Engineering Memo of Compliance1 12-4-18.pdfY MEMORANDUM ENGINEERING MEMO OF COMPLIANCE Date: December 4, 2018 To: Michele Szafran, Planning Division From: JoAnne Zulauf, Engineering Division Subject: PLN20180050, Ryker Young (Real Property Funding Group LLC), 2 lot short plat; 20114 83rd Ave W Engineering has reviewed the preliminary short plat application for the Real Property Funding Group LLC property at 20114 83rd Ave. W. The information provided indicates general engineering feasibility. As part of the preliminary short plat review, requirements regarding development of the adjacent public infrastructure were determined. Consistent with the City's Official Street Map, there are no street dedications required along 83rd Ave. W. property frontage. Lot and Street Layout and Sidewalks: The property is a lot on 83rd Ave W. 83rd Ave W is classified as a local street. A requirement has been established that access to Lot 1 and Lot 2 shall be a single access from 83rd Ave W. Edmonds Community Development Code (ECDC) Chapter 18.90 regulates the construction of sidewalks that could prevent the implementation of the comprehensive sidewalk plan. • 83rd Ave W is a local street in the RS-8 zone. 83rd Ave W street right-of-way is classified as a local street and per City Code, sidewalks are only required on one side of the street. Sidewalks have already been established on east side of 83rd Ave W and therefore are not a requirement of this short plat located on the west side of 83th Ave W. Edmonds Community Development Code (ECDC) Chapter 18.80.060.D regulates the construction of driveways. Driveway slopes shall not exceed 14 percent unless authorized by the public works director in accordance with specific criteria set forth in this code section. The driveway shall not be approved to exceed a 20% slope. The decision of the public works director shall be made only after notice as a Type II project permit application and decision. City of Edmonds Applicant indicates a driveway slope greater than 14%, up to 15% in some areas on the preliminary plans and has submitted a driveway slope waiver request consistent with code requirements. 1. Driveway slopes shall not exceed 14 percent unless authorized by the public works director in accordance with the criteria set forth below. The decision of the public works director shall be made only after notice as a Type II project permit application and decision. (See Chapter 20.01 ECDC.) 2. The public works director may authorize driveway slopes to exceed 14 percent up to a maximum of 20 percent if he determines that: a. The driveway is the only economical and environmentally reasonable alternative. - The elevation differences along the frontage range form a low elevation of 372, to a high elevation of 386. The property then slopes up to elevations of 400 to 414 along the back property line. To minimize the on -site slope of the joint access drive, the access starts at the high elevation of 386. b. The driveway will not present a traffic, pedestrian, bicycle or safety hazard or otherwise negatively impact public safety; The new driveway will be placed at the same location as the existing driveway. No addition access shall be added to the property frontage. A vertical curve is designed at the frontage to smoothly transition from the slope of 83rd Ave W to the 15% slope. The new joint entrance shall provide a stronger visual identifier to pedestrians that a vehicle access point exists. c. The police and fire chief concur in allowing the increased driveway slope; and The joint access length is 113 ft in length. The standard length in which a turn around is required is 150 ft in length. Additionally the vertical curve at the frontage will allow a transition from 83rd to the 15% which will easily accommodate fire and emergency vehicles. The consistent 15% slope of the access will also work to provide easy access. d. The public health, safety and general welfare will not be adversely affected. There is no indication that the proposal shall adversely affect public health, safety or general welfare. Therefore, the public works director finds that the waiver request is consistent with the criteria of ECDC 18.80.060 D. Please find attached the Engineering Requirements for the subject development. The applicant will be required to satisfy these requirements as a condition of short plat approval. Subsequent to obtaining a preliminary short plat determination of approval from the Planning Division, the applicant will be required to submit revised civil construction plans addressing all short plat conditions. Civil plans are to be submitted to the Engineering Division as noted below. A civil plan review fee is to be paid at the time of submittal. At this time, the review fee is $2785. The following information is provided to assist with the civil construction plans review process: 1) Civil plan submittal shall consist of two hard copies and supporting documents, as well as one electronic copy. A civil subdivision application form can be found on the city website. Please include the completed application form with both the hard copy submittal and the electronic submittal. Electronic copies can be emailed to EngineeringPermits@edmondswa.gov. 2) Civil plan sheets shall include an approval block similar to that provided on the City website. 3) Include utility purveyor information consistent with EUC Handout #E28, available on the City website. Add Stormwater purveyor, City of Edmonds as well as Fire — Fire District 1 4) Replace General Notes with the currently available notes found on the City website. Please revise year of WSDOT/APWA to current year and add the year of the stormwater manual the system is designed to meet. 5) Include construction sequence consistent with that found on the City website. Include phasing of work and protection of areas where low impact development techniques will be used to meet stormwater management requirements. Existing trees and vegetation shall be retained where feasible and tree protection measures identified on the plans. 