Knob Hill-Approved Cost Estimate.pdfSite Improvement Bond Quantity Worksheet Web date: 12/02/2008
LQ King County
Department of Development & Environmental Services
900 Oakesdale Avenue Southwest
Renton, Washington 98057-5212 For alternate formats, call 206-296-6600.
206-296-6600 TTY 206-296-7217
Project Name: Knob Hill Short Plat Date: 7-13-17
Location: 19125 94th Ave W Edmonds. WA 98020 Project No.:
Activity No.:
Clearing greater than or equal to 5,000 board feet of timber?
yes
If yes,
Forest Practice Permit Number:
(RCW 76.09)
Page 1 of 9
X no
w:a iwc;c �Iwo R-w
Note: All prices include labor, equipment, materials, overhead and
profit. Prices are from IRS Means data adjusted for the Seattle area
or from local sources if not included in the IRS Means database.
1
li-wks-sbq.xls 'el i ,
5 1+6q
Unit prices updated: 02/12/02
Version: 11 /26/2008
Report Date: 12/02/2008
Site Improvement Bond Quantity Worksheet Web date: 12/02/2008
Reference #
Unit
Price
Unit
Quantity
# of
Applications
Cost
EROSION/SEDIMENT CONTROL
Number
Backfill & compaction -embankment
ESC-1
$ 5.62
CY
Check dams, 4" minus rock
ESC-2
SWDM 5.4.6.3
$ 67.51
Each
Crushed surfacing 1 1/4" minus
ESC-3
WSDOT 9-03.9(3)
$ 85.45
CY
Ditching
ESC-4
$ 8.08
CY
Excavation -bulk
ESC-5
$ 1.50
CY
38
$57.00
Fence, silt
ESC-6
SWDM 5.4.3.1
$ 1.38
LF
Fence, Temporary (NGPE)
ESC-7
$ 1.38
LF
Hydroseeding
ESC-8
SWDM 5.4.2.4
$ 0.59
SY
Jute Mesh
ESC-9
SWDM 5.4.2.2
$ 1.45
SY
Mulch, by hand, straw, 3" deep
ESC-10
SWDM 5.4.2.1
$ 2.01
SY
20
$40.20
Mulch, by machine, straw, 2" deep
ESC-11
SWDM 5.4.2.1
$ 0.53
SY
Piping, temporary, CPP, 6"
ESC-12
$ 10.70
LF
Piping, temporary, CPP, 8"
ESC-13
$ 16.10
LF
Piping, temporary, CPP, 12"
ESC-14
$ 20.70
LF
Plastic covering, 6mm thick, sandbagged
ESCA5
SWDM 5.4.2.3
$ 2.30
SY
Rip Rap, machine placed; slopes
ESCA 6
WSDOT 9-13.1(2)
$ 39.08
CY
Rock Construction Entrance, 50'x15'x1'
ESCA7
SWDM 5.4.4.1
$ 1,464.34
Each
Rock Construction Entrance, 100'x15'x1'
ESCA8
SWDM 5.4.4.1
$ 2,928.68
Each
Sediment pond riser assembly
ESCA9
SWDM 5.4.5.2
$ 1,949.38
Each
Sediment trap, 5' high berm
ESC-20
SWDM 5.4.5.1
$ 17.91
LF
Sed. trap, 5' high, riprapped spillway berm section
ESC-21
SWDM 5.4.5.1
$ 68.54
LF
Seeding, by hand
Sodding, 1" deep, level ground
ESC-22
SWDM 5.4.2.4
$ 0.51
SY
ESC-23
SWDM 5.4.2.5
$ 6.03
SY
Sodding, 1" deep, sloped ground
ESC-24
SWDM 5.4.2.5
$ 7.45
SY
TESC Supervisor
ESC-25
$ 74.75
HR
10
$747.50
Water truck, dust control
ESC-26
SWDM 5.4.7
$ 97.75
HR
5
$488.75
WRITE -IN -ITEMS **** (see page 9)
Filter Socks
$100.00
Each
3
$300.00
ESC SUBTOTAL:
30% CONTINGENCY & MOBILIZATION:
ESC TOTAL:
COLUMN:
Page 2 of 9
li-wks-sbq.xls
$ 1664 -
$ 500 -
$ 2164 -
A
IV 50' • bO
Unit prices updated: 02/12/02
Version: 11 /26/2008
Report Date: 12/02/2008
Site Improvement Bond Quantity Worksheet
Web date: 12/02/2008
Existing
Right -of -Way
Future Public
Road Improvements
& Drainage Facilities
Private
Improvements
Quantity Completed
(Bond Reduction)'
Quant.
