Meiers pre-con 08.26.2013.pdfI WIN i ., i i mkm 1901h St SSV Retaining Wall Proicct Monday, August 26, 2013, gam 1. Sign in and self -introduction 2. Roles / responsibilities of City Representatives and Consultants • Project Coordiantor — Jerry Shuster, P.E.- Primary Point of contact ® Rob English, P.E. City Engineer, Project Oversight • Tod Moles — Street/Storm Manager, Road Closures, detour signs, stormwater system, road condition. • Jeanie McConnell - Engineering Program Manager, Haul routes, erosion control • JoAnne Zulauf — Engineering Technician HI, erosion control, project inspections • Bryan Hawkins, HWA GeoSciences - soldier pile wall inspections/oversight 3. Roles I responsibilities of Meiers Representatives and Consultants • Geotechnical Consultant — Gary Flowers • Project General Contractor — Cascade Utilities • Project Driller — Versatile Drilling ® Other 4. Designation of Emergency Contacts for both parties and exchange of contact information V kswkk r, 5. Settlement Agreement — Responsibilities of Each Party • Items 4f, 4g, 4h, 4i, and 4e are applicable during construction for Meiers representatives. • Items 5b, 5d, 5h, 5i specifically relevant to the City are applicable during construction for the City 6. Traffic Control. and Safety • City to close road and put up detour signs • City to notify potentially affected residents (300+) • City will notify Police, Fire, Edmonds School Dist., Kings School, Post Office, and garbage haulers. • Contractor shall maintain access to homeowners on 190"' St SW (8). • Contractor shall maintain access for Emergency Vehicles in 190`11 St. • Contractor Haul Routes. Many roads into the City have weight restrictions. Discuss potential haul routes and turnaround areas. • Laydown / stockpile areas Precoxnstr action Conference ® Utility locates —City has storm, sanitary sewer and stormwater lines on street 7. Environmental Concerns Erosion sediment control during construction (Settlement Agreement item 4i) including catch basin socks on 190"' St adjacent to and downstream of the construction area. ® Watch weather forecast to dictate for further erosion control Final Site Stabilization (Settlement Agreement item 4e). 8. Construction Schedule/ Inspection Frequency • Contractor Proposed schedule ® City proposed inspection frequency ® City noise ordinance / working hours 9e Other Items Preconstruction Mtg Ageada.docx 2 Meiers Soldier Pile Wall —19016 — 94`" Ave W Precon — August 26, 2013 Project construction and road closure estimated to be September 11 through October 4cn Week of 8/26 —City will locate storm line, specifically near upper end of wall (nearest Meiers driveway). City will run a tracked camera with sonde through the storm line to locate it along the proposed wall location. Tod Moles will meet with Gary Flowers to discuss storm location, pile spacing and potential impacts. Jeanie McConnell/JoAnne Zulauf will issue and email ROW construction permit for project. ROW permit to include traffic control and haul/route plans. 9/10 — City will setup area with signs, etc. in preparation for 9/11 AM road closure of 190t" 9/11-- Road closure to be in place — local access to be maintained above and below the project limits. Cascade Utilities (Bob Bailie) will start prep and excavate at toe of wall. Filter socks will be installed in catch basins. Exposed soils will be covered with fabric. Existing pavement to protected (steel plates, rubber mats, etc.) to prevent equipment from damaging pavement. 9/16— Versatile Drilling (John) to start. Wall install expected to take 3-4 days. Frontier has overhead lines in the way. Contractor to coordinate with Frontier. HWA will inspect wall install including drainage behind wall. City representative (JoAnne Zulauf) will make daily visits to the site. City will also inspect storm connection to catch basin. Refer to Settlement Agreement and Release for project responsibilities. rr P11 `., V e IIII u l .,d 2 s i.. ,....„ , pper�, ry�y�� v.p C3ro YJJJ(Y W rypm ..... ...,,. ____. __. ._............. ___ ........ z