Engineering Comments 3.pdfof ED40CITY OF EDMONDS
�° PLAN REVIEW COMMENTS
ENGINEERING DIVISION
�sr_ ig90 (425) 771-0220
City Website: www.edmondswa.gov
DATE: August 20, 2019 Please note -this is the third review of these plans. Future reviews
will add additional charges equal to actual review hours needed to complete the approval process.
FROM: JoAnne Zulauf, Engineering Technician
Joanne.zulauf@edmondswa.gov
RE: Application #: BLD20181098
Project: Chung - Single Family Residence
Project Address: 721 Edmonds Way Lot 1
During review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please submit revised plans/documents including a written
response to each item below.
New Comments: 1. The change to the location of the water line was not updated on the sheet A0.
2. The purveyor for sewer is listed as OVWSD on sheet C1.0-should be COE
GENERAL
1) Done
2) Done.
3) Done
4) 8.20.19 Still outstanding. 3.25.19 Not done. Submit Side Sewer Permit Application form
5) Done
6) Done
7) Done
8) Done
9) Done
10) 8.20.19 Rockery is still shown on plan sheet A0. Needs to be shown on all plans and must
include top and toe elevations for each end of rockery and at every 2 ft of change. 3.25.19
Not done. Response letter states that rockery is removed but it is still shown on the plans. A
rockery is shown along the access road. The City of Edmonds does not review or approve
rockeries. Construction of rockeries is prohibited within the City of Edmonds under certain
circumstances and in certain situations per Edmonds Community Development Code
18.40.020. Please review the code section to verify this rockery falls outside of the
prohibitions. Top and toe elevations for the rockery are required at each end of the wall and
at every two feet of change.
11) 8.20.19 Still outstanding. 3.25.19 Not Done. This requires a review, please submit as soon as
possible. A Stormwater Covenant is required to be recorded against the property based on
the proposed stormwater facilities for the project. Please complete the covenant, including
notarization and any required exhibits and submit to the city. Ensure the stormwater
covenant meets Snohomish County Record Drawing requirements. The document must be
complete, but will not be recorded prior to permit issuance. Prior to construction, final
location of facilities are to be verified (by field inspection and asbuilt) and then the covenant
will be recorded.
12) Show all private easement information for this lot only within the plan set submittal.
13) Done.
14) Done.
15) Done
16) Done.
17) Ok
TESC-You can use a copy of the tesc plan from the short plat -just add a copy to each set of
drawings in each permit.
1) Done.
2) Done.
3) Done.
4) 8.20.19 Entrance must be perpendicular to Edmonds Way for a minimum of 20 ft. In
reviewing the geotech report, there are provisions for installing the construction entrance,
please show per report. 3.25.19 Future location of pervious pavement should be protected
to the extent possible. Please add fence to part of it at least. Orange protective barrier
fencing shall be placed at the drip line of trees to remain and around areas proposed for low
impact development techniques, such as rain gardens, infiltration systems, etc., to protect the
area from compaction.
5) Done.
6) Done.
7) Done.
SEWER
1) Done.
2) Done.
3) Done.
STORM
1) Done.
2) 8.20.19 Stormwater engineer will address if overflow discharge is not acceptable. If it is
acceptable then this comment is satisfied. 3.25.19 Please show the location they will
discharge into the soil per note on C3. Show where the footing drains will discharge.
3) Done.
4) Done.
5) Done.
STORMWATER ENGINEER REVIEW
Refer to separate plan review comments by City Stormwater Engineer, Zachary Richardson.
Please contact Zack directly at 425-771-0220 or by email at
Page 2 of 3
zachary.richardson(aedmondswa.i!ov with any specific questions you may have regarding his
comments.