Engineering Decision-Final_Plat-PLN20180053.pdfCITY OF EDMONDS
ENGINEERING DIVISION
Date: October 7, 2019
To: Kernen Lien, Environmental Programs Manager
From: Jeanie McConnell, Engineering Program Manager
Subject: PLN20180053, Select Homes - Final Short Plat
9215 Bowdoin — 2 lot Short Plat
The Engineering Division has found that the subject 2-lot short plat meets the requirements
established for civil subdivision improvements in accordance with Edmonds Community
Development Code (ECDC) 20.75.
Preliminary plat approval was issued by the Planning Division on November 7, 2018 and
included engineering conditions of approval.
Civil construction plans were submitted to the Engineering Division on January 4, 2019
consistent with the conditions of approval and ECDC 20.75.120. The plans were approved
for construction on July 10, 2019.
The improvements shown on the approved plans have not yet been constructed. Consistent
with ECDC 20.75.130, a performance bond has been posted as surety that these
improvements will be completed within 12 months following recording of the short plat. A
performance bond was submitted by the developer and accepted by the City on July 18, 2019
reflecting the total cost to construct all required improvements in the amount of $64,173.72.
The subject development did not include street dedications to the City.
Thank you.
City of Edmonds