Unit Price
Unit
Quant.
Cost
Quant.
Cost
Quant.
Cost
Com lete
Cost
GENERAL ITEMS
No.
Backfill & Compaction- embankment
GI - 1
1 $ 5.62
CY
Backfill & Compaction- trench
GI - 2
$ 8.53
CY
Clear/Remove Brush, by hand
GI - 3
$ 0.36
SY
Clearing/Grubbing/Tree Removal
GI - 4
$ 8,876.16
Acre
Excavation - bulk
GI - 5
$ 1.50
CY
Excavation - Trench
GI - 6
1 $ 4.06
CY
Fencing, cedar, 6' high
GI - 7
$ 18.55
LF
Fencing, chain link, vinyl coated, 6' hi i
GI - 8
$ 13.44
LF
Fencing. chain link, gate. vinyl coated.
GI - 9
$ 1.271.81
Each
Fencing, split rail, 3' high
GI - 10
$ 1212
LF
Fill & compact - common barrow
GI - 11
$ 2257
CY
Fill & compact - gravel base
GI - 12
$ 25.48
CY
60
$1528.80
Fill & compact - screened topsoil
GI - 1'
$ 37.85
CY
Gabion, 12" deep, stone filled mesh
GI - 14
$ 5431
SY
Gabion, 18" deep, stone filled mesh
GI - 15
$ 7485
SY
Gabion, 36" deep, stone filled mesh
GI - 16
$ 132.48
SY
Grading, fine, by hand
GI - 17
$ 2.02
SY
Grading, fine, with grader
GI - 18
$ 0.95
SY
Monuments, 3' Ion_
GI - 19
$ 135.13
Each
Sensitive Areas Sign
GI - 20
$ 2.88
Each
Sodding, 1" deep, sloped ground
GI - 21
$ 7.46
SY
Surveying, line & grade
GI - 22
$ 788.26
Day
1
$788.26
Surveying, , lot location/lines
GI - 23
$ 1,556.64
Acre
Traffic control crew ( 2 fla gers 1
GI - 24
$ 85.18
HR
6
$511.08
Trail. 4" chipped wood
GI - 25
$ 7.59
SY
Trail, 4" crushed cinder
GI - 26
$ 8.33
SY
Trail, 4" top course
GI - 27'
$ 8.19
SY
Wall, retaining, concrete
GI - 28
$ 44.16
SF
Wall, rockery
GI - 29
$ 9.49
1 SF
Page 3 of 9
SUBTOTAL
$2829
Unit prices updated: 02/12/02
*KCC 27A authorizes only one bond reduction Version: 11 /26/08
li-wks-sbq.xls Report Date: 12/02/2008
Site Improvement Bond Quantity Worksheet
Web date: 12/02/2008
Existing
Right-of-way
Future Public
Road Improvements
& Drainage Facilities
Private
Improvements
Bond Reduction*
Quant.
Unit Price
Unit
Quant. Cost
Quant. Cost
Quant. Cost
Complete
Cost
ROADIMPROVEMENT
No.
AC Grinding, 4' wide machine < 1000s
RI - 1
$ 28.00
SY
72
$2016.00
AC Grinding, 4' wide machine 1000-200
RI - 2
$ 15.00
SY
AC Grinding, 4' wide machine > 2000s
RI -3
$ 7.00
SY
AC Removal/Disposal/Repair
RI - 4
$ 67.50
SY
Barricade, type I
RI - 5
$ 30.03
LF
Barricade, type III ( Permanent)
RI - 6
$ 4505
LF
Curb & Gutter, rolled
RI - 7
$ 17.00
LF
Curb & Gutter, vertical
RI - 8
$ 12.50
LF
Curb and Gutter, demolition and dispos
I RI - 9
S 18.00
LF
Curb, extruded asphalt
RI - 10
$ 5.50
LF
Curb, extruded concrete
RI - 11
$ 7.00
LF
Sawcut, asphalt, 3" depth
RI - 12
$ 1.85
LF
590
$1091.50
includes all 3 roads
Sawcut, concrete, per 1" depth
RI - 13
$ 1.69
LF
Sealant, asphalt
RI - 14
$ 1.25
LF
Shoulder, AC, ( see AC road unit price
RI - 15
$ -
SY
Shoulder, gravel. 4" thick
RI - 16
$ 15.00
SY
Sidewalk, 4" thick
RI - 17
$ 35.00
SY
Sidewalk, 4" thick, demolition and dispo
RI - 18
$ 29.50
SY
Sidewalk, 5" thick
RI - 19
$ 3850
SY
Sidewalk, 5" thick, demolition and dis o
RI - 20
$ 37.50
SY
Sign, handicap
RI - 21
S 85.28
Each
Striping. per stall
RI - 22
$ 5.82
Each
Striping, thermoplastic, ( for crosswalk) I
RI - 23
$ 2.38
SF
Stripinq, 4" reflectorized line JR1
- 24
$ 0.25 1
LF
Page 4 of 9
SUBTOTAL
$3108
Unit prices updated: 02/12/02
*KCC 27A authorizes only one bond reduction Version: 11 /26/08
li-wks-sbq.xls Report Date: 12/02/2008
Site Improvement Bond Quantity Worksheet
Web date: 12/02/2008
Existing
Right-of-way
Future Public
Road Improvements
& Drainage Facilities
Private
Improvements
Bond Reduction*
Quant.