6) Civil plans shall show all existing and the future separate building permit improvements in a light line weight. All improvements and notes specific to only the construction of the short plat improvements shall be shown using a dark line weight. Thank you. CITY OF EDMONDS 121 - 5TH AVENUE NORTH, EDMONDS, WA 98020 PUBLIC WORKS DEPARTMENT - ENGINEERING DIVISION REQUIREMENTS FOR SHORT PLATS To: Planning Division File Number: PLN20180050 From: JoAnne Zulauf, Engineering Technician Engineering Division Date: October 23, 2018 Project: Ryker Young 2 Lot Short Plat Address: 20114 83rd Ave W Required as a Required as a Requirement Condition of Condition of Already Subdivision Building Permit Satisfied 1. Right -of Way Dedication for Public Streets: AMMM a) N/A X Public Street Improvements & Access �" (Asphalt, curb, gutter and sidewalks): a) 83rd Ave W to be widened along property frontage to comply with street standards for the specific roadway classification, as required. X b) Curb and gutter shall be provided along property frontage as required to comply X with City standards and requirements. c) Provide asphalt or concrete driveway approaches on each lot per City Code. X d) Cross slope of public road shall not exceed 2% X e) Lots 1 & 2 shall take access from private access road. X i. Access road curb cut shall be constructed to meet City standards and ADA requirements. ii. Access road at 83rd Ave W shall meet sight distance requirements set forth by the American Association of State Highway and Transportation Officials (AASHTO). 3. Private Access Requirements & Im rovements: a) Lot 1 and 2 shall take access off shared private access road. X i. Private access road shall be paved to 12.0-feet in width, plus 18" asphalt thickened edge or 6-inch concrete extruded curb may be used to direct storm flows. ii. Slope of private access road and driveways shall comply with City Codes and standards. iii. Cross slope of private access road shall not exceed 2% b) Individual driveway access points shall meet sight distance requirements set forth by the American Association of State Highway and Transortation Officials X (AASHTO). c) Driveway entrance for each point of access shall be provided to City standards X d) Provide asphalt or concrete driveway approaches on each lot per City Code. X e) Slope of driveway shall not exceed 14% unless a driveway slope waiver has been granted in accordance with ECDC 18.80.060. X 1 of 3 ENGR RQMNTS - Ryker Young Short Plat printed 12/7/2018 Required as a Required as a Requirement Condition of Condition of Already Subdivision Building Permit Satisfied 4. Street Turnaround: a) N/A X 5. Easements (City utilitiesprivate access other utilities): a) Provide all easements as required - access, utility, etc. x b) All lots shall take access off private access road. X c) Private access easement shall be 15 (frfiteen) feet in width X 6. Street Li hts: a) N/A 7. Street Trees/Planting Strip: a) N/A X 8. Water System Improvements (COE): a) Applicant must meet requirements set forth by City of Edmonds for connection to public water system. X b) Public hydrant spacing shall meet requirements of ECDC 19.25. X c) Provide water service stub to each Lot X d) Connect to public water system. X X e) Install storz adapter on existing fire hydrant, as required. X 9. Sanitary Sewer System Improvements (COE): a) Applicant must meet requirements set forth by City of Edmonds for connection to public sewer system. X b) Provide new service lateral from City's sanitary sewer main to development. X X i. Provide 6" sewer lateral from main to property line/edge of easement ii. Provide 4" side sewer to individual lots. iii. Where side sewer provides service to more than one lot, it shall be a minimum of 6". c) Connect to public sewer system. X X 10. Stormwater System Improvements: a) Provide a Stormwater Management Report and Site Plan that shows compliance with the 2014 Department of Ecology Stormwater Manual as amended by ECDC X 18.30 and the Stormwater Addendum. i. Stormwater management design shall account for proposed short plat improvements, including improvements within the right-of-way and future lot development. ii. Stormwater management system to be located on private property. b) Construct privately owned and maintained stormwater management system. X i. Construction of Low hnpact Development BMP's for individual lots may be deferred to the single family building permit with condition of construction deferral noted as such on the face of the plat map. ii. Stormwater management system to be located on private property. c) Connect all new hard surfaces to stormwater management system(s) as required. X X d) Provide storm sewer stub to all proposed lots, as applicable. X e) Connect to public storm system, as applicable. X X 11. Under round Wiring (per Ord. 1387): a) Required for all new services. X X 2 of 3 ENGR RQMNTS - Ryker Young Short Plat printed 12/7/2018 Required as a Condition of Subdivision Required as a Condition of Building Permit Requirement Already Satisfied 12. Excavation and Grading (per IBC) a) Submit a grading plan as part of engineered site plan. b) Submit grading plan for foundations with building permit. X X X 13. Si na a and Striping (per City Engineer): a) All signs shall be vinyl letters and to City standards. b) Install fire and aid address signage. X X 14. Survey Monumentation (per Ord., Sect. 12.10.120): a) N/A 15. As -built Drawings(per City Engineer): a) Provide an as -built drawing of all street and utility improvements both in electronic format as well as a hard copy. X X' 6. Other Requirements: a) Plat showing lots, easements, legals, survey information X X b) Legal documents for each lot X c) Field stake lot comers (by professional surveyor) X d) Field stake utility stubs at property lines X e) Clustered mailbox location per Postmaster X f) Maintenance agreements X g) Transportation Impact Fee Analysis X 17. Engineering Fees: a) Storm system general facility charge for shared hard surface areas X b) Storm system general facility charge for each new lot X c) Sewer general facility charge X d) Water general facility charge X e) Water meter fee X f) Transportation impact fee per each new SFR X g) Parks impact fees X h) Short Plat civil plan review fee X i) Right -of -Way Construction Permit X j) Inspection fees X 3 of 3 ENGR RQMNTS - Ryker Young Short Plat printed 12/7/2018