DIBBLE ENGINEERS INC. Structural
Professional Structural Engineering Services
' Review
Summary
Edmonds Center Townhomes, HOA
Attn: David Thiele, HOA President
3801 Kromer Ave,
Everett, WA 98201
September 25, 2014
DEI Project: 14-402
Re: Structural Review — Rot damage decay and shoring
Site Address: 624 Daley Street Unit 1
Edmonds, WA 98020
Snohomish County Assessor Parcel # 007 372 00100100
Dear Mr. Thiele:
In coordination with the structural damage that was identified during an exterior paint and caulking project, DEI has reviewed
and recommended immediate shoring to prevent a collapse from occurring. The conditions identified are located at the HOA's
the north-west corner at an existing (4) 2x6 support framing beam that aligns under a bearing wall. The deck corner damage is
the result of a water leak that contributed to a severe wood rot and decay internal of the framing floor and wall and created
significant decay damage. Based on the extent of damage, decay, and debris from the rot, the building corner and deck are in a
state of collapse.
DEI completed a site visit on September 25, 2014 to review the installed and completed shoring, consisting of a sleeper GLB 5-
I/5x12" beam inset under the decay area, with a series of 2x6 shoring studs. The studs were braced in the weak axis at
approximately at 4' on center to prevent lateral buckling. The shoring as completed provides a redundant load path for the
building corner to allow occupancy to remain. The condition as noted will need a structural replacement beam and a permit
with the city.
The excessive decay damage will require a replacement of the bundled (4) 2x6 beam which spans approximately six feet from a
post internal of the garage out to the face of the garage. The location'of the beam under the bearing wall framed above will
require short term wall support, and removal of the damaged and decayed deck sheathing. The full extent of the decay is not yet
exposed, but we would expect that the garage header and support studs may also need to be replaced. With the current shoring
in place, DEI recommends further exposing the full extent of the damage and decay for review by the Architect and Engineer
prior to the repair and replacement.
Based on the extent of the decay, DEI recommends the City be notified for their review and permitting of the repairs. Mr.
David Thiele, the HOA president concurs. Please contact us with any questions or clarifications.
Sincerely,
DIBBLE ENGINEERS, INC.
Robb A. Dibble, RE
Prinicpal
CC: Keith Soltner, AIA, Soltner Group Architects
City of Edmonds — Builidng Official,
Attachments: Partial framing plan — Sketch
A.. jo
wASHy
o�
w
1�
.� �3745
TONAL
I
y
1
1029 Market Street Page 1 of I A 425-828-4200
Kirkland, WA 98033 F. 425-827-6131
DIBBLE ENGINEERS, I N C Project No. Sheet No.
Project Date
Subject �'I'Z AM ► I�L�, � y� U -r' By
Of
{
-. _.._
�A1-1 A61t oc-A77Oh,3
C,ly'jC
0r
-<i+vrzj"'-� -13cccXO c��
S %.'r
INV2oI4-oDL+3
Johns, Kristin
From: Bjorback, Leif
Sent: Friday, September 26, 201410:51 AM
To: Johns, Kristin
Subject: FW: Edmonds Center Townhomes
Attachments: 2014-09-25 005.JPG; 2014-09-25 011.JPG; 2014-09-25 019.JPG; 2014-09-25 021.JPG; DEI
Review 9-26-14.pdf
Will you please start an INV on this address and attach -this email info? Thanks
Leif
From: Robb Dibble [mailto:Robb@DibbleEngineers.com]
Sent: Friday, September 26, 2014 9:31 AM
To: Josh Twigg; Bill Bogen; 'Emily Hill'
Cc: 'Keith Soltner'; Dawn Fraser; Mike Johnson; Bjorback, Leif
Subject: RE: Edmonds Center Townhomes
Good Morning,
Thank you David for the time to provide access.
Thank you Josh for the emergency shoring —the building is stabilized to allow for continued occupancy of the unit above.
City Building Official Mr. Bjorback, please see the attached structural review summary and framing sketch with the
attached photos for the substantial decay area identified that will need support of the wall framing above in the process
of completing the beam replacement.
