Graphite Studio 202 Main 1.docxMEMORANDUM
September 19, 2019
TO:Pelletier Architects
FROM:Steve Fisher, City of Edmonds Public Works, 425-771-0235
RE:Plan review for trash enclosure
BLD20191111 – Graphite Art Studio, 202 Main St., Edmonds
The resubmitted plan for the trash enclosure shows a new location that is now adjacent to the alleyway to the south. This location is acceptable but needs to have the enclosure to be
orientated to have a clear 14’ minimum opening directly to the alley.
Instead of two gate sections, the center post must be eliminated to allow the full clear 14’ minimum opening, thus utilizing one pair of gates.
Or, as the waste hauler commented, it would be ideal to have a wide roll-up door to access the enclosure. This would eliminate gate sections swung into the alley, therefore avoiding
making the alley narrower and harder for servicing.