On Thursday, December 4, 2014 4:26 PM, Julian Liu <julianliu100@yahoo.com> wrote:
Hi Chuck,
Yes, I agree. The word "upper" in the first line of Page 8 of my 9/30/2014 geotechnical report should
be changed to "lower". Will you accept the acknowledgement with this email?
Julian Liu
LIU & ASSOCIATES, INC.
19213 Kenlake Place NE
Kenmore, WA 98028
(Office) 425-483-9134 (Cell) 206-354-1291
On Thursday, December 4, 2014 10:58 AM, "Miller, Chuck" <Chuck.Miller@edmondswa.gov> wrote:
I think you need to look at page 8, as noted in the plan review comment letter. Right at the top of the page it
states “Reinforced backfill of the upper block wall should be constructed with structural fill.”. That requirement
does not appear to be consistent with the information provided elsewhere in the report.
From: Julian Liu \[mailto:julianliu100@yahoo.com\]
Sent: Thursday, December 04, 2014 9:41 AM
To: almark_corporation@frontier.com; Miller, Chuck
Subject: Re: BLD2014-1052 Almark SFR plan review comments Julian on your report for the 8040 Cyrus job the plan
reviewer had comments that may need to be changed
Hi Mark and Chuck,
I've reviewed twice the "Wall Backfill" section on Page 3 and "Plate 2" of my 9/30/2014 report and
found no contraction or ambiguity regarding the requirement of the lower wall backfill. It is clearly
stated under the "Wall Backfill" section that "
The taller lower wall is to be
excavated and backfilled with geogrid mesh embedded in the backfill
to increase stability of the wall. This reinforced wall backfill
should be constructed with structural fill in accordance with
recommendations under the STRUCTURAL FILL section of this report."
Plate 2 also clearly calls out the lower wall backfill to be
structural fill.
Julian Liu
LIU & ASSOCIATES, INC.
19213 Kenlake Place NE
Kenmore, WA 98028
(Office) 425-483-9134 (Cell) 206-354-1291
On Thursday, December 4, 2014 6:44 AM, "almark_corporation@frontier.com" <almark_corporation@frontier.com> wrote:
--- On Wed, 12/3/14, Miller, Chuck <Chuck.Miller@edmondswa.gov> wrote:
> From: Miller, Chuck <Chuck.Miller@edmondswa.gov>
> Subject: BLD2014-1052 Almark SFR plan review comments
> To: "'almark_corporation@frontier.com'" <almark_corporation@frontier.com>
> Date: Wednesday, December 3, 2014, 3:47 PM
>
>
>
>
>
>
>
>
> Good
> afternoon,
>
>
> Please find
> attached the Building Division plan review comments for your
> project. They were to have been sent to you on
> November 25th, but I can find no record of that
> happening.
>
>
> Reviews by
> other divisions, such as Engineering, Planning, or Fire, may
> result in additional comments.
>
>
> Feel free
> to contact me if you have any questions.
>
>
> Chuck
> Miller, Plans Examiner
> chuck.miller@edmondswa.gov
>
> 425-771-0220 x 1314
>
>
> City of
> Edmonds
> Development
> Services Department
> Building
> Division
> 121
> 5th Avenue N
> Edmonds, WA
> 98020
> www.edmondswa.gov
>
>
>
>
>