Plan review comments for Barley & Maize 8-9-18.doc
Plan Review Comments
Plan Check #: BLD20180940 Date: August 9, 2018
Project Name / Address: Barley & Maize / 525 Main St. Edmonds
Contact Person / Email: Venus Forteza / maizeandbarley@gmail.com
Reviewer: Les Krestel Division: Wastewater Treatment Plant / Pretreatment
The subject application has been reviewed but cannot be completed until the following items have been addressed/completed.
Is the prep sink to the left of the 3-comp sink a veg prep or meat prep sink?
There is no dishwasher. Is this correct?
These fixtures, if applicable, must be connected to the HGI:
Wok - if any
3 comp sink
Meat prep sink
Prewash sink (pre dishwasher)
Do not connect these to the HGI:
Mop Sink
Vegetable prep sink
Hand sinks
Dishwasher
Floor drains
Be sure to leave sufficient space above the HGI for removing the lid during GT maintenance.
A maintenance log or manifest will be posted on a wall near the HGI and will be filled out at each cleaning or pump out by the vendor or whoever performs this maintenance.
Please respond to the questions by email and if I may be of any assistance or if you have any questions please email or call the numbers below. Thank you.
Les Krestel
City of Edmonds Pretreatment Technician
Office: (206) 672 5755
Cell: (206) 595 3117
les.krestel@edmondswa.gov
City of Edmonds Wastewater Pretreatment Program
200 2nd Ave S., Edmonds, WA 98020
Office: (425) 672-5755 Mobile: (206) 595-3117