EDMONDS WESTGATE — PROJECT SCHEDULE — 8/2/16
SCHEDULE - ADR + SEPA
8/10/16
Submit pre -application to city
8/31/16
Pre -application to take place within (3) weeks of submittal
,4f8t11; 7�/
Pre -application meeting
(only occur @ 1:30 and 3:00 every Thursday)
9/9/16 - 9/21116
Prepare ADR package + SEPA checklist
9/22/16
Submit ADR package + SEPA checklist
11/1/16
28-day completeness review. City will notify applicant.
11116/16
ADR meeting scheduled (15'/3'd Wed. of the month - see below)
12/7/16 OR 12/21/16
ADR meeting date (2 meeting minimum due to public concern)
3/1117 OR 3/15/17
2"d ADR meeting
4/1/2016
Closeout ADR + SEPA checklist
SCHEDULE - BUILDING PERMIT:
9/22/16 - 1/18/17
Prepare building permit submittal
1/20/17
Submit building permit to City
1/23/17 - 3/31/17
City of Edmonds to review initial submittal (-50 days)
4/3/17
Round I comments from City of Edmonds complete
4/4/16 - 4/18/17
Design team to work on comments (10 days)
4/19/17
Resubmit Round I building permit comments to City
4/20/17 - 6/6/17
City of Edmonds review Round I corrections (-35 days)
6/9/17
Round II comments from City of Edmonds complete
6/12/17 - 6123/17
Design team to work on comments (10 days)
6/26117
Resubmit Round II building permit comments to City
6/27/17 - 7/24/17
City of Edmonds to review Round 11 corrections (-20 days)
7/24/17 - 8/4117
Permit prepped for issuance (-10 days)