning • Building • Engineering
Engineering Plan Review Comments
thth
2.Plot Planin the middle to right side if sheet (Streets shown –Main,Bowdoin, 84, and 212)
a.How were the location of the bends determined on theplans?In reviewing the plans it appears
that thegas main may be tooclose to the new watermain; such thatthere is not enough
undisturbed soils between the watermain and gas main to provide thrust protection.Accuracy as
to gas main locations is critical, since a lotof the utilities are being placed after the gas main is
installed. The City wantsto ensure that the possibility of gas main relocations during the road
project is minimized.
th
b.Revise alignment of gas main on 84Pl W, south of intersection such that it is further south by
approximately 13’for the run crossing the street and so thatthe run going North/South is 6’to 8’
eastofthe existing sewer main(see attached area, highlighted in yellow).
c.Shift gas main running Southwest/Northeast so that it is further away from the proposed water
main(see attached area, highlighted in yellow).
Sheet 3of 5
No Comments
Sheet 4of 5
No Comments
Sheet 5of 5
1.General Notes
a.Please remove any notes form the ‘General Notes’section that does not apply.
b.Please revise ‘2010 WSDOT/APWAstandards specs…’to ‘2012’in note #1.
2.General R/W use restoration requirements (8-040)
a.Please review all notes and revise the reference to Snohomish County to the City of Edmonds.
3.Trench Notes
a.Please revise note 1 to state the following: “Longitudinal trench -Per City of Edmonds Standard
Detail E2.3.”
b.Remove note 3.
Please resubmit 3 copies of the revised traffic control plansand associated documents with a written
response to each item to an Engineering Technician. Please contact me at 425-771-0220ext 1321or by e-
mail at jennifer.lambert@ci.edmonds.wa.usif you have specific questions regarding these plan
corrections.