Engineering Comments 1.pdfof ED40CITY OF EDMONDS
�° PLAN REVIEW COMMENTS
ENGINEERING DIVISION
�sr_ ig90 (425) 771-0220
City Website: www.edmondswa.gov
DATE: December 10, 2018
FROM: JoAnne Zulauf, Engineering Technician
Joanne.zulauf@edmondswa.gov
RE: Application #: BLD20181580
Project: Select Homes - Single Family Residence
Project Address: 7902 203rd St SW
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please submit revised plans/documents including a written
response to each item below.
Resubmittals can be made at the Development Services Department on the 2nd floor of City Hall.
Permit Center hours are M, T, Th & F from 8am-4:30pm and on Wednesdays from 8:30am-noon.
City of Edmonds handouts, new updated standard details with new reference numbers, application
and other forms, and development code may be referenced on the City website:
www.edmondswa.gov under Services/Permits and Development.
GENERAL
1) Submit ROW Permit Application form
2) Submit Side Sewer Permit Application form
3) A Stormwater Covenant is required to be recorded against the property based on the
proposed stormwater facilities for the project. Please complete the covenant, including
notarization and any required exhibits and submit to the city. Ensure the stormwater
covenant meets Snohomish County Record Drawing requirements. The document must be
complete, but will not be recorded prior to permit issuance. Prior to construction, final
location of facilities are to be verified (by field inspection and asbuilt) and then the covenant
will be recorded.
WATER
4) Please call out size of water meter.
5) Provide separation information where the sewer stub and water line cross. Note sleeving
etc.