Engineering Decision-Final_Plat.pdfCITY OF EDMONDS
ENGINEERING DIVISION
Date: April 26, 2019
To: Mike Clugston, Senior Planner
From: Jeanie McConnell, Engineering Program Manager
Subject: PLN20170028, Jenkins Lane - Final Plat
720 —13th Way SW — 5 lot Plat
The Engineering Division has found that the subject 5-lot plat meets the requirements
established for civil subdivision improvements in accordance with Edmonds Community
Development Code (ECDC) 20.75.
The Hearing Examiner's Decision, which provided preliminary plat approval, was issued on
November 9, 2017 and included engineering conditions of approval. Civil construction plans
were submitted to the Engineering Division on December 22, 2017 consistent with the
conditions of approval and ECDC 20.75.120. The plans were approved for construction on
June 21, 2018. The improvements shown on the approved plans have not yet been
constructed in their entirety. Consistent with ECDC 20.75.130, a performance bond has been
posted as surety that these improvements will be completed within 12 months following
recording of the plat. A performance bond was submitted by the developer and accepted by
the City on August 31, 2018 reflecting the total cost to construct all required improvements in
the amount of $231,708.00.
As a condition of development the subject plat will dedicate a 10-foot strip of property as
public street to the City of Edmonds along 13th Way SW. The dedication was reviewed by the
Council's Planning, Parks and Public Works committee on January 23, 2018 and approval
was given to forward to the full council.
Consistent with ECDC 18.30.090, a permanent access easement has been granted to the City
of Edmonds for access to the private stormwater facility located in Tract 999. Access is for
inspection purposes to ensure that stormwater facilities are properly operated and maintained
in accordance with City of Edmonds Code.
Thank you.