This letter is to confirm that shoring is in place, and that the building is stabilized, and to alert the City of the issue, and
that it is being properly handled.
Thanks,
Robb A. Dibble, PE
Principal
Dibble Engineers, Inc.
Professional Structural Enoisearinn Smicft
1029 Market Street, Kirtland, WA 98033
office: (425) 828-4200
tax: (425) 827-6131
www.dibbleeneineers.com
office ext.222
From: Josh Twigg [mailto:josh@ruffconstruction.com]
Sent: Thursday, September 25, 201412:07 PM
To: Bill Bogen; 'Emily Hill'
Cc: 'Keith Soltner'; Dawn Fraser; Mike Johnson; Robb Dibble
Subject: RE: Edmonds Center Townhomes
I called Dave Thiele this morning and received verbal authorization to engage DEI to review the shoring per the DEI
proposal. Robb will attend a meeting at the project site this morning at 11am with Dave and Emily.
Best Regards,
Bill Bogen, Sr. Project Manager
Soltner Group Architects
206.547.7288 Office
206.384.1548 Mobile
www.soltne[group.com
From: Bill Bogen [mailto:Bill@soltnergroup.coml
Sent: Thursday, September 25, 2014 8:31 AM
To: 'Emily Hill'
Cc: Keith Soltner; 'Josh Twigg'; 'Dawn Fraser'; 'Mike Johnson'; 'Robb Dibble'; bill@soltneraroug.com
Subject: Edmonds Center Townhomes
Hello Emily,
I have attached a proposal from Dibble Engineers to assist in the repair of the damage at the Unit 1 garage. I
have also mailed a copy to Dave Thiele. We work closely with Robb Dibble and recommend DEI be approved to
assist in this repair.
Please call with any questions.
RUFF crew: How is the shoring progressing?
Best Regards,
Bill Bogen, Sr. Project Manager
Soltner Group Architects
206.547.7288 Office
206.384.1548 Mobile
www.soltnergroup.com
3
Good afternoon,
Attached are eight (8) pictures of the existing joist(s) once the drywall was removed as well as the erected shore wall. If
there are any questions that either you may have please do not hesitate in contacting me.
Thank you in the opportunity in providing our services,
Joshua J. Twigg, General Manager
R.C.I. 6505 Place SE, Woodinville, WA.
Office: 425.487.0702 I Fax: 425.487.0772
�r�ry�r RUFFCONSTRUCTION,COM
Celebrating 27 Years as Your Multi -Family Renovation Experts!
MV
From: Josh Twigg
Sent: Thursday, September 25, 2014 10:27 AM
To: 'Bill Bogen'; 'Emily Hill'
Cc: 'Keith Soltner; Dawn Fraser; Mike Johnson; 'Robb Dibble'
Subject: RE: Edmonds Center Townhomes
Good morning,
I am awaiting photo's from my crew that installed/erected the shore wall, as soon as I receive them I will immediately
forward to all parties.
Mr. Dibble; if at your meeting this morning in review of the shore wall there are any modifications that are felt needed
to be made please let me know and I will act accordingly/expeditiously in getting them taken care of. The client is in
great hands with both SGA and DEI, we at Ruff look forward in potentially assisting the two of you moving forward with
the needed repairs.
Thank you all for your time and please do not hesitate in contacting me if I may be of any assistance (cell; 425.351.2032),
Joshua). Twigg, General Manager
R.C.I.6505 233111 Place SE, Woodinville, WA.
Office: 425.487.0702 1 Fax: 425.487.0772
W WVV. RUFFCONSTRUCTI ON .COM
Celebrating 27 Years as Your Multi -Family Renovation Experts!
From: Bill Bogen fmailto:Bi[IC&soltnergrouo.coml
Sent: Thursday, September 25, 2014 10:19 AM
To: 'Emily Hill'
Cc: 'Keith Soltner'; Josh Twigg; Dawn Fraser; Mike Johnson; 'Robb Dibble'; 'Bill Bogen'; bill@soltnergroup.com
Subject: RE: Edmonds Center Townhomes
All,
Just to keep everyone in the loop....