NWC_variance_signed.pdfCITY OF EDMONDS DAVE EARLING
MAYOR
CITY HALL • THIRD FLOOR
121 5TH AVENUE NORTH • EDMONDS, WA 98020 • (425) 771-0247 • fax (425) 771-0252
www.edmondswa,gov
4) C. 18°d OFFICE OF THE MAYOR
September 10, 2012
Warren W. Moore, VP of Operations
Northwestern Construction of Washington, Inc..
PO Box 2522
210 N. Helena St.
Spokane, WA 99220-2522
RE: ECC 5.30.120.C.2 —Variance to work extended hours
Dear Mr. Moore,
Regarding your written request dated September 7, 2012, 1 will allow Northwestern Construction a
variance to work extended hours so that the Westgate Elementary Reroofing project can be completed
on time. The variance shall be in effect starting today, Monday, September 10, 2012 and go through
Sunday, September 16, 2012. During that time Northwestern Construction will be allowed to work until
8 pm on weekdays and from 10 am — 6 pm on Sunday.
Per ECC 5.30.120.C.2 Edmonds City staff will notify all residents within 300' of the project site about the
variance. Northwestern Construction will be responsible for notifying the Police Department and for the
at -site posting.
Please be advised that I am granting the maximum allowable variance under ECC 5.30.120.C.2 which is
seven days.
Sincerely,
David. O. Earling
Mayor
cc: Michael Clugston
• Incorporated August 11, 1890 •
Sister City - Hekinan, Japan