Unit Price
Unit
Quant. Cost
Quant. I Cost
Quant. Cost
Complete
Cost
ROAD SURFACING (4" Rock = 2.5 base & 1.5" top course) For'93 KCRS (6.5" Rock= 5" base & 1.5" top course)
For KCRS '93, (additional 2 5" base) ad
RS - 1
$ 3.60
SY
AC Overlay, 1.5" AC
RS - 2
$ 11.25
SY
AC Overlay, 2" AC
RS - 3
$ 15.00
SY
258
$3870.00
includes all 3 roads
AC Road, 2", 4" rock, First 2500 SY
RS - 4
$ 21.00
SY
AC Road, 2", 4" rock, Qty. over 2500SY
RS - 5
$ 19.00
SY
AC Road, 3", 4" rock, First 2500 SY
RS - 6
$ 23.30
SY
AC Road, 3", 4" rock, Qtv. over 2500 S)r
RS - 7
$ 21.00
SY
AC Road, 5", First 2500 SY
RS - 8
$ 2760
SY
AC Road, 5", Qty. Over 2500 SY
RS - 9
$ 25.00
SY
AC Road, 6". First 2500 SY
RS - 1(
$ 3310
SY
AC Road, 6", Qty. Over 2500 SY
RS - 1'
$ 30.00
SY
Asphalt Treated Base, 4" thick
RS - 1:
$ 2000
SY
Gravel Road, 4" rock. First 2500 SY
RS - 1;
$ 15.00
SY
Gravel Road, 4" rock, Qty. over 2500 S`,
S - 1Z
$ 8.50
SY
PCC Road, 5", no base, over 2500 SY
RS - 1,11
$ 27.00
SY
PCC Road, 6", no base.. over 2500 SY
IRS - 1 E
$ 25.50
SY
Thickened Edge
RS - 1
$ 8.60
LF
513
$4411.80
includes all 3 roads
Page 5 of 9
SUBTOTAL
$8282
Unit prices updated: 02/12/02
'KCC 27A authorizes only one bond reduction. Version: 11 /26/08
li-wks-sbq As Report Date: 12/02/2008
Site Improvement Bond Quantity Worksheet
Web date: 12/02/2008
Existing
Right-of-way
Future Public
Road Improvements
& Drainage Facilities
Private
Improvements
Bond Reduction*
Quant.
Unit Price
I Unit
Quant. Cost
Quant. I Cost
Quant. Cost
ComDlete
Cost
DRAINAGE (CPP = Corrugated Plastic Pipe, N12 or Equivalent) For Culvert prices. Average of 4' cover was assumed. Assume perforated PVC is same price as solid pipe.
Access Road, R/D
D - 1
S 21.00
SY
Bollards - fixed
D - 2
$ 240.74
Each
Bollards - removable
D - 3
$ 452.34
Each
* (CBs include frame and lid)
CB Type l
D- 4
S 1,257.64
Each
CB Type IL
D - 5
$ 1,433.59
Each
CB Type ll, 48" diameter
D - 6
$ 2,033.57
Each
for additional depth over 4'
D - 7
$ 436.52
FT
CB Type II, 54" diameter
D - 8
$ 2,192 54
Each
for additional depth over 4'
D - 9
$ 486.53
FT
CB Type II. 60" diameter
D - 10
$ 2,351 52
Each
for additional depth over 4'
D - 11
$ 536.54
FT
CB Type ll, 72" diameter
D - 12
$ 3.212.64
Each
for additional depth over 4'
D - 13
$ 692.21
FT
Through -curb Inlet Framework (Add)
D - 14
$ 366.09
Each
Cleanout, PVC, 4"
D - 15
$ 130.55
Each
Cleanout, PVC, 6"
D - 16
$ 174.90
Each
Cleanout, PVC, 8"
D - 17
$ 224.19
Each
Culvert, PVC, 4"
D - 18
$ 8.64
LF
Culvert, PVC, 6"
D - 19
$ 12.60
LF
Culvert, PVC, 8"
D - 20
$ 13.33
LF
Culvert, PVC, 12"
D - 21
$ 21.77
LF
Culvert, CMP, 8"
D - 22
$ 17.25
LF
Culvert, CMP, 12"
D - 23
$ 26.45
LF
Culvert, CMP, 15"
D - 24
$ 32.73
LF
Culvert, CMP, 18"
D - 25
$ 3774
LF
Culvert, CMP, 24"
D - 26
$ 5333
LF
Culvert, CMP, 30"
D - 27
$ 71.45
LF
Culvert, CMP, 36"
D - 28
$ 112.11
LF
Culvert, CMP, 48"
D - 29
$ 14083
LF
Culvert, CMP, 60"
D - 30
$ 235.45
LF
Culvert, CMP, 72"
D - 31
$ 302 58
LF
Page 6 of 9
SUBTOTAL
Unit prices updated: 02/12/02
*KCC 27A authorizes only one bond reduction. Version: 11 /26/08
li-wks-sbq As Report Date: 12/02/2008
Site Improvement Bond Quantity Worksheet
Web date: 12/02/2008
DRAINAGE CONTINUED
Existing
Right-of-way
Future Public
Road Improvements
& Drainage Facilities
Private
Improvements
Bond Reduction's
Quant.
No.
I Unit Price
Unit
Quant.
Cost
Quant,
Cost
Quant.
Cost
Com fete
Cost
Culvert, Concrete, 8"
D - 32
$ 21.02
LF
Culvert, Concrete, 12"
D - 33
$ 30.05
LF
Culvert, Concrete, 15"
D - 34
$ 37.34
LF
Culvert, Concrete, 18"
D - 35
$ 44.51
LF
Culvert, Concrete. 24"
D - 36
$ 61 07
LF
Culvert, Concrete, 30"
D - 37
$ 104.18
LF
Culvert, Concrete, 36"
D - 38
$ 137.63
LF
Culvert, Concrete, 42"
D - 39
$ 158.42
LF
Culvert, Concrete, 48"
D - 40
$ 175.94
LF
Culvert, CPP, 6"
D - 41
$ 10.70
LF
Culvert, CPP, 8"
D - 42
$ 16.10
LF
Culvert, CPP, 12"
D - 43
$ 2070
LF
Culvert, CPP, 15"
D - 44
$ 23.00
LF
Culvert, CPP, 18"
D - 45
$ 2760
LF
Culvert, CPP, 24"
D - 46
$ 36.80
LF
Culvert, CPP, 30"
D - 47
$ 4830
LF
Culvert, CPP, 36"
D - 48
$ 55.20
LF
Ditching
D - 49
$ 8.08
CY
Flow Dispersal Trench (1,436 base+)
D - 50
$ 2599
LF
French Drain (3' depth)
D - 51
$ 22.60
LF
Geotextile, laid in trench, polypropylene
D - 52
$ 2.40
SY
Infiltration pond testing
D - 53
$ 74.75
HR
Mid -tank Access Riser, 48" dia, 6' deep
D - 54
$ 1,605.40
Each
Pond Overflow Spillway
D - 55
$ 1401
SY
Restrictor/Oil Separator, 12"
D - 56
$ 1,045.19
Each
Restrictor/Oil Separator. 15"
D - 57
$ 1.095.56
Each
Restrictor/Oil Separator, 18"
D - 58
$ 1,146.16
Each
Ri ra , placed
D - 59
$ 39.08
CY
Tank End Reducer (36" diameter)
D - 60
$ 1,000.50
Each
Trash Rack, 12"
D - 61
$ 211.97
Each
Trash Rack, 15"
D - 62
$ 237.27
Each
Trash Rack, 18"
D - 63
$ 268.89
Each
Trash Rack, 21"
1 D - 64
$ 306.84
Each
Page 7 of 9
6-1glCel/_11
Unit prices updated: 02/12/02
'KCC 27A authorizes only one bond reduction. Version: 11/26/08
li-wks-sbq.xls Report Date: 12/02/2008
Site Improvement Bond Quantity Worksheet
Web date: 12/02/2008
Existing
Right-of-way
Future Public
Road Improvements
& Drainage Facilities
Private
Improvements
Bond Reduction*
Quant.
Unit Price
Unit
Quant. Price
Quant. Cost
Quant. Cost
Complete
Cost
PARKING LOT SURFACING
No.
2" AC, 2" top course rock & 4" borrow
PL - 1
$ 21 00
SY
2" AC, 1.5" top course & 2.5" base cou
PL - 2
$ 2800
SY
4" select borrow
PL - 3
$ 4.55
SY
1.5" top course rock & 2.5" base course
PL - 4
$ 1141
SY
UTILITY POLES & STREET LIGHTING Utility pole relocation costs must be accompanied bfranchise Utility's Cost Statement
Utility Pole(s) Relocation
5P-1
Lump Sum
Street Light Poles w/Luminaires
UP-2
Each
WRITE -IN -ITEMS
(Such as detention/water quality vaults.)
No.
6" PVC side sewer
wl -1
$52
LF
60
$3120
Sewer Main connection
WI - 2
$1300
EA
2
$2600
Side Sewer Cleanouts
WI - 3
$800
EA
2
$1600
Rockery Demo/Rebuild
WI - 4
$40
LF
38
$1520
(NW corner Lot 3)
WI - 5
FT
Cones, Signage, etc.
WI - 6
$500
Landscaping - replace
WI - 7
$1000
Mailboxes
WI - 8
$900
WI-9
megalugs & pipe extension
wi-io 1
$1800
1
$1800
Page 8 of 9
SUBTOTAL
SUBTOTAL (SUM ALL PAGES)
30% CONTINGENCY & MOBILIZATION
$13,040
$27,259
$8,178
GRANDTOTAL: $35,437
COLUMN: B
-I& �L, 5Z .
C
D E
Unit prices updated: 02/12/02
*KCC 27A authorizes only one bond reduction. Version: 11 /26/08
li-wks-sbq.xls Report Date: 12/02/2008
Site Improvement Bond Quantity Worksheet Web date: 12/02/2008
Original bond computations prepared by:
Name: Date:
PE Registration Number: Tel. #:
Firm Name:
Address: Project No:
ROAD IMPROVEMENTS & DRAINAGE FACILITIES FINANCIAL GUARANTEE REQUIREMENTS
PERFORMANCE BOND* PUBLIC ROAD & DRAINAGE
AMOUNT BOND* AMOUNT MAINTENANCE/DEFECT BOND*
Stabilization/Erosion Sediment Control (ESC)
(A)
$
2,164 -
Existing Right -of -Way Improvements
(B)
$
35,437 -
Future Public Road Improvements & Drainage Facilities
(C)
$
-
Private Improvements
(D)
$
-
Calculated Quantity Completed
Total Right -of Way and/or Site Restoration Bond*/**
(A+B)
$
37,601 -
(First $7,500 of bond* shall be cash.
Performance Bond* Amount (A+B+C+D) = TOTAL
(T)
S
37,601 -
Minimum bond' amount is 1000
Reduced Performance Bond* Total ***
���i 0
Maintenance/Defect Bond* Total
{��
I
NAME OF PERSON PREPARING BOND* REDUCTION:
REQUIRED AT RECORDING OR
TEMPORARY OCCUPANCY ***
(E) $
T x 0.30 $
(T-E) $ Use larger of Tx30% or T-E
OR
Date:
(B+C) x
0.25 = $
* NOTE: The word "bond" as used in this document means any financial guarantee acceptable to King County.
*' NOTE: KCC 27A authorizes right of way and site restoration bonds to be combined when both are required.
The restoration requirement shall include the total cost for all TESC as a minimum, not a maximum In addition, corrective work, both on- and off -site needs to be included
Quantities shall reflect worse case scenarios not just minimum requirements. For example, if a salmonid stream may be damaged, some estimated costs for restoration
needs to be reflected in this amount. The 30% contingency and mobilization costs are computed in this quantity.
*** NOTE: Per KCC 27A, total bond amounts remaining after reduction shall not be less than 30% of the original amount (T) or as revised by major design changes.
SURETY BOND RIDER NOTE: If a bond rider is used, minimum additional performance bond shall be S (C+D)-E
REQUIRED BOND* AMOUNTS ARE SUBJECT TO REVIEW AND MODIFICATION BY DDES
Page 9 of 9 Unit prices updated: 02/12/02
Check out the DDES Web site at www.kinpcounty.goy/permits Version: 11 /26/08
li-wks-sbq.xls Report Date: 12/02/2008