Engineering Decision-Final_Short Plat.pdfCITY OF EDMONDS
ENGINEERING DIVISION
Date: July 24, 2019
To: Mike Clugston, Senior Planner
From: JoAnne Zulauf, Engineering Technician
Subject: PLN20170020, Johnson - Final Short Plat
8498 Talbot Rd — 2 lot Short Plat
The Engineering Division has found that the subject 2-lot short plat meets the requirements
established for civil subdivision improvements in accordance with Edmonds Community
Development Code (ECDC) 20.75.
Preliminary plat approval was issued by the Planning Division on June 11, 2018 and included
engineering conditions of approval.
Civil construction plans were submitted to the Engineering Division on April 1, 2019
consistent with the conditions of approval and ECDC 20.75.120. The plans were approved
for construction on June 13, 2019. The improvements shown on the approved plans have not
yet been constructed. Consistent with ECDC 20.75.130, a performance bond has been posted
as surety that these improvements will be completed within 12 months following recording of
the plat. A performance bond was submitted by the developer and accepted by the City on
June 26, 2019 reflecting the total cost to construct all required improvements in the amount of
$69,708.96.
Consistent with ECDC 18.30.090, a permanent access easement has been granted to the City
of Edmonds for access to the future private stormwater facility located on Lot 1 and/or Lot 2.
The construction of the stormwater system has been deferred to coincide with the building
permit development of Lot 2. Access is for inspection purposes to ensure that stormwater
facilities are properly operated and maintained in accordance with City of Edmonds Code.
The subject development did not include street dedications to the City.