pln20120046-Engineering Decision-Final_Plat.pdfCITY OF EDMONDS
ENGINEERING DIVISION
Date: April, 3, 2014
To: Jen Machuga, Associate Planner
From: Jeanie McConnell, Engineering Program Manager
Subject: PLN20120046, Niebrugge 2 lot Short Plat - Final Decision
22301 95th Pl W
The Engineering Division has found that the subject 2-lot short plat meets the requirements
established for civil subdivision improvements in accordance with Edmonds Community
Development Code (ECDC) 20.75 and is approved and authorized for recording.
Civil construction plans were submitted to the Engineering Division on May 6, 2013 and
approved for construction on November 8, 2013 consistent with ECDC 20.75.120.
Civil construction improvements listed as conditions of approval in attachment 11 of the staff
report and as shown on the approved civil construction plans have not yet been constructed in
their entirety. Consistent with ECDC 20.75.130, a performance bond has been posted as
surety that these improvements will be completed within 12 months following recording of
the plat. While many of the improvements have been completed, a performance bond was
submitted by the developer and accepted by the City on November 25, 2013 reflecting the
total cost to construct all required improvements in the amount of $41,117.24.
The subject development did not include grants of easements to the City or street dedications.
Thank you.
City of Edmonds