Limited Notice to Proceed
Permit Application :Date:
# BLD20061302 / BLD20061303 3/3/08
Project Name/Address:
Emerson – Culver SFRs / 7211 & 7217 Meadowdale Beach Road
Contact Person/Address, Fax or E-mail:
Milo Sligar, mlsligar@aol.com / Michael Painter, fax 360-588-4526
Reviewer: Ed Sibrel Division:
Engineering
A limited Notice to Proceed is granted for the establishment of clearing limits, TESC, preliminary storm
drainage and construction access for the above noted project. Further construction approval is subject to
the Engineering Program Manager, and is not implied in this notice.
Prior to construction, post notice of pending activity per item #3 of Construction Sequence.
1. In order to establish the frontage storm tightline and install construction access, permission granted to
divert the incoming stormwater in the ditch from the SE corner of the lot across the street into the ditch
along the south side of the roadway. The conveyance hose shall be protected by temporary ramps, the
ramps securely attached to the road surface, and signed both at the ramp and approaching the ramps a
distance of 200 feet in both directions. During this construction, hay bales configured into weir systems
shall be installed per plan to ensure that runoff from the property shall be below the state-established
maximum turbidity levels. Temporary erosion control shall be maintained on the downhill side of the
construction entrance at all times until the entrance is completed.
2. The clearing and grading limits shall be identified, flagged, and fenced. The silt fence along the lower
perimeter of the property shall be installed. Take care the the fence does not excessively channel or
concentrate runoff. Judicious use of quarry spalls, sand bags, and other energy dissipators can
accomplish this.
3. Perimeter protection and source-control interception of incoming surface water per item #7 of
Construction Sequence shall be installed and clean water diverted around the site.
4. Sediment weirs, ponds, and traps shall be in place prior to clearing / grubbing, It is highly
recommended to leave as much ground as possible in its natural state until immediately prior to its use in
construction. Proper phasing of construction activities is important. It’s easier to keep water clean than
to get it clean.
5. Follow Construction Sequence from Item #8 onward, subject to the approval of the Engineering
Program Manager.