Engineering Decision-Final Short Plat.pdfCITY OF EDMONDS
ENGINEERING DIVISION
Date: October 22, 2018
To: Michele, Szafran, Planning
From: JoAnne Zulauf, Engineering
Subject: PLN20170046, Select Homes
18807 8811 Ave W — 3 lot Short Plat
The Engineering Division has found that the subject 3-lot short plat meets the requirements
established for civil subdivision improvements in accordance with Edmonds Community
Development Code (ECDC) 20.75.
Preliminary short plat approval was issued by the Planning Division on January 5, 2018 and
included engineering conditions of approval.
Civil construction plans were submitted to the Engineering Division on April 9, 2018
consistent with the conditions of approval and ECDC 20.75.120. The plans were approved
for construction on July 31, 2018. While most of the improvements have been installed and
inspected, the short plat construction has yet to be completed in its entirety. Consistent with
ECDC 20.75.130, a performance bond has been posted as surety that these improvements will
be completed within 12 months following recording of the short plat. A performance bond
was submitted by the developer and accepted by the City on August 1, 2018 reflecting the
total cost to construct all required improvements in the amount of $162,587.88.
As a condition of development the subject short plat will dedicate a 10-foot strip of property
as Public Street to the City of Edmonds along 88th Ave W. The dedication was approved by
the City Council during their October 9, 2018 meeting.
Consistent with ECDC 18.30.090, a permanent access easement has been granted to the City
of Edmonds for access to the private stormwater facility located on Lot 1. Access is for
inspection purposes to ensure that stormwater facilities are properly operated and maintained
in accordance with City of Edmonds Code.
City of Edmonds