PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: January 17, 2008
TO: Atilla Hegyi
st
19620 81 Place W
Edmonds, WA 98026
FROM: Ann Bullis, Assistant Building Official
RE: Plan Check # 2007-0795
Project: Hegyi Remodel/Addition
st
Project Address: 19620 81 Place W
During review of the plans for the above noted project, it was found that the following information,
clarifications or changes are needed. Provide written responses to each comment and where
changes can be found on the plans. Please resubmit to Theresa Umbaugh, Permit Coordinator.
1.Regarding your request to defer response to previous item 3, 4 & 5 in Building Division plan
review comments dated 10/5/2007, as explained in City letter dated 9/24/2007, if you were
unable to obtain City or County permit records for the kitchen addition, then the addition must
be included with this permit. The Stop Work order will not be lifted until all issues are resolved
and permit(s) issued. The design (structural and architectural) of the kitchen and remodel of the
living/dining/den/entry area must be reviewed at the same time. For clarification to your
statement in your response letter (dated January 10, 2008) regarding item 3g, the area of the
kitchen addition shown the site plan approved for the roof cover (permit #1998-0031) was
labeled on the plan submitted to the City as existing house, and in no way gave approval for
the kitchen addition.
2.One set of the structural calculations/plans submitted to the City must be wet signed by the
engineer of record. Have the engineer include as part of his stamped/signed calculations:
a.The full scope of his design, and
b.A reduced copy of the plans that support the structural design calculations (or he can
stamp the project set of plans). As I explained at our previous meeting, the engineer
will need fully dimensioned framing plans to scale to do the structural calculations,
so item #2 of the 10/5/07 comments is still required.