Loading...
Engineering Prelim Comments 3-Spence-PLN20170057.pdfMEMORANDUM REQUEST FOR ADDITIONAL INFORMATION Date: April 11, 2018 To: Brad Shipley, Associate Planner From: Jeanie McConnell, Engineering Program Manager Subject: PLN20170057, Spence 2-lot short plat 17606 72°d Ave W The comments provided below are based upon review of the preliminary development plan & preliminary drainage report for the subject short plat. Additional information is requested from the applicant at this time in order to continue review of the application and provide preliminary approval. Please ask the applicant to provide a written response to each of the comments below and revise and resubmit plans accordingly. Comments 1 December 27, 2018 Comments 2 — April 11, 2018 Comments 3 — May 23, 2018 GENERAL 1. ok 2. ok UTILITIES 3. ok 4. ok 5. ok 6. May 23, 2018 — No exceptions were taken with regards to the stormwater engineer comments of April 11, 2018 and the reposnse letter states revision were made, however, the text of the report was not updated. Please provide an updated report accordingly. April 11, 2018 — Refer to attached plan review comments by City Stormwater Engineer, Zachary Richardson. Please contact Zack directly at 425-771-0220 or by email at City of Edmonds Zachary.richardson(kedmondswa.gov with any specific questions you may have regarding his comments. December 27, 2018 comment - Please submit a stormwater report consistent with the 2012/14 Stormwater Manual and the city's Stormwater Addendum. Please include full infiltration calculations (see Appendix B of the Addendum to determine the specific testing requirements). Ensure the stormwater management design for the proposed single family lot is reflective of the eve line of the house, driveway, and any patios, walkways, etc. Show a stormwater mitigation system on the plans based on the infiltration rate and the infeasibility checklists. If there will be an outfall, show what it connects to and where. Plans show connection to a catch basin that is not on the city system. Please show the catch basin as proposed. Provide approximate invert elevations for all points of connection as well as length and size of pipe, including the City storm system inverts if applicable. Thank you.