Engineering Memo of Compliance.pdfDate:
To:
From:
Subject:
MEMORANDUM
October 3, 2018
Brad Shipley, Associate Planner
Natalie Griggs, Engineering Technician
PLN20180056 — Landscape Modification
Elm Place HOA — 619 Elm PI
Engineering has reviewed the subject application and found the information provided is
consistent with Title 18 Edmonds Community Development Code & Engineering standards.
It is requested that the following be included as a condition of project approval.
1) Trees shall be fell onto private property.
2) Vehicles and equipment shall be located on private property. Should it be necessary to
utilize any portion of the City right-of-way, including the street or sidewalk, to
perform any of this work then the contractor shall apply for and obtain a right-of-way
construction permit in advance of starting work. A traffic control plan will be required
as part of the right-of-way permit application.
3) Contractor/owner is responsible for keeping all debris on site and preventing any silt
laden runoff from leaving the site and/or entering the city storm system.
4) Contractor/owner shall repair/replace any damaged sections of curb/gutter, sidewalk
or other public improvements in City right-of-way per City standards that is caused by
or occurs during the permitted project.
5) Contractor/owner is responsible for locating all on -site utilities and any utilities on
neighboring properties that could be impacted by the tree removal. The water utility
purveyor for this site is Olympic View Water and Sewer District and for sewer the
purveyor is the City of Edmonds. Relocation/revision/repair to any utilities may
require separate permit.
Thank you.
City of Edmonds