Pre-Con Meeting-05.19.10.pdfCITY OF EDMONDS MTG DATE: May 19, 2010 PRE -CONSTRUCTION MEETING Subdivsions, Multi -Family, Commercial TIME: 8:30am Project Name: Hershman Site Address: 2010183rd Ave W Developer/Owner: Gene Kulinovsky — ph. 425.444.1575 e-mail: to@myestore.com Contractor: Andrew Shubin — AAA NW Construction Inc Project Contact/Phone #/Fax #: ph. 253.820.2152 e-mail: aaanw@hotmail.com Subdivision Permit # : PLN20070062 Right -of -Way Permit #: ENG20100214 Single Family Building Permit #: BLD20100166 Side Sewer Permit #: ENG20100215 Engineering representative at meeting: Jeanie McConnell, Engineering Program Manager Plans on Site: Approved Civil plans for subdivision, Approved plans for single family residence INSPECTIONS — GENERAL INFO: Engineering Inspection Line: 425-771-0220, ext. 1326 • Requests for final engineering inspection must be made 48 hours in advance. All other engineering inspection requests must be made prior to lam each workday morning to receive an inspection that day. • Contractor/Developer must call for inspections. Leave detailed information on the inspection request line stating the work planned for the day. The inspector will try to time inspections in conjunction with the construction activity for the day whenever possible. Call the Development Services Department at 425-771-0220 and inform the front desk of inspection cancellations. Do not call the inspection line to cancel an inspection request for that day. • City of Edmonds inspectors will provide inspections as requested and may stop by periodically as deemed necessary. • Special inspections performed by licensed engineers/engineering firms does not eliminate the requirement to have an inspection performed by a City inspector. All test reports created by the special inspector must be provided to the City within one week of testing. • All sections of pipe are to be inspected after installation and prior to backfill or as determined by inspector on a project specific basis. • All connections (i.e. Joints, Tees, CB's, MH's, etc.) and thrust blocks must be inspected prior to backfill. Pre -Con Meeting, Page 1 of 3 Revised 8/26/04 ® Mobilization and Erosion Control City of Edmonds Standard Details: ELL, E1.1.1, E 1.2, E1.3, Filter fabric fence, quarry spall rock construction entrance, filter socks in CB's, sediment pond, dust control, covering of stockpiles, etc. All erosion and sedimentation control measures are to be implemented at the start of the project and shall be maintained for the duration of the project. Erosion control measures shall remain in place until all exposed soils are vegetated. Exposed soils shall be covered within 2 days during the winter months (Oct. to April) and 7 days during the summer months (April to Oct). Existing paved driveway on north side of property may suffice as construction entrance depending on condition of on -site soils after driveway grading beyond the asphalt is complete. Landslide buffer on south side of property to be delineated by orange barrier fence. All materials & equipment shall be kept on site. ® Tightline Inspection for positive flow or slope required per plans, approved material type, proper bedding, etc. ® Footing Drains The footing drain shall not connect to the storm detention system. Connection for the retaining wall drainage system shall be made to the outfall side of the detention control structure. The house foundation drains shall be directed to an on -site drywell, minimum size of 3' x 3' x 3' or as recommended by geotech. ® On -Site Drainage Detention System Construct per approved plans. Bed in pea gravel or crushed rock to springline (midline pipe). Verification of control structure orifice's required prior to installation. Mudding required inside and out at all pipe connections to CB's and MH's as well as each riser and pick holes. CMP can be replaced by N-12 if contractor chooses. Storm force line to be located entirely on private property. Catch basin to be set on private property, at property line to provide transition point between force line & gravity. ® Off -Site Drainage System Two catch basins to be installed in the right-of-way. One CB will be nearside in the new gutter flow line. 8" DIP to be run across 83rd Ave W to another new CB that is to be set on the existing City system. Hershman SP — 20101 83`d Ave W Page 2 of 3 Pre -Con Meeting 05.19.10 ® Sanitary Sewer —lateral / side sewer Proposal is to connect to 6" sanitary sewer lateral that serves existing home. Sewer force line for new home shall transition to a gravity line, per City standards, on private property. Core drill, Romac inserta-tee - inspection required at time of core drill; coupon to be verified. ® Water System — domestic service line Contact City of Edmonds Public Works Department to install new water service from City main to meter (425.771.0235). Contractor shall stake desired meter location and elevation. ® Form Inspections Contractor to schedule a separate pre -con meeting with the Engineering inspector regarding curb, gutter and sidewalk installation. Curb/gutter and sidewalk form inspections required prior to pour. City inspector must give approval of forms before pour. Monolithic pours are not permitted. ® Traffic Control Traffic Control plans must be approved for use prior to implementation. Approved plan and designated haul route to be followed. Certified flaggers required. ® Asbuilts Asbuilt of all improvements to be provided to the City of Edmonds prior to receiving project final. Electronic drawings of asbuilts to be submitted. ® Trench Patch/Compaction Compaction tests required in City right-of-way. 95% compaction must be met and reports must be submitted to the City prior to paving. CDF is not an approved backfill material. ® Noise Restrictions Construction hours are M-F, 7am-6pm and Saturdays, 10am-6pm. No work Sundays and Federal Holidays. Comments: • Approved plans for single family residence and subdivision indicate existing trees along north property line are to be maintained, but plans also indicate construction of a retaining wall and driveway in this area. Developer is to discuss situation with City Planning Division to determine if tree removal will be acceptable. • Engineering Inspector Contact Info: O Jeanie McConnell — 425.771.0220 x1338 O JoAnne Zulauf — 425.771.0220 x1324 O Jennifer Lambert — 425.771.0220 x1321 Hershman SP — 20101 83`d Ave W Page 3 of 3 Pre -Con Meeting 05.19.10