Engineering Comments 2.pdfCITY OF EDMONDS
PLAN REVIEW COMMENTS
ENGINEERING DIVISION
(425)771-0220
City Website: www.edmondswa.gov
DATE: March 25, 2019
FROM: JoAnne Zulauf, Engineering Technician
Joanne.zulauf@edmondswa.gov
RE: Application #: BLD20181466
Project: Chung - Single Family Residence
Project Address: 725 Edmonds Way Lot 2
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please submit revised plans/documents including a written
response to each item below.
Resubmittals can be made at the Development Services Department on the 2nd floor of City Hall.
Permit Center hours are M, T, Th & F from 8am-4:30pm and on Wednesdays from 8:30am-noon.
City of Edmonds handouts, New updated standard details with new reference numbers, application
and other forms, and development code may be referenced on the City website:
www.edmondswa.gov under Services/Permits and Development.
GENERAL
1) Done.
2) Done.
3) Done.
4) 3.25.19 Not done. Submit Side Sewer Permit Application form
5)
Done.
6)
Done.
7)
Done.
8)
Done.
9)
Done.
10) Done.
11) 3.25.19 Not done. This needs to be reviewed and may need correction. Please submit as
soon as possible. A Stormwater Covenant is required to be recorded against the property
based on the proposed stormwater facilities for the project. Please complete the covenant,
including notarization and any required exhibits and submit to the city. Ensure the
stormwater covenant meets Snohomish County Record Drawing requirements. The
document must be complete, but will not be recorded prior to permit issuance. Prior to
construction, final location of facilities are to be verified (by field inspection and asbuilt)
and then the covenant will be recorded.
12) 3.25.19 Not completed.There is a side sewer easement that benefits Lot 2 across Lot 1.
Show all private easement information for this lot only within the plan set submittal.
13) Done
14) OK
TESC-You can use a copy of the tesc plan from the short plat -just add a copy to each set of
drawings in each permit.
1) Done
2) 3.25.19 Construction entrance is to protect the right of way from debris. It should be located
at the entrance of the short plat on Lot 3. The area where the construction entrance is shown
now is proposed to have pervious pavement. Outline the area and make note that heavy
equipment should avoid the area as much as feasible. Show construction entrance on the
plans and incorporate and reference New City standard de-
3) Done
4) 3.25.19 Add around pervious pavement area. Orange protective barrier fencing shall be
placed at the drip line of trees to remain and around areas proposed for low impact
development techniques, such as rain gardens, infiltration systems, etc., to protect the area
from compaction.
5) Done.
6) Done.
7) Done.
SEWER — Done.
STORM
1) Done.
2) 3.25.19 Note on C3 states footing drains discharge into surrounding soil. Please show where
this is going to happen. Show where the footing drains will discharge.
3) Done.
4) Done.
5) Done.
STORMWATER ENGINEER REVIEW
Refer to separate plan review comments by City Stormwater Engineer, Zachary Richardson.
Please contact Zack directly at 425-771-0220 or by email at
zachary.richardsonnedmondswa.gov with any specific questions you may have regarding his
comments.
Page 2 of 2