Northpoint - RFI 063 - SW-4 Drag Straps at Level 2_SA.pdfSALUS HEALTHCARE ARCHITECTURE November 27, 2018 Leif Bjorback, Kristin Johns City of Edmonds, Development Services Department 121 5th Ave N Edmonds, WA 98020 Subject: Northpoint Recovery, Remodel of Edmonds Facility Request for adding Drag Straps at Level 2 Permit #BLD2018-0447 RE: RFI-063 To Leif Bjorback and Kristin Johns, Venture Construction will be meeting with either Milton Thompson or Eric Carter to review attached new detail #12/SKS-10 and Elevation-4 for the second floor drag straps. The drag struts occur along Gridline-3 at the north and south sides, see attached partial plan for locations. In the original design, the hold downs were on the underside of the soffit and exposed to the exterior. Instead, drag straps were added on top of the second -floor plywood (which will be covered by flooring material) We are requesting one of the site inspectors approve this detail. Thank you for your consideration. Douglas McNutt Principal — Salus Architecture Encl: Structural Detail #12/SKS-10, Elevation-4 and Partial Structural Floor Plan S-102 C: R. David Frum, FAIA, ACHA ZA16029 Northpoint Recovery\Docs\06.01-MunicipalReview\AFTER PERMIT ISSUED Request for Clarification to City_10-24-18\RFI-063 SW-4 Drag Struts at Level 2\Northpoint - SW-4 Drag Straps at Level 2.docx 1402 Third Ave, Suite 200 / Seattle, WA 98101 / T 206.652.0722 / F 206.340.2266 / www.salus.archi Mr. Leif Bjorback, November 27, 2018 Page 2 Original Details on 4/S-221 Shear Wall Elevations that is cart of the permit set: Drawing sheet S-102 calls for tea locations of continuous 8"x16" drag strut with 2-HDU11 just west GL-3 & GL-6 at Level 2. These drag struts are shown to terminate at GL-A & GL- J. Terminating these drag struts at these two identified grid lines would expose the hold downs below the Level 2 exterior soffit area. A B C 8' 2'-4'' 15'-8" DRAG STRAP 3 ;W9 G H J 2'_8" 2'_A$ ROOF-RIDG� 24' - 7 3/4" ' R F 23' - 10" 3 2-HDU11 LEVEL 12'-0" Mr. LeifEjorback, Novernber27,2[q8 Page Revised Details on 4/S-221 Shear Wall Elevations and New Detail 12/S- | Wood Framing Details: Attached detail #12/SK3'10and E|evaton'4show drag strut hold-downs relocated inside the exterior wall with steel straps at each end - above the second level plywood. Partial Structural Floor Plan S-102 locates the detail. This has been signed by Greg Lee (ABKJ structural engineer ofrecord). __--------------- W�tILA N� 0IM Ji W W- LL N _ W N co O Q 0 n Q ry U) ry Z O Q w J W ABKJ I Andersen Bjornstad Kane Jacobs Consulting Civil and Structural Engineers 1402 Third Avenue, Suite 200 1 Seattle, Washington 98101 206.340.2255 phone 1206.340.2266 fax www.abkj.com Northpoint RecoverT I y RFI #063 RESPONSE Partial Elevation-4/S-221 Project number 18003.00 S KS-09 Date 11/21/18 Drawn by Checked by GJL Scale NONE ►�OORY r L-K E) PLWD DECK E) TJI JST 16 GA x 1 1/4" W DRAG STRAP PROVIDE WEB STIFF TO MATCH TJI FLG THK 8x16 DRAG STRUT BLKG NOTES: DRAG STRAP NAILING TO BE 20-10d @ 1 AVE OC AT EACH END OF THE DRAG STRAP, WITH MAX 12" SPACING IN BETWEEN. 12 SW-4 LEVEL 2 DRAG STRAP RFI #063 RESPONSE ABKJ1 Northpoint New Detail 12/S-582 Andersen Bjornstad Kane Jacobs Project number 18003.00 Consulting Civil and Structural Engineers Recovery T I Date 11 /21 /18 S KS — 1 0 1402 Third Avenue, Suite 200 � Seattle, Washington 98101 206.340.2255 phone 206.340.2266 fax Drawn by www.abkj.com Checked by GJL Scale